12-01 Scope of Work 2026-05-18 (Updated).pdf
PDF 181 KB Posted
- Solicitation number
- 26-096
- Issued by
- Marion County, Florida
About this file
This Scope of Work document pertains to a road reclamation and resurfacing project in Florida for Silver Creek and Silver Creek 1st Addition. The project encompasses approximately 0.91 miles of minor local road sections and includes roadway preparation, shoulder removal, minor clearing and grubbing, limerock importation to establish a 2% roadway slope, reclaiming and resurfacing, temporary and permanent thermoplastic striping, and stabilization of disturbed areas. The contract term is 60 calendar days from the issuance of the Notice to Proceed, with all work except thermoplastic striping required to be completed within the first 30 calendar days. Thermoplastic striping placement comprises the final 30 calendar days of the contract. Liquidated damages will be assessed for any incomplete contract items, excluding thermoplastic striping, after the initial 30-calendar-day period. The contracting authority strongly recommends that contractors visit the project work location prior to submitting a bid to ensure comprehensive cost estimates and project understanding.
The document does not contain specific pricing terms, set-aside information, incumbent contractor details, funding sources, or other financial requirements in the provided content.
View the file
Other files
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Scope of Work
DESCRIPTION OF PROJECT
This project involves reclaiming and resurfacing of approximately .91 miles of minor local road sections in Silver Creek and Silver Creek 1st Addition. Reclaim and resurface work involves roadway prep, shoulder removal, minor clearing and grubbing, importing limerock to re-establish 2% roadway slope, reclaiming and resurfacing, temporary striping, permanent thermoplastic striping, and stabilizing all areas disturbed during construction.
CONTRACT TERM
This contract will be in effect for 60 calendar days from the date of the NOTICE TO PROCEED. The NOTICE TO PROCEED will not be issued until all required documentation is received by the COUNTY. The last 30 calendar days of the contract is to accommodate the placement of thermoplastic striping only. All other contract related work must be completed within 30 calendar days. Liquidated damages will begin to be imposed if there are any outstanding contract items remaining incomplete except for thermoplastic striping after 30 calendar days.
PRIOR TO SUBMITTING BID
It is in the CONTRACTOR’s best interest and highly recommended for CONTRACTOR to visit the project work location before submitting a bid.