11-001. Attachment 1 Applicant Pricing Bid Template Level 2 Charging.docx

DOCX document 39 KB Posted

Attached to
Community Electric Vehicle Charging
Solicitation number
RFP-200-25
Issued by
Boulder County, Colorado

About this file

This document is a Pricing Bid Template for Level 2 Electric Vehicle (EV) Charging Infrastructure for Boulder County, Colorado, prepared as part of a Request for Proposals (RFP) for community EV charging infrastructure. The project involves designing, installing, and operating four networked Level 2 EV charging ports with SAE J1772 connectors, with final site locations to be determined within Boulder County, prioritizing shared parking areas at multifamily properties. The project is funded through the U.S. Department of Transportation's Federal Highway Administration Charging and Fueling Infrastructure (CFI) discretionary grant program, authorized under the Bipartisan Infrastructure Law.

The bid template provides a comprehensive breakdown of costs across five key categories: pre-construction (planning and design), equipment purchase, installation, operational costs, and other potential expenses. Vendors are required to provide detailed unit and total costs for each phase, including site assessments, engineering, permitting, equipment, electrical work, installation labor, networking fees, maintenance, and ongoing operational support. The RFP mandates that selected vendors provide a turnkey solution with high user satisfaction rates and over 97% station uptime, while also ensuring compliance with federal funding requirements, including National Electric Vehicle Infrastructure (NEVI) Standards. Vendors must be prepared to guide site hosts through the entire process from assessment to installation and maintenance.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Attachment 1 - Pricing Bid Template for Level 2 EV Chargers Please provide a detailed list of costs associated with designing, installing, and operating four Level 2 EV charging ports in Boulder County. This includes all necessary phases: pre-construction, installation, and ongoing operations.

System Overview

· Ports: Four Level 2 charging ports (continuous power delivery rating of 6 kW)

· Connectors: SAE J1772, permanently attached

· Networked: Yes

· Location: Final sites to be determined within Boulder County; priority locations include shared parking area at multifamily properties Cost Breakdown - Four Networked Level 2 Charging Ports Please use this template to describe the items, unit cost, and total cost to implement the project described in the RFP Scope of Services.

Site host locations will be finalized after vendor(s) are selected for award. Therefore, the applicant’s budget must describe costs on a per unit basis, and then calculate the total overall cost of four Level 2 charging ports.

Boulder County is providing applicants with this template to ensure the selection committee can review consistent budget information in all applications. The applicant must include the cost for each item (both equipment and labor) listed in the tables below. However, applicants are encouraged to modify the template to add any costs that are missing and necessary to be responsive to the requested services in the RFP. Please include the costs for items of equipment, hardware, accessories, parts, construction materials, and software as well as the hourly labor rates for team members.

I. Pre-Construction (Planning & Design)

Item
Description
Quantity
Unit Cost
Total Cost

(1 dual-port station) Total Cost (4 ports)

Site Assessment
Physical inspection, parking lot survey, grid proximity, load capacity check
Site Drawings
Drawings of parking lot and charger locations; including ADA accessibility requirements
Preliminary Engineering
Provide description
Permitting
Local jurisdiction permits
Utility Coordination
Utility applications and engineering reviews; stamped electrical drawing
Site easement, if applicable
Provide description, if Category 2 applicant will offer 3rd party ownership
Other Pre-Construction items, if relevant
Provide description
Hourly rate for respective team members
Include hourly rate of each worker, estimated hours needed, and duration of time

II. Equipment Purchase

Item
Description
Quantity
Unit Cost
Total Cost

(1 dual-port station) Total Cost (4 ports)

EVSE Units (4 ports networked)
Charging station hardware; Networked 6 kW L2 EVSE with J1772 connectors
Mounting (pedestals / walls)
Installation accessories for mounting chargers
Cabling / Connectors
Heavy-duty cable, connectors, protective sleeves; indicate whether cables are replaceable
Network Activation Fee (include ongoing network management fee under Operational costs below)
One-time fee to activate network features per station
Communication Hardware
Provide description
Other equipment items, if relevant
Provide description

III. Installation (Construction & Electrical)

Item
Description
Quantity
Unit Cost
Total Cost

(1 dual-port station) Total Cost (4 ports)

Construction / Trenching
Underground conduit work in parking lot (trenching, boring, concrete, asphalt) and repairs; open trenches must be safely covered during off hours
Concrete and bases for chargers, or similar
Provide description
Safety features for chargers, such as bollards
Provide description
Other construction items, if relevant
Provide description; ensure project meets ADA accessibility requirements
Conduit & Wiring
From electrical panel to charging stations
Panel Upgrades
New circuit breakers, meter upgrades, or added capacity
Transformer Upgrade (if needed)
External or pad-mounted transformer work
Other electrical components, if relevant
Provide description; a method for disconnecting chargers may be necessary depending on the site.
Installation Labor (licensed electrician, construction employees, etc.)
Include hourly rate of each worker, estimated hours needed, and duration of time
Signage & Pavement Markings
EV-only and/or Accessible-EV-Use-Last signs, paint, wayfinding decals
Landscaping
Site restoration, replanting
Station Commissioning
Final testing, utility sign-off, activation
Other installation items, if relevant
Provide description

IV. Operational Costs (Provide annual cost data)

Item
Description
Quantity
Unit Cost
Total Cost Per Year

(1 dual-port station) Total Cost Per Year (4 ports)

Networking Fees / Software (all categories)
Connectivity, user access, remote diagnostics, data sharing

Clarify in application if cost is invoiced all at once or annually

5-year Warranty (all categories)
Equipment and labor warranties

Clarify in application if cost is invoiced all at once or annually

Maintenance & Repairs / Support (Category 1)
Example: Routine inspections, cleaning, cable replacements; Applicants to Category 1 must customize the price bid template to match their maintenance and repairs service that meets the safety, reliability, and customer service objectives of this RFP and these specific categories.
Maintenance & Repairs / Support (Category 2)
Example: Routine inspections, cleaning, cable replacements; Applicants to Category 2 must customize the price bid template to match their maintenance and repairs service that meets the safety, reliability, and customer service objectives of this RFP and these specific categories.
Electricity Costs
Power usage based on kWh delivered
Data & Reporting Services
Reporting platform
Other operational items, if relevant
Provide description
Hourly rate for respective team members
Include hourly rate of each worker, estimated hours needed, and duration of time

V. Other Costs

Item
Description
Quantity
Unit Cost
Total Cost

(1 dual-port station) Total Cost (4 ports)

Battery Storage (for demand management) (cost would need justification for approval)
Mitigate peak loads or store solar (covered outside project)

Summary (4 networked ports)

Item
Cost (total of 4 ports)

1.Planning

2.Equipment

3.Installation

Total Capital Cost (#1 + #2 + #3 above)

Operating Cost (Annual)