This is an Invitation for Bids (IFB27-30) issued by the Incorporated County of Los Alamos, New Mexico, for two construction projects: the NM4 Crossing and Multi-Use Trail Project (CN5101730) and the Pinon School Trail Project (CN5101970). The projects involve construction of approximately 2,500 feet of new multi-use trail alignment and 3,500 feet of reconstructed multi-use trail alignment along NM4 between Sherwood Boulevard and La Vista Drive, as well as installation of a Pedestrian Hybrid Beacon (HAWK Signal) crosswalk across NM4 approximately 600 feet east of La Vista Drive. Additionally, the Pinon School Trail will be rehabilitated from Pinon Park to Grand Canyon Drive with ADA compliance upgrades. A non-mandatory pre-bid conference is scheduled for November 17, 2026, at 11:00 a.m. at Los Alamos County Fire Station 3 in White Rock, New Mexico. Bids are due by 2:00 p.m. Mountain Standard Time on December 15, 2026, through the County's electronic Procurement Portal. Bid award is anticipated for January 5, 2027, with a Notice to Proceed on January 20, 2027. Substantial completion is targeted for November 20, 2027, and final completion by December 31, 2027. The contract is subject to a partial winter suspension.

Bidders must submit a bid security equal to five percent of the total bid amount in the form of cash, certified checks, or bid bonds. The project is wholly or partially funded with federal funds administered by the New Mexico Department of Transportation (NMDOT) through subrecipient grant agreements, and all contractors must comply with federal grant requirements including Davis-Bacon Act wage rates, Buy America requirements, and Title VI civil rights provisions. No specific set-asides for disadvantaged business enterprises or other categories are identified in this solicitation. The County reserves the right to accept any bid and reject any or all bids. All work must comply with the 2019 Edition of the NMDOT Standard Specifications for Highway and Bridge Construction, and contractors must obtain all necessary permits, including traffic permits, excavation permits, and Stormwater Pollution Prevention Plan (SWPPP) notice of intent. Performance and labor-material bonds equal to one hundred percent of the contract amount are required upon award.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Invitation For Bids (IFB)

Incorporated County of Los Alamos Procurement Division

101 Camino Entrada, Building 3 Los Alamos, NM 87544

NOTIFICATION REGARDING SUBMISSION PROCESS AND REGISTRATION INSTRUCTIONS

The Incorporated County of Los Alamos (“County”) has recently implemented a new on-line eProcurement portal. This new platform, Euna Procurement powered by Bonfire, provides the County’s electronic Bid and Proposal process (“County’s Procurement Portal”). It is where the County will post solicitation opportunities, including Invitation for Bids (IFB), Request for Proposals (RFP), Request for Qualifications (RFQ) and Request for Information/Interest (RFI). The County’s Procurement Portal will streamline the County’s Bid process for Bid or Proposal submission, acceptance, evaluation, and award. For vendors, the County’s Procurement Portal will enhance communication, allow for fast and accurate Bids and Proposals, and provide automatic notification about projects.

Registered vendors will view and submit Bids and Proposals electronically. The past practice of submitting electronic Bids and Proposals by email or submitting paper Bids and Proposals is being phased out. If you are seeing this notification in a solicitation document, submissions will be accepted ONLY electronically through the County’s Procurement Portal for this solicitation. It is every Offeror’s responsibility to read, understand, and submit Bids and Proposals in accordance with the instructions provided in and specific to each solicitation document.

Required Action: Please register as a vendor on the County’s Procurement Portal by visiting https://losalamosnm.bonfirehub.com and click on “Register”. Registration is free and only takes a few minutes. Please be sure to select the applicable NIGP: The Institute for Public Procurement (“NIGP”) Commodity Codes for your business when you are prompted so that you can receive notification of recommended opportunities when they are sent out by the County to the NIGP Commodity Codes you have selected.

Already Have a Bonfire Vendor Account? If you already have a Bonfire vendor account and are already registered for another agency’s portal, you will still need to visit the County’s Procurement Portal at https://losalamosnm.bonfirehub.com and click on “Log In” to provide County-requested information, view open opportunities, receive opportunity notifications, and submit Bids and Proposals through the County’s Procurement Portal. You will be able to manage the multiple agencies with whom you do business through the button labelled “My Supplier Hub” in your Bonfire account.

For Bonfire Support, visit the Vendor Help Center at https://vendorsupport.gobonfire.com where you can view support articles and videos and search FAQ’s on all aspects of Bonfire. For personal assistance, you can email Support.Bonfire@eunasolutions.com . Support is available Monday to Friday from 6:00 a.m. to 6:00 p.m. Mountain Time.

https://losalamosnm.bonfirehub.com/ https://vendorsupport.gobonfire.com/ mailto:Support.Bonfire@eunasolutions.com

IFB27-30 Incorporated County of Los Alamos NM4 Crossing and Multi-Use Trail Project (CN5101730) and Pinon School Trail (CN5101970)

INCORPORATED COUNTY OF LOS ALAMOS

BID AND SPECIFICATIONS

NM4 Crossing and Multi-Use Trail Project (CN5101730)

And Pinon School Trail (CN5101970)

INVITATION FOR BIDS NO. IFB27-30

Advertised on November 10, 2026

Prepared by:

Bryan Romero

Reviewed by:

Keith Wilson, P.E., Deputy Public Works Director

Authorized for release by:

Eric Martinez, P.E., Public Works Director

Docusign Envelope ID: D5752F70-C4BE-872E-83A1-DEEB843DAAE9

1.0 BIDDING PHASE --------------------------------------------------------------------------------- 10

1.1 Invitation for Bids ------------------------------------------------------------------------------------------------------------------10

1.2 Summary of Work ------------------------------------------------------------------------------------------------------------------13

1.3 Requirements for Bidders -------------------------------------------------------------------------------------------------------15

1.3.1 Bid Evaluation Criteria ------------------------------------------------------------------------------------------------------15

1.3.2 Required Bid Response Documents -------------------------------------------------------------------------------------16

1.3.3 The Bidder’s Bid Response Documents --------------------------------------------------------------------------------16

1.3.4 Liquidated Damages for Failure to Enter into Contract ------------------------------------------------------------17

1.3.5 Conditions of Work ---------------------------------------------------------------------------------------------------------17

1.3.6 Addenda and Requests for Interpretation ----------------------------------------------------------------------------17

1.3.7 Power of Attorney -----------------------------------------------------------------------------------------------------------18

1.3.8 Obligation of Bidder --------------------------------------------------------------------------------------------------------18

1.3.9 Safety Standards and Accident Prevention ---------------------------------------------------------------------------18

1.3.10 Substitutes or Brand Name or Equal ------------------------------------------------------------------------------------18

1.3.11 Bids to Remain Subject to Acceptance ---------------------------------------------------------------------------------19

1.3.12 Withdrawal of Bids ----------------------------------------------------------------------------------------------------------19

1.3.13 Acceptance or Rejection of Bids -----------------------------------------------------------------------------------------19

1.3.14 Award --------------------------------------------------------------------------------------------------------------------------19

1.3.15 Registration of Contractors and Subcontractors --------------------------------------------------------------------19

1.4 Notices to Contractors ------------------------------------------------------------------------------------------------------------20

1.4.1 Applicable Law ---------------------------------------------------------------------------------------------------------------20

1.4.2 Gross Receipts Tax ----------------------------------------------------------------------------------------------------------20

1.4.3 Minimum Wage Rates ------------------------------------------------------------------------------------------------------20

1.4.4 Work Conditions -------------------------------------------------------------------------------------------------------------20

1.4.5 Public Information ----------------------------------------------------------------------------------------------------------21

1.4.6 Performance and Labor and Material Bonds Requirements ------------------------------------------------------21

1.4.7 NMDOT Standard Specifications ---------------------------------------------------------------------------------------------21

1.4.8 Supplemental Technical Specifications --------------------------------------------------------------------------------22

1.4.9 Abandoned Utilities ---------------------------------------------------------------------------------------------------------22

1.4.10 Coordination with County Gas, Water, Sewer (GWS) & Electric Operations ---------------------------------22

1.4.11 Time of the Essence ---------------------------------------------------------------------------------------------------------23

1.4.12 Potholing ----------------------------------------------------------------------------------------------------------------------23

1.4.13 Permits, CPM Schedule, and Roadway Material Submittals --------------------------------------------------------23

1.4.14 Geotechnical Investigation Report --------------------------------------------------------------------------------------24

1.4.15 Disposal of Excess Material -----------------------------------------------------------------------------------------------24

1.4.16 Storm Water Control -------------------------------------------------------------------------------------------------------24

1.4.17 Field Offices -------------------------------------------------------------------------------------------------------------------24

1.4.18 Security ------------------------------------------------------------------------------------------------------------------------25

1.4.19 Maintenance During Construction --------------------------------------------------------------------------------------25

1.4.20 Snow Removal and Ice Control-------------------------------------------------------------------------------------------25

1.4.21 Preconstruction Walk-Through ------------------------------------------------------------------------------------------25

1.4.22 Cast Iron Truncated Domes – ADA Detectable Warning Surfaces -----------------------------------------------26

1.4.23 Traffic Control Supervisor -------------------------------------------------------------------------------------------------26

1.4.24 Monthly Asphalt Binder Price Adjustment Procedures ------------------------------------------------------------26

1.4.25 ADA Construction Inspection Procedure [April 6, 2023] -----------------------------------------------------------27

1.4.26 Davis Bacon Act (DBA) Conformance Requirements [January 1, 2019] ----------------------------------------29

1.4.27 Buy America [January 1, 2019] -------------------------------------------------------------------------------------------31

1.4.28 Federal Requirements [October 23, 2023] ----------------------------------------------------------------------------31

1.4.29 Return of Lobbying Disclosure [January 1, 2019] --------------------------------------------------------------------77

1.4.30 Professional Services [January 1, 2019] --------------------------------------------------------------------------------81

1.4.31 CN:5101730 & CN:5101970 Cooperation with Utilities – No Anticipated Impacts --------------------------81

1.4.32 Approved Products List (April 15, 2023) ------------------------------------------------------------------------------------82

1.5 Bid Forms -----------------------------------------------------------------------------------------------------------------------------83

1.5.1 Bid Forms (Base Bid) --------------------------------------------------------------------------------------------------------85

1.5.1.1 CN 5101730 NM4 Crossing and Multi-Use Trail Project Base Bid -----------------------------------------------85

1.5.1.2 CN 5101970 Pinon School Trail Project Base Bid --------------------------------------------------------------------91

1.5.2 Bid Forms (Bid Alternates) ------------------------------------------------------------------------------------------------93

1.5.2.1 CN:5101730 Bid Alternate #1 – NM4 All Concrete Trail ------------------------------------------------------------93

1.5.3 List of Subcontractors ------------------------------------------------------------------------------------------------------94

1.5.4 Bid Bond -----------------------------------------------------------------------------------------------------------------------95

1.5.7 Permanent Main Office Address of Company ------------------------------------------------------------------------98

1.5.8 Authorization for Verification of Information ------------------------------------------------------------------------98

1.5.9 Certificate of Contractors Registration --------------------------------------------------------------------------------99

1.5.10 Non-Collusion Affidavit -------------------------------------------------------------------------------------------------- 100

1.5.11 NMDOT Bidders Quoters for DBDE ------------------------------------------------------------------------------------ 101

2.0 AWARD PHASE --------------------------------------------------------------------------------- 102

2.1 Award Forms ---------------------------------------------------------------------------------------------------------------------- 102

2.1.1 Notice of Award ----------------------------------------------------------------------------------------------------------- 102

2.1.2 Receipt of Notice of Award --------------------------------------------------------------------------------------------- 104

2.1.3 Performance Bond -------------------------------------------------------------------------------------------------------- 105

2.1.4 Payment (Labor and Materials) Bond -------------------------------------------------------------------------------- 108

2.1.5 Insurance Requirement -------------------------------------------------------------------------------------------------- 110

2.1.6 Contract ---------------------------------------------------------------------------------------------------------------------- 112

3.1 Construction Phase Related Forms ------------------------------------------------------------------------------------------ 120

3.1.1 Contractor Personnel Information ------------------------------------------------------------------------------------ 120

3.1.2 Notice to Proceed --------------------------------------------------------------------------------------------------------- 121

3.1.3 Acceptance of Notice to Proceed -------------------------------------------------------------------------------------- 122

3.1.4 Application and Certification for Payment Part 1 ----------------------------------------------------------------- 123

3.1.5 Application and Certification for Payment Part 2 ----------------------------------------------------------------- 124

3.1.6 Affidavit of Payment and Release of Liens -------------------------------------------------------------------------- 125

3.1.7 Field Order ------------------------------------------------------------------------------------------------------------------ 127

3.1.8 Change Order --------------------------------------------------------------------------------------------------------------- 128

3.0 CONSTRUCTION PHASE ---------------------------------------------------------------------- 133

3.2 Conditions of the Contract - General Conditions ------------------------------------------------------------------------ 133

3.2.1 Definitions ------------------------------------------------------------------------------------------------------------------- 133

3.2.2 Additional Instructions --------------------------------------------------------------------------------------------------- 136

3.2.3 Schedules, Reports and Records --------------------------------------------------------------------------------------- 138

3.2.4 Shop Drawings and Submittals ----------------------------------------------------------------------------------------- 141

3.2.5 Start of Various Types of Work and Management Planning ---------------------------------------------------- 141

3.2.6 Materials, Services and Facilities -------------------------------------------------------------------------------------- 143

3.2.7 Substitutes or “Brand Name” or Equal ------------------------------------------------------------------------------- 144

3.2.8 Inspection and Testing --------------------------------------------------------------------------------------------------- 145

3.2.9 Correction of Work-------------------------------------------------------------------------------------------------------- 146

3.2.10 Patents ----------------------------------------------------------------------------------------------------------------------- 147

3.2.11 Surveys, Permits, and Regulations ------------------------------------------------------------------------------------ 148

3.2.12 Subsurface and Physical Conditions ---------------------------------------------------------------------------------- 149

3.2.13 Protection of Work, Property and Persons-------------------------------------------------------------------------- 152

3.2.14 Changes in the Work ----------------------------------------------------------------------------------------------------- 153

3.2.15 Suspension, Delay or Termination of Work ------------------------------------------------------------------------- 156

3.2.16 Subcontracting ------------------------------------------------------------------------------------------------------------- 158

3.2.17 Duties of the Contractor ------------------------------------------------------------------------------------------------- 158

3.2.18 Job Site Administration -------------------------------------------------------------------------------------------------- 159

3.2.19 Engineer’s Authority ------------------------------------------------------------------------------------------------------ 163

3.2.20 Duties, Responsibilities and Limitations ----------------------------------------------------------------------------- 164

3.2.21 Engineer’s Review of Work, Rejection of Work, Inspections, and Tests ------------------------------------- 165

3.2.22 Limitations of Authority ------------------------------------------------------------------------------------------------- 165

3.2.23 Land and Right-of-Way --------------------------------------------------------------------------------------------------- 165

3.2.24 Warranty/Guaranty ------------------------------------------------------------------------------------------------------- 165

3.2.25 Miscellaneous -------------------------------------------------------------------------------------------------------------- 167

3.2.26 Dispute Resolution, Applicable Law, and Venue ------------------------------------------------------------------- 167

3.2.27 Examination of Records Provisions ----------------------------------------------------------------------------------- 168

3.2.28 American with Disabilities Act Compliance ------------------------------------------------------------------------- 168

3.2.29 A. Bids and Proposals are public Records --------------------------------------------------------------------------- 168

3.2.30 Wage Rate Determination ---------------------------------------------------------------------------------------------- 168

3.3 ATTACHMENTS -------------------------------------------------------------------------------- 169

3.3.1 License Agreement for Staging Area TBD ---------------------------------------------------------------------------------- 170

3.3.2 Wage Rate Information -------------------------------------------------------------------------------------------------- 176

3.3.3 Geotechnical Report ------------------------------------------------------------------------------------------------------------ 184

3.3.4 Report on Recommendations for Moving and Resetting of the Large Pottery Art Piece ---------------------- 185

3.4 SPECIAL PROVISIONS ---------------------------------------------------------------------------- 186

3.4.1 Section 605-A: Concrete Scupper -------------------------------------------------------------------------------------------- 186

3.4.2 Section 606-A: Bike Lane Divider -------------------------------------------------------------------------------------------- 188

3.4.3 Section 704-F: Bike Lane Bonded Aggregate Surfacing Treatment ------------------------------------------------- 190

3.4.4 T/LPA 100 Division -------------------------------------------------------------------------------------------------------------- 195

3.4.5 SECTION 106.12: BUY AMERICA REQUIREMENTS ----------------------------------------------------------------------- 285

3.4.6 SECTION 106-A: BUILD AMERICA/BUY AMERICA PRODUCT INFORMATION SHEET ------------------------------ 286

3.4.7 Modifying Sections 511; 532; 533; 606 ------------------------------------------------------------------------------------- 287

3.4.8 Modifying Sections 606; 701; 703; 720 ------------------------------------------------------------------------------------- 288

3.4.9 MODIFYING SECTION 303: BASE COURSE ---------------------------------------------------------------------------------- 289

303.1 DESCRIPTION ------------------------------------------------------------------------------------------------------------------- 289

303.2 MATERIALS --------------------------------------------------------------------------------------------------------------------- 289

303.3 CONSTRUCTION REQUIREMENTS ----------------------------------------------------------------------------------------- 290

303.4 METHOD OF MEASUREMENT ----------------------------------------------------------------------------------------------- 293

303.5 BASIS OF PAYMENT ---------------------------------------------------------------------------------------------------------- 293

3.4.10 MODIFYING SECTION 402: ASPHALT MATERIALS AND MINERAL ADMIXTURES -------------------------------- 294

3.4.11 MODIFYING SECTION 407: TACK COAT------------------------------------------------------------------------------------ 297

3.4.12 MODIFYING SECTION 408: PRIME COAT ---------------------------------------------------------------------------------- 298

3.4.13 MODIFYING SECTION 416: Minor Paving --------------------------------------------------------------------------------- 299

416.1 DESCRIPTION ------------------------------------------------------------------------------------------------------------------- 299

416.2 MATERIALS --------------------------------------------------------------------------------------------------------------------- 299

416.3 CONSTRUCTION REQUIREMENTS ----------------------------------------------------------------------------------------- 299

416.4 METHOD OF MEASUREMENT ----------------------------------------------------------------------------------------------- 301

416.5 BASIS OF PAYMENT ---------------------------------------------------------------------------------------------------------- 301

3.4.14 MODIFYING SECTION 423: HOT MIX ASPHALT (HMA) (MAJOR PAVING) ----------------------------------------- 303

3.4.15 MODIFYING SECTION 502: DRILLED SHAFTS ----------------------------------------------------------------------------- 306

3.4.16 MODIFYING SECTION 509: PORTLAND CEMENT CONCRETE MIX DESIGNS --------------------------------------- 307

3.4.17 MODIFYING SECTION 511: CONCRETE STRUCTURES ------------------------------------------------------------- 318

3.4.18 MODIFYING SECTION 512: SUPERSTRUCTURE CONCRETE ----------------------------------------------------------- 319

3.4.19 MODIFYING SECTION 602: SLOPE AND EROSION PROTECTION STRUCTURES ----------------------------------- 320

3.4.20 MODIFYING SECTION 603: TEMPORARY EROSION AND SEDIMENT CONTROL ---------------------------------- 323

603.1 DESCRIPTION ------------------------------------------------------------------------------------------------------------------- 323

603.2 MATERIALS --------------------------------------------------------------------------------------------------------------------- 328

603.3 CONSTRUCTION REQUIREMENTS ----------------------------------------------------------------------------------------- 329

603.4 METHOD OF MEASUREMENT ----------------------------------------------------------------------------------------------- 334

603.5 BASIS OF PAYMENT ---------------------------------------------------------------------------------------------------------- 334

3.4.21 MODIFYING SECTION 606: METAL BARRIER, CABLE BARRIER AND CONCRETE WALL BARRIER ------------- 337

3.4.22 MODIFYING SECTION 618: TRAFFIC CONTROL MANAGEMENT ----------------------------------------------------- 339

3.4.23 MODIFYING SECTION 621: MOBILIZATION ------------------------------------------------------------------------------- 340

3.4.24 MODIFYING SECTION 632: REVEGETATION ------------------------------------------------------------------------------ 342

3.4.25 MODIFYING SECTION 701: TRAFFIC SIGNS AND SIGN STRUCTURES ----------------------------------------------- 363

3.4.26 MODIFYING SECTION 702: CONSTRUCTION TRAFFIC CONTROL DEVICES ---------------------------------------- 366

3.4.27 MODIFYING SECTION 704: PAVEMENT MARKINGS -------------------------------------------------------------------- 370

3.4.28 MODIFYING SECTION 704-A: TEMPORARY MARKING TAPE ---------------------------------------------------------- 371

3.4.29 MODIFYING SECTION 704-B: RETROREFLECTIVE PREFORMED PLASTIC MARKINGS (TAPE) ------------------ 372 3.4.30MODIFYING SECTION 704-C: HOT THERMOPLASTIC MARKINGS ---------------------------------------------------- 373

3.4.31 MODIFYING SECTION 704-D: PREFORMED THERMOPLASTIC PAVEMENT MARKINGS ------------------------ 374

3.4.32 MODIFYING SECTION 706: SIGNAL AND LIGHTING SERVICE SYSTEMS -------------------------------------------- 375

3.4.33 MODIFYING SECTION 716: LUMINAIRES ---------------------------------------------------------------------------------- 376

3.4.34 MODIFYING SECTION 902: QUALITY CONTROL -------------------------------------------------------------------------- 377

3.4.35 MODIFYING SECTION 904: QUALITY LEVEL ANALYSIS (QLA) --------------------------------------------------------- 378

3.4.36 MODIFYING SECTION 905: QUALITY ASSURANCE FOR MINOR PAVING ------------------------------------------- 379

905.1 DESCRIPTION ------------------------------------------------------------------------------------------------------------------- 379

3.4.37 MODIFYING SECTION 906: MINIMUM TESTING REQUIREMENT’S (MTR’S) -------------------------------------- 385

906.1 DESCRIPTION ------------------------------------------------------------------------------------------------------------------- 385 STRUCTURE DEFINITIONS, FOUNDATION AND BACKFILL REQUIREMENTS FOR ACCEPTANCE ---------------------- 390 CHARACTERISTICS TOLERANCES ------------------------------------------------------------------------------------------------ 401 GRADATION TOLERANCES -------------------------------------------------------------------------------------------------------- 401 CONCRETE TOLERANCES -------------------------------------------------------------------------------------------------------- 402 HOT MIX ASPHALT (HMA)/ WARM MIX ASPHALT (WMA) ------------------------------------------------------------------------- 403

TOLERANCES ---------------------------------------------- 403

3.5 TECHNICAL SPECIFICATIONS ----------------------------------------------------------------- 405

3.5.1 Section 107: Legal Relations, Environmental Requirements, and Responsibility to the Public --------------- 406

3.5.2 Section 201: Clearing and Grubbing ----------------------------------------------------------------------------------------- 406

3.5.3 Section 203: Excavation, Borrow, and Embankment -------------------------------------------------------------------- 406

3.5.4 Section 207: Subgrade Preparation ------------------------------------------------------------------------------------------ 406

3.5.5 Section 303: Base Course ------------------------------------------------------------------------------------------------------- 406

3.5.6 Section 416: Minor Paving ----------------------------------------------------------------------------------------------------- 406

3.5.7 Section 502: Drilled Shafts ----------------------------------------------------------------------------------------------------- 406

3.5.8 Section 510: Portland Cement Concrete ------------------------------------------------------------------------------------ 406

3.5.9 Section 511: Concrete Structures -------------------------------------------------------------------------------------------- 406

3.5.10 Section 540: Steel Reinforcement ------------------------------------------------------------------------------------------ 406

3.5.11 Section 570: Pipe Culverts ---------------------------------------------------------------------------------------------------- 406

3.5.12 Section 601: Removal of Structures and Obstructions ---------------------------------------------------------------- 406

3.5.13 Section 602: Slope and Erosion Protection Structures ---------------------------------------------------------------- 406

3.5.14 Section 603: Temporary Erosion and Sediment Control -------------------------------------------------------------- 406

3.5.15 Section 607: Fence ------------------------------------------------------------------------------------------------------------- 406

3.5.16 Section 608: Sidewalks, Drive Pads, and Concrete Median Pavement -------------------------------------------- 406

3.5.17 Section 609: Curb and Gutter ------------------------------------------------------------------------------------------------ 406

3.5.18 Section 618: Traffic Control Management -------------------------------------------------------------------------------- 406

3.5.19 Section 621: Mobilization ----------------------------------------------------------------------------------------------------- 406

3.5.20 Section 632: Revegetation ---------------------------------------------------------------------------------------------------- 406

3.5.21 Section 662: Manholes -------------------------------------------------------------------------------------------------------- 406

3.5.22 Section 664: Landscape Planting -------------------------------------------------------------------------------------------- 406

3.5.23 Section 701: Traffic Signs and Sign Structures --------------------------------------------------------------------------- 407

3.5.25 Section 702: Construction Traffic Control Devices---------------------------------------------------------------------- 407

3.5.26 Section 704: Pavement Markings ------------------------------------------------------------------------------------------- 407

3.5.27 Section 705: General Requirements for Traffic Signal and Highway Lighting Systems ------------------------ 407

3.5.28 Section 707: Signal and Lighting Standards ------------------------------------------------------------------------------ 407

3.5.29 Section 709: Rigid Electrical Conduit --------------------------------------------------------------------------------------- 407

3.5.30 Section 710: Pull Boxes and Splice Cabinets ----------------------------------------------------------------------------- 407

3.5.31 Section 711: Wiring ------------------------------------------------------------------------------------------------------------ 407

3.5.32 Section 712: Signal Assemblies ---------------------------------------------------------------------------------------------- 407

3.5.33 Section 713: Detectors -------------------------------------------------------------------------------------------------------- 407

3.5.34 Section 714: Traffic Signal Controllers ------------------------------------------------------------------------------------- 407

3.5.35 Section 716: Luminaires ------------------------------------------------------------------------------------------------------- 407

3.5.36 Section 721: Pavement Marking Removal -------------------------------------------------------------------------------- 407

3.5.37 Section 801: Construction Staking by the Contractor ------------------------------------------------------------------ 407

3.5.38 Section 802: Post Construction Plans -------------------------------------------------------------------------------------- 407

1.0 BIDDING PHASE

1.1 Invitation for Bids

The Incorporated County of Los Alamos (“County”) reserves the right, in its sole discretion, to accept any bid and to reject any or all bids.

Bids are invited from all responsible bidders.

1. ELECTRONIC SUBMISSIONS ONLY

A full copy of the solicitation and all associated documents can be found on the County’s Procurement Portal at https://losalamosnm.bonfirehub.com/. Only Bids submitted through the County’s Procurement Portal by the Bid Due Date stated herein, or as may be modified by addendum, will be considered. Late responses will not be considered. To register to view and download solicitation documents and submit a Bid through the County’s Procurement Portal, follow the instructions on page 1 of this solicitation.

Only Bids received through the Procurement Portal prior to 2:00 p.m. MST, December 15, 2026 will be reviewed.

2. ADDITIONAL DOCUMENTS AND INFORMATION INCLUDED AS A PART OF THIS IFB

Additional documents are referenced in this IFB, which may include, but are not limited to, exhibits, attachments, links to documents online, and documents that are provided through the County’s Procurement Portal. Any such documents are considered to be a part hereof and constitute, along with this solicitation document and any addenda, the complete solicitation package. Documents required to be submitted as a component of Bidders’ Response will be noted as such in each individual solicitation posted on the County’s Procurement Portal, and Bidders will be unable to submit their Bids through the County’s Procurement Portal until all required documents and information have been uploaded or provided by Bidders.

Please also reference “1.3.3 The Bidder’s Bid Response Documents ” below.

3. GRANT RELATED INFORMATION

Federal Funding. This project is wholly or partially funded with Federal funds, which are administered by the New Mexico Department of Transportation (“NMDOT”) through the subrecipient grant agreements CN5101730 and CN5101970 between NMDOT and the County. As part of any response to this solicitation, Bidders shall affirm their ability to meet federal grant requirements contained herein. Bidders who cannot affirm ability to meet these requirements may be deemed non-responsive or non-responsible.

Federal grant requirements are provided in Section 1.4 Notices to Contractors, and Section

3.4 Special Provisions.

Incorporated County of Los Alamos Invitation for Bids Number: IFB27-30

New NM4 Crossing and Multi-Use Trail Project (CN5101730) & Pinon School Trail

(CN5101970)

Bid security in the amount of five percent (5%) of the bid must accompany the bid. Such cash, certified checks or bid bonds will be returned to all except the three finalist bidders within three days after the opening of bids. The remaining cash, checks and bid bonds will be returned promptly after the County and the accepted Bidder have executed the contract, or if no award has been made within sixty (60) days after the date of the opening of bids, upon demand of the bidder at any time thereafter, so long as Bidder has not been notified of the acceptance of Bidder’s bid.

In submitting their Bid Bond, it is not mandatory that Bidders use the Bid Bond form provided in the packet. The County strongly encourages all Contractors to use this form, but if the contractor elects not to use it, the Bid Bond must be submitted on a form acceptable in the construction industry and approved by the County Project Manager in advance of the bid due date.

A Non-Mandatory Pre-Bid Conference will be held onTuesday, November 17, 2026 at 11:00 AM both in person at Los Alamos County Fire Station 3, at 129 NM-4, White Rock, NM 87547, and via Microsoft Teams. The meeting link is provided in the Project in the Procurement Portal.

This conference is held to answer questions from the prospective bidders as well as familiarize bidders with the project. Questions regarding the meaning of plans, specifications or other documents related to the project should be submitted in writing prior to the pre-bid conference.

The County will preside at the pre-bid conference and provide for the recording and distribution of minutes. The pre-bid conference will include, but not be limited to the following:

1. Discussion of schedule for procurement, progress, values for progress payments and submittals.

2. Critical work sequencing and priorities.

3. Use of construction site premises, storage areas, office areas, security, cleaning, and

County’s needs.

4. Transmittal, review, and distribution of submittals.

5. Field decision process.

6. Maintain record documents.

7. Public Information. Optional

QUESTIONS

Any questions must be received in writing at least six (6) business days prior to the submission due date, unless otherwise stated herein or in an addendum. Questions must be submitted through the County’s Procurement Portal. Please follow the instructions on page one (1) of this document to register for the County’s Procurement Portal to submit written questions.

Bidders who submit questions via e-mail or by phone shall be redirected to submit written questions through the County’s Procurement Portal.

Bidders must submit in writing through the County’s Procurement Portal, as stated herein, any questions or requested clarification necessary for Bidder to provide a complete Response with all Bid response components and pricing included. Bidders are asked to refrain from including in Bids statements such as “more information available upon request,” “pricing to be determined,” or other similar statements. Such statements and failure of Bidder to seek clarification needed for Bidder to provide the requested information may result in a Bidder being found non-responsive or non-responsible. This in no way may be construed to conflict with County’s right to hold interviews and discussions for clarification with Bidders, as further described herein. Failure of any bidder to receive any addendum or interpretation shall not relieve such bidder from any obligation under its bid as submitted. All addenda so issued shall become part of the solicitation documents.

The County reserves the right to issue addenda to the solicitation documents including construction specifications and plans during the advertising period as provided in the solicitation documents. Bidders are responsible for determining if any addenda have been issued. The terms, bid and solicitation are interchangeable. Also, the defined terms contract and agreement are interchangeable.

1.2 Summary of Work

Incorporated County of Los Alamos Bid Number: IFB27-30

NM4 Crossing and Multi-Use Trail Project (CN5101730) & Pinon School Trail (CN5101970)

This project is issued by and under the control of The Incorporated County of Los Alamos. The contracting office is the Public Works Department. The location of the project is in the County of Los Alamos, New Mexico.

The summary of work is as follows, but is not limited to the following:

Solicitation Advertised November 10, 2026 Pre-Bid Meeting November 17, 2026 Bids Due December 15, 2026 Bid Award January 5, 2027 Pre-Construction Meeting January 19, 2027 Notice to Proceed January 20, 2027 Substantial Completion Date November 20, 2027 Final Completion Date December 31, 2027 The dates listed above are tentative and subject to change.

Work to achieve Final Completion, including all Operations and Maintenance Manuals, final Certified Payrolls, As-built drawings, Warranty Certificates, Final Inspection by the Manufacturer and approval of the Installation, and other close-out documents by December 31, 2027.

Part 1 Project Scope of Work:

NM4 Crossing and Multi-Use Trail Project (CN5101730): This project includes the construction of both new and reconstructed multi-use trails along NM4 between Sherwood Blvd. and La Vista Dr. and within Piñon Park in White Rock. The planned improvements will enhance connectivity and safety for pedestrians and cyclists. The project includes approximately 2,500ft of new multi-use trail alignment and approximately 3,500ft of reconstructed multi-use trail alignment along NM4 and within the County owned Pinon Park. Additionally, a new enhanced mid-block crosswalk with a Pedestrian Hybrid Beacon (aka HAWK Signal) will be installed across NM4 approximately 600 feet east of La Vista Drive.

Pinon School Trail (CN5101970): This project includes the rehabilitation of the Pinon School Trail connection from Pinon Park to Grand Cayon Drive and access to the newly constructed Pinon School. This will also bring the existing trail into ADA compliance.

Part 2 Work Sequence:

A. The Contractor shall prepare and submit for the Owners approval a work sequence plan.

Once approved, the contractor shall execute the plan and resubmit for the owner’s approval any revisions needed to this plan.

B. Contractor shall test all materials, parts and equipment installed as part of this project;

start up the system, before Final Acceptance by Owner.

Part 3 Incidental Work:

A. Contractor shall provide, as part of the contract price, all labor, superintendence, machinery, equipment, supplies, temporary utility services, third party compliance testing and analysis, necessary to complete the various items of work in accordance with these contract documents, to provide a complete, functional, and ready-to-use installation.

B. Contractor shall, as part of the contract price, acquire all necessary approvals for access to all project sites.

C. Contractor shall, as part of this contract price, furnish all environmental protection including, but not limited to all necessary work to prevent storm water and other environmental pollution on any construction site or adjacent areas, as well as anywhere in the vehicle and pedestrian routes used by the contractor’s vehicles and equipment.

D. Contractor shall be responsible for the restoration, reseeding/replanting and cleanup of any areas affected by the project, including any work and materials and labor necessary to return the project site(s) to its original state (prior to construction), by removing all evidence of construction debris, repairing all damage to vegetation, landscapes and finished ground surfaces, scarifying any hard-pack and driven-over earth areas, reseeding any areas disturbed by the contractor’s construction activities, and installing erosion protection as indicated on the drawings, or as required by Contractor’s Stormwater Pollution Prevention Plan (“SWPPP”).

E. Contractor is responsible to attend, at no additional cost to the Owner, the following meetings:

a. Preconstruction meeting to be scheduled by Owner.

b. Weekly progress meetings on site.

c. Special and final field observation meetings when requested or scheduled by the Owner.

d. Construction coordination meetings requested or scheduled by the

County.

e. Stakeholder/utility customer meetings when deemed necessary by the

County to keep them informed or to resolve unanticipated concerns.

Part 4 Restrictions to Dates and Times for Work Zones:

A. Partial Suspension for Winter: Project dates assumes a partial suspension for winter. Note that only work that can be completed and secured prior to a partial winter suspension is permitted. No open excavations are to be left during the suspension. All roadways and pedestrian facilities shall be fully open prior to the beginning of the suspension. The Contractor is responsible for periodic inspection of the projects limits during the winter suspension at no additional cost to County.

B. Partial or Full Winter Suspension Liquidated Damages: Failure to substantially complete work initiated prior to Partial or Full Winter shut down will result in Liquidated Damages. Liquidated damages will be in accordance with the current NMDOT Standard Specifications for Highway and Bridge Construction section 108, Table 108.8:1 Schedule of Liquidated Damages. Liquidated damages will be charged per day for failure to complete work initiated prior to winter suspension. These liquidated damages shall be considered mutually exclusive from the overall project completion liquidated damages listed above.

The contractor shall still be responsible for winter suspension maintenance or the county could enforce a double recovery which would include liquidated damages plus direct maintenance costs.

C. Liquidated Damages for Work: Failure to complete all work on time will result in Liquidated Damages applied to this contract in accordance with the current edition of the New Mexico Department of Transportation Standard Specifications for Highway and Bridge Construction section 108, Table 108.8:1 Schedule of Liquidated Damages. Liquidated damages will be charged per day for failure to complete work by any of the substantial and/or final completion dates listed.

1.3 Requirements for Bidders

Bids must be made with the understanding and in accordance with these conditions for bidders:

1.3.1 Bid Evaluation Criteria

Bid acceptance and bid evaluation. Bids shall be unconditionally accepted without alteration or correction, except as authorized in this article. Bids shall be evaluated based on the requirements set forth in the IFB, which may include criteria to determine acceptability such as inspection, testing, quality, workmanship, delivery and suitability for a particular purpose. Those criteria that will affect the bid price and be considered in evaluation for award shall be objectively measurable, such as discounts, transportation costs, and total of life cycle costs. The IFB shall set forth the evaluation criteria to be used. Only criteria that are set forth in the IFB may be used in bid evaluation. Interviews are to be used only for the purpose of clarification. The final evaluation results shall be forwarded to the purchasing agent.

The evaluation criteria for this Bid are:

1. Accurate submission of Bid Response Documents

2. Cost

The County may make such investigations as deemed necessary to determine the ability of the Bidder, and any prospective subcontractors of the Bidder, to perform the work, and the bidder shall furnish to the County all such information and data for this purpose as the County may reasonably request. The County reserves the right to reject any bid if the evidence submitted by, or investigation of, such Bidder fails to satisfy the County that such Bidder is properly qualified to carry out the obligations of the Contract and to timely complete the work contemplated herein. Conditional bids may not be accepted in the sole discretion of the County.

1.3.2 Required Bid Response Documents

The bidder shall follow the instructions described in Section 1.1 Invitation for Bids.

1.3.3 The Bidder’s Bid Response Documents

The following documents must be completed and included in this preferred order:

1. Copy of Bidder’s State of New Mexico Contractor’s License(s) with proper classifications.

2. Bid Form (Section 1.5.1)

3. Alternatives and Allowances, if applicable (Section 1.5.2)

4. List of Subcontractors with Company Name, license number(s) and classification(s) (Section 1.5.3).

5. Bid Bond (Section 1.5.4)

6. Campaign Contribution Form (Section 1.5.5)

7. Certification – Debarment, Suspension, and other Responsibility Matters (Section

1.5.6)

8. Permanent Main Office Address of Company (Section 1.5.7) – Note requirement to provide a Certificate of Good Standing and Compliance from the New Mexico Secretary of State, if incorporated.

9. Authorization for Verification of Information (Section 1.5.8)

10. Provide proof of online registration and payment of $400.00 for Certificate of

Contractors Registration (Section 1.5.9) with New Mexico Department of Workforce Solutions.

11. Non-Collusion Affidavit (Section 1.5.10)

12. NMDOT Bidders Quoters for DBDE (Section 1.5.11)

13. Provide proof of bidder’s NMDOT prequalification at the time of bid opening in accordance with 18.27.5 NMAC by including the most recent NMDOT Prequalified Contractors and Subcontractors List found on the NMDOT website at the following web address, or as may be amended. County reserves the right to verify NMDOT prequalification status with NMDOT to ensure bidders are on the list at the time of bid opening (Section 3.4.11 of the IFB, Section 102.2 of the T/LPA 100 Division):

https://www.dot.nm.gov/highway-operations-program/operations-support-division-director/construction-civil-rights-bureau/prequalification-requirements/

The County may consider a bid to be non-responsive or non-responsible if the Contractor fails to include any of the items described in items 1 through 13, above.

1.3.4 Liquidated Damages for Failure to Enter into Contract

The successful Bidder, upon failure or refusal to execute and deliver the Contract and required Bonds within ten (10) calendar days after Bidder has received the Notice of Award, shall forfeit the Bidder’s Bond to the County, as liquidated damages for such failure or refusal, the bid security deposited with Bidder’s bid.

1.3.5 Conditions of Work

Each bidder must inform itself fully of the conditions relating to the construction of the Project and the employment of labor thereon. Failure to do so will not relieve a successful bidder of its obligation to furnish all material and labor necessary to carry out the provisions of the Contract. Insofar as possible, the Contractor in carrying out the Work must employ such methods or means as will not cause any interruption of, or interference with the Work of any other contractor, or the daily operations of County offices. The Work in this Contract will be carried out during the hours of 8:00 a.m. to 5:00 p.m., Monday through Friday unless otherwise scheduled with and approved by the County. Noise Ordinance Waivers are required for work occurring between the hours 9:00 p.m. and 7:00 a.m.

1.3.6 Addenda and Requests for Interpretation

A. No interpretation of the meaning of the plans, specifications or other pre-bid documents will be made to any bidder orally and bidders understand that no oral interpretation once made may be relied upon. Every request for such interpretation shall be in writing addressed to the Project Manager. Requests for interpretation must be received at least six (6) working days (Monday-Friday) prior by 5:00 p.m. to the date fixed for the opening of bids. Failure of any bidder to acknowledge all addenda on the Addendum Acknowledgement Form shall not relieve such bidder from any obligation under its bid as submitted and may render the bidder non-responsive. Each Bidder shall ascertain prior to submitting a Bid that the Bidder has received all Addenda issued, and the Bidder shall specifically acknowledge their receipt in the bid. All addenda so issued shall become part of the Contract documents.

B. Addenda will be e-mailed to all who are known by the County to have requested Bid Documents.

C. No Addenda will be issued later than four (4)…