11-00 ULTMA 2026 PS Addendum 03 2026-11-02-FINAL.pdf

PDF 1 MB Posted

Attached to
2026 Pump Station Improvements Project
Solicitation number
US.256212
Issued by
Lancaster County, Pennsylvania

About this file

Addendum No. 03 to the Upper Leacock Township Municipal Authority 2026 Pump Station Improvements Project clarifies contract requirements for two separate construction contracts: Contract 2026-02 (General Construction) and Contract 2026-03 (Electrical Construction). This addendum, issued on November 2, 2026, by RETTEW Associates Inc., supersedes conflicting language in original contract documents and must be acknowledged by bidders on their bid forms to avoid disqualification. The addendum incorporates materials from a pre-bid meeting held on October 29, 2026, including a sign-in sheet, meeting minutes, reference photographs, and a 14-page list of bidders' questions and responses. Sealed bids were due online by 10:00 AM on November 5, 2026, through the PennBID portal, with a mandatory pre-bid meeting and site visit held at the Owner's office located at 161 Newport Road, Leola, Pennsylvania. Successful bidders must provide a 10% certified check or bid bond and complete the project within 240 calendar days of receiving the Notice to Proceed.

Key technical clarifications in Addendum No. 03 address generator installation, propane system modifications, electrical panel upgrades, and fencing reuse at the Glenbrook location. The Authority will retain existing generators with the Electrical Contractor responsible for disconnection and removal; the Owner will handle transportation and storage. Existing concrete generator pads will be reused for new generator installation. The Electrical Contractor must perform all required demolition work, including HVAC equipment removal and trenching for conduit installation. Bid Alternate #2 specifies replacement of three sides of existing fence material with reuse of the existing gate and chainlink fence front side, which will receive new privacy slats. The propane piping relocation at the facility must match existing material and pipe size. At the Hertzog Pump Station, the existing wet well hatch will be enlarged to 42 inches by 42 inches, and the Electrical Contractor must furnish and install a new secondary stainless steel guide rail support angle and upgrade the electrical panel as detailed in the contract drawings to accommodate the new aeration system load. Performance and payment bonds equal to 100% of the contract price will be required from the successful bidder.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3020 Columbia Avenue, Lancaster, PA 17603 ● Phone: (800) 738-8395 E-mail: rettew@rettew.com ● Web site: rettew.com

ADDENDUM NO. 03

November 2, 2026

To: All Prospective Bidders

RE: Upper Leacock Township Municipal Authority 2026 Pump Station Improvements Project Contract 2026-02: General Construction Contract 2026-03: Electrical Construction RETTEW Project No. 0571405975

Dear Bidders:

The following Addendum No. 03 is hereby made to the contract documents for the above-referenced project. Any additions, clarifications or deletions described in this Addendum take precedence over any instructions at conflict herein. All items in this Addendum shall be considered in preparation of your proposal for the referenced project.

Receipt of this Addendum shall be acknowledged by inserting this number and date in the space provided on the Bid Form. Failure to do so may result in disqualification of the Bidder. The addendum consists of two pages and the following attachments:

Pre-Bid Meeting Sign-In Sheet (2 pages) Pre-Bid Meeting Minutes (3 pages) Photo of Reusable Fence at Glenbrook (1 page) List of Bidders’ Questions and Responses (14 pages)

PRE-BID CLARIFICATIONS

1. The Authority's current propane supplier is Sweetwater Propane, Inc. Contact information is as follows:

Sweetwater Propane, Inc.

Phone: (717) 740-3430

2. Owner wishes to retain the existing generators. The Electrical Contractor shall disconnect and remove the existing generators from service and from the buildings. The Owner shall provide transportation and storage of the removed generators.

3. All demolition work required to complete the Work of the Electrical Contract shall be the responsibility of the Electrical Contractor. This includes, but is not limited to, removal of existing HVAC equipment designated for replacement and trenching required for installation of conduit and associated electrical work.

Addendum No. 03 Upper Leacock Township Municipal Authority/2026 Pump Station Improvements Project November 2, 2026 RETTEW Project No. 0571405975

4. The existing concrete generator pads are intended to remain and be reused for installation of the new generators. Reference Keyed Note 1 on sheets E-04 and E-06.

5. In addition to re-using the existing gate at Glenbrook, the front side of the gate that is chain link fence is also re-useable. Bid Alternate #2 shall be for the replacement of the 3 sides that are currently poly material, re-use of the existing gate, and re-use of the chainlink on the front side.

New privacy slats shall be installed within the existing chain-link fence section that is to remain.

The photograph provided with this addendum indicates the section of fence and gate to remain.

6. The Contractor shall match the existing propane piping material and pipe size for the relocated propane tank installation.

At Hertzog, the existing pump guide rail support configuration shall be maintained. The Owner wishes to retain the existing arrangement where the pump guide rail brackets are mounted to a secondary stainless steel angle bracket. Photographs of the existing bracket configuration were previously provided with Addendum No. 1.

The proposed wet well hatch shall be increased in size to 42 inches by 42 inches. The Contractor shall furnish and install a new secondary stainless steel guide rail support angle to accommodate installation within the enlarged hatch opening. The float wiring shall be mounted to the secondary bracket in a manner similar to the existing conditions.

7. It was mentioned by the Owner during the prebid that the existing Hertzog Pump Station panel has insufficient capacity for the proposed aeration system. The existing electrical panel at the Hertzog Pump Station is to be upgraded as shown on the Contract Drawings, Sheet E-03 Detail B.

The EC shall provide the panel modifications identified in Detail B as required to accommodate the new aeration system electrical load.

END OF ADDENDUM

Z:\Shared\Projects\05714\0571405975 - 2026 Pumping Station Improvements Project\MUN\05 Bidding\Addenda\No. 03\0_Addendum 03_ULTMA_2026 PS_2026-11-02.docx

RETTEW

3020 Columbia Avenue, Lanaster~ PA 17603 • Phone: (800) 731-8395 E-matl: rettew(trettew.com •Website: rettew.com

We answer to you.

PRE-BID MEETING SIGN-IN SHEET

October 29, 2026

OWNER:

PROJECT:

Upper Leacock Township Munldpal Authority 2026 Pump Station Improvements Project

NAME COMPANY

( Please Print) (Pie- Print)

Abraham King, PE, CCCA RETTEW Associates Inc.

Andrew Ferko, PE RETTEW Associates, Inc.

Cr4br, e. ( 1/ew Lohd~~ Pl no(Ll{i ~( ei t t ;·c , ; I\<..

.J~ ~cl-£ Ar36L e £co ;V

-re~~G~ fS! °P"""t'j 3,,~, f(c>blJ: (cJc~7;_ F 1c-{dfo rLe-

Bui A l b°'-VJ U hr;~ L at1>'tYv-cA lo vi

Pace 1of9

Sw~ty <:onsulunu

CONTACT INFORMATION

Phone: 717-344-5031

Fax:

E-Mail: abraham king@rettew com

Phone: 814-315-2690

Fax:

E-Mail: ~ndrew.ferko@rettew com

Pttone:(,{O- o''(' 7 ~25 Fax:

E-11a11:(.,,.frnt,ct~; @/1GLA6~ ~ !

Phone: 7f7- 3fz - fl,.,_

Fax:

E-llall:j~'t.~4>ftt~ ...... 4'.-..

Phone-:

Fax:

E-llail: j 1wy/.,.p,: e.~p~J . ..,.

Phone: 7 \ c l..& ~ DJ'r-7

Fax:

E-llall: rw; /Jv~. "'-QI, ~foe~

Phone: YiLf _, ~ 7 7 .1JQ~ ! .

Fax:

E-llall: P'\ ~1, ~ fl_»l!_~, ~ . ~ 0.,, kelly.helsel Text Box

RETTEW.

3020 Columbia Avenue, Lancaster, PA 17603 • Phone: (800) 738-8395 E-mail: rettew@rettew.com • Web site: rettew.com we answer to you.

E~nHrs

Em,lronminUJ c«cstAtants

PRE-BID MEETING SIGN-IN SHEET Surveyors undst~ AtchiUCts

October 29, 2026

OWNER:

PROJECT:

Upper Leacock Township Municipal Authority 2026 Pump Station Improvements Project

NAME COMPANY

(Please Print) (Please Print)

Du-t~ {\\4 r''f '1\ q~ UL1A~ S~r fJtP+.

/ici/ l11tt1J {I? ,µ-14--

Sa!Qty

Consuttants

CONTACT INFORMATION

Phone: (7/ 7) 9J1 JI% f Fax:

E-Mail: d MA.. -1-; -1 Q_U/ t 't.-p. c,.,.

Phone: /I l,.IJi -'f)'tS'LJ

Fax:

E-Mail:

Phone:

Fax:

E-Mail:

Phone:

Fax:

E-Mail:

Phone:

Fax:

E-Mail:

Phone:

Fax:

E-Mail:

Phone:

Fax:

E-Mall:

RE'f'l'EW.

kelly.helsel Text Box

PRE-BID MEETING

Upper Leacock Township Municipal Authority

2026 Pump Station Improvements Project October 29, 2026

We answer to you.

3020 Columbia Avenue, Lancaster, PA 17603 Phone: (800) 738-8395 Phone: (800) 738-8395 E-mail: rettew@rettew.com ● Web site: rettew.com

RETTEW Job No.: 0571405975 Upper Leacock Township Municipal Authority

2026 Pump Station Improvements Project Contract No. 2026-02 – General Construction

Contract No. 2026-03 – Electrical Construction

Thursday, October 29, 2026

MINUTES

IN ATTENDANCE:

Derek Martin Upper Leacock Township Municipal Authority Michael Morris Upper Leacock Township Municipal Authority Abraham King, PE RETTEW Associates, Inc.

Andrew Ferko, PE RETTEW Associates, Inc.

Contractors and vendors

(see attached sign-in sheet)

1.0 INTRODUCTIONS

• The project team made introductions.

2.0 CONTRACT MILESTONES

• The bid opening will occur on Thursday, November 5, 2026 at 10:00 A.M.

• All Contract milestones are outlined in the agreement sections of the Project Manual.

3.0 APPLICATION FOR PAYMENT

• Submission will be required the first week of month for closeout of previous month.

4.0 PROJECT OVERVIEW:

The project will be bid under two separate prime contracts:

• General Construction

• Electrical Construction

2026 Pump Station Improvements Project

5.0 ACCESS AND RIGHT-OF-WAY: the selected contractor will have access within the within the project property boundaries only. No other off-site staging or laydown areas have been secured for the project. Township/Authority staff will remain on-site throughout the duration of construction.

There were no comments from contractors on additional staging areas required by work.

6.0 FUNDING REQUIREMENTS: the project is grant-funded through the Commonwealth Financing

Authority of Pennsylvania. Special requirements:

• Project Sign

• CFA Sexual Harrassment Clause

• Prevailing Wage Rates

7.0 ITEMS OF INTEREST:

• Addendum no. 3 is anticipated to be issued next Monday and will include a copy of the sign in sheet, meeting minutes, and bidder clarifications.

• Clarifications will close on PennBid at 10:00 am on Monday, November 2, 2026. Bids open

November 5, 2026.

• General contractor will be responsible to coordinate and pay for concrete and compaction testing outlined in the specifications.

• The project includes eight (8) bid alternates. The determination of the apparent low bidder will be based solely on the base bid items. Bid alternates will be excluded from determining the apparent low bidder.

8.0 QUESTIONS

9.0 COMMENTS

10.0 PROJECT SITE TOUR

• A project site tour was held at the conclusion of the meeting.

2026 Pump Station Improvements Project

I believe these minutes accurately reflect the items discussed during this pre-bid meeting. If there are any revisions or corrections to these minutes, please contact the undersigned within five days of the date of publication.

Recorded by:

RETTEW

Abraham King, PE, CCCA

Project Manager

Attachment

- Sign-in Sheet

DISTRIBUTION:

- via PennBid Website

Z:\Shared\Projects\05714\0571405975 - 2026 Pumping Station Improvements Project\MUN\05 Bidding\Prebid

Meeting\Meeting Minutes_Prebid_2026-10-29.docx

Generated on Nov 02, 2026 3:27 PM EST - Kelly Helsel

Public Q&A

#1 - HVAC Contract

Uhrig Construction, Oct 07, 2026 10:20 AM EDT, Not Public - Pending

Who is responsible for getting HVAC numbers? Does HVAC have its own prime contract or is it the responsibility of the GC?

Kelly Helsel, Oct 12, 2026 10:05 AM EDT, Public - Answered

HVAC will not have its own prime contract.

Demolition and installation of the new motor actuated intake louvers is currently represented in the plans as responsibility of the GC, with final electrical connections to be completed by the EC.

This will be modified in Addendum 1.

All HVAC work directly associated with installation of the new generators is currently identified in the plans to be completed by the Electrical Contractor (2026-04). This includes but is not limited to disconnecting the existing exhaust duct sheet metal and natural gas connections to facilitate the installation of the new generator, providing new exhaust duct sheet metal and flexible connectors from the new generator as required, and providing new gas piping and connections, and providing generator engine exhaust piping and insulation as shown in the electrical drawings.

In order to simplify the scope of the two Contracts and assist bidders with pricing, the plans will be modified in Addendum 1 to show all HVAC work to be completed by the EC.

#2 - Wet well/Manhole Coating

Vortex Lining Systems, LLC, Oct 07, 2026 11:06 AM EDT, Not Public - Pending

Would the owner/engineer consider Quadex Structure Guard an approved wet well/manhole epoxy liner?

Quadex® Structure Guard® is a 100% solids, high-build epoxy coating that provides both long-term corrosion protection and structural enhancement for critical wastewater infrastructure. This includes manholes, pump stations, treatment plants, and any other facilities that experience high levels of corrosion and abrasion. Whether in municipal or industrial applications, Structure Guard is formulated to withstand the most aggressive and turbulent environments, ensuring that your infrastructure remains reliable and effective.

Kelly Helsel, Oct 12, 2026 10:06 AM EDT, Public - Answered

Refer to the Instructions to Bidders, Article I-10. No consideration of substitutions or "or equals" for this project will be considered prior to the effective date of the Agreement.

#3 - Contracts

Garden Spot Electric, Inc., Oct 12, 2026 8:34 AM EDT, Not Public - Pending

Pennbid lists 4 contracts (See Decisions) for this project but the details only appear to indicate 2.

Please verify there are no Plumbing or HVAC contracts for this project.

Kelly Helsel, Oct 15, 2026 2:18 PM EDT, Public - Answered

There are two Contracts for this Project: General Construction (Contract 2026-02) and Electrical

Construction (Contract 2026-03).

There are no separate Plumbing or HVAC Contracts for this Project. All Work identified in the

Contract Documents shall be completed under either Contract 2026-02 or Contract 2026-03. All

HVAC work will be completed by the EC. A portion of the work associated with the motor actuated louver is currently shown in the plans to be completed by the GC. This will be modified in

Addendum 1 on 10/16/2026. All HVAC work will be completed by the EC.

#4 - E02 Note 1 - 2" Control

Garden Spot Electric, Inc., Oct 12, 2026 8:48 AM EDT, Not Public - Pending

E02 Note 1 indicates extending existing 2" and 1" Conduit. My understanding is the 1" LP-15,17 circuit noted is #10s for power and is spicing in the existing J-Box. I am not seeing where there is indication of what is to be pulled through the 2" and where its going. The final sentence is also not making sense to me. "Contractor shall route power and control in separate shielded cable construction as shown" - Where is this shown? I see NO control related to note 1. Note 3 has control but nothing related to a 2" Conduit. Please clarify what is going in the 2", where its going and where its to be intercepted.

Kelly Helsel, Oct 15, 2026 2:18 PM EDT, Public - Answered

For Drawing E02, notes 1, 2, and 3 are showing the work necessary for both power and control for the new aeration system and connections to the control panel from the electrical panel LP and existing duplex pump control panel located in the existing generator building. New conduits shall be routed from the new aeration system control panel to the existing junction box at the primary wet well. An existing empty 2”C extends from this existing junction box back the existing generator building and is noted on the drawing background as “exist UG conduit”. The contractor shall utilize these new and existing conduit pathways to extend the new power and control wiring needed to support the aeration system control panel for leader noted details and respective notes.

Conductors needed for both power and control shall be included in shielded cable construction as these circuits will route combined in 2”C from the existing junction box to the generator building and may route with existing instrumentation cables. We would anticipate a service loop in the existing junction box and no splices needed. This existing empty 2”C pathway will avoid the work necessary for routing new conduits underground from the existing generator building to the aeration system.

#5 - E03 Note 3 - Extend FM Cable

Garden Spot Electric, Inc., Oct 12, 2026 8:58 AM EDT, Not Public - Pending

Please confirm if the existing FM Cable is long enough to be reused for the new Meter Vault location. Per note 3 contractor to extend and conduit and cable. Cable cannot be extended.

Please advise if new FM cable is required and if so which contract would supply it.

Kelly Helsel, Oct 15, 2026 2:19 PM EDT, Public - Answered

The proposed location of the flow meter should slightly reduce the length of cable required when compared to existing conditions, and therefore a replacement cable is not anticipated. Should field conditions require a replacement cable for the flow meter, it will be supplied by the EC and handled via change order.

#6 - Site Visit - Prebid

Garden Spot Electric, Inc., Oct 12, 2026 10:31 AM EDT, Not Public - Pending

I have a number of questions that may be answered if I can get my eyes on the existing sites. The prebid date is awfully close the the bid date and more importantly question period end date. It does not allow contractors time to formulate questions post site visit and have them answered in time for the bid. 2 work days for a question period and then 3 more days to have them answered by and make changes to estimates is very tight. Please provide more time inbetween pre-bid and bid. If this is not possible please allow contractors to visit all 4 sites at least 1 week prior to scheduled prebid.

Kelly Helsel, Oct 15, 2026 2:19 PM EDT, Public - Answered

Provide the questions in written form and answers will be provided with sufficient time for bid preparation. An extension to the schedule will not be provided. A site visit will be held after the prebid meeting. No additional site visits will be permitted.

#7 - Estimates

Garden Spot Electric, Inc., Oct 12, 2026 10:33 AM EDT, Not Public - Pending

When were the estimates per contract calculated? Please provide approx date of estimate.

Kelly Helsel, Oct 15, 2026 2:19 PM EDT, Public - Answered

The Engineer's opinion of probable construction cost was prepared during final design, just prior to bid.

#8 - Bypass Pumping

PSI Pumping Solutions Inc., Oct 13, 2026 3:17 PM EDT, Not Public - Pending

Can an automated alarm dialer be utilized in place of 15728 1.6 C.?

Kelly Helsel, Oct 15, 2026 2:20 PM EDT, Public - Answered

An automated dialer system will be acceptable, but contractor staff needs to be available to respond in the event of an emergency.

#9 - Bareville PS

PSI Pumping Solutions Inc., Oct 14, 2026 10:14 AM EDT, Not Public - Pending

Can you please provide the make and model of the existing pump so that the upper guide rail can be ordered correctly.

Kelly Helsel, Oct 15, 2026 2:20 PM EDT, Public - Answered

No guide rails are to be replaced as part of this project. It is assumed that this question is pertaining to the Hertzog Pump Station. Sheet 01C-03 includes a callout stating "Existing top guide rail support brakcet to be removed and reinstalled into new hatch opening". This note does not pertain to the actual top guide rail bracket, but rather an additional, custom fabricated steel bracket that extends across the clear opening of the wet well, which the pumps top rail bracket is mounted to. Contractor to field verify based on the location and size of the new access hatch, whether replacement of this bracket is necessary. Should the additional bracket be required to mount the rails with the new access hatch, then the Contractor shall fabricate and install a new bracket that fits the updated access hatch. Should the contractor determine that the bracket is no longer necessary, the top bracket may be mounted directly to the inside clear opening of the access hatch.

At the Bareville pump station, a similar callout is provided indicating the replacement of pump brackets. For Bareville, this is referring to the two brackets that hold the rail to the inside of the access hatch. No custom secondary bracket exists at this station. Bareville Pumps are 30 HP

Myers 4VCX300M$.

A photograph of these brackets will be included with Addendum 1.

#10 - Hertzog PS

PSI Pumping Solutions Inc., Oct 14, 2026 10:16 AM EDT, Not Public - Pending

What is the make and model of the pump so that we can determine the concrete pump pad to be replaced, or can you provide a detail sketch?

Kelly Helsel, Oct 15, 2026 2:20 PM EDT, Public - Answered

The existing pump labeled Grinder Pump No. 01 at Hertzog Pump Station is a Myers model number WG50 Submersible Pump with a 5.75" Impeller, Single-Phase 5 HP. However, the note indicated replacement of concrete bases is incorrect. The bases to be replaced are integral to the pump, and not a separate concrete base. A cutsheet indicating the bases that need replaced will be included in the upcoming Addendum 1.

#11 - Hertzog PS Bypass

PSI Pumping Solutions Inc., Oct 14, 2026 10:18 AM EDT, Not Public - Pending

Where is the nearest suction point for bypassing the pumping station? Is a larger site plan available? How long is the force main to the termination point?

Kelly Helsel, Oct 15, 2026 2:21 PM EDT, Public - Answered

It is anticipated that bypass pumping will be required at both Hertzog and Apricot. The contractor will be able to bypass pump from existing influent manholes at both stations. For discharges, the contractor will be required at both stations to make a temporary connection to the existing forcemain.

#12 - Hertzog Aeration Blower

PSI Pumping Solutions Inc., Oct 14, 2026 10:20 AM EDT, Not Public - Pending

Is the location of the proposed blower outside of any electrical classified areas? ie. distance from the wet well vent?

Kelly Helsel, Oct 15, 2026 2:21 PM EDT, Public - Answered

Location of the proposed aeration systems is outside of electrical classified areas.

#24 - Glenbrook WW Grate

PSI Pumping Solutions Inc., Oct 14, 2026 10:22 AM EDT, Not Public - Pending

What is the size of the existing hatch for the retrofit safety grate to be installed?

Kelly Helsel, Oct 21, 2026 4:00 PM EDT, Public - Answered

Two stations will require a retrofit: Glennbrook and Apricot. At Hertzog and Bareville, new lids are being provided on the wet well. For Hertzog and Bareville, proposed hatch sizes are indicated in the plans.

Based on the existing as-built drawings, the existing access hatch at Glenbrook has approximately a 38"x48" clear opening, and the existing access hatch at Apricot has approximately a 32"x58" clear opening. However, exact dimensions will need to be confirmed by the Contractor prior to ordering the associated safety grating.

#21 - Glenbrook / Apricot Generator

PSI Pumping Solutions Inc., Oct 14, 2026 10:25 AM EDT, Not Public - Pending

What contract is responsible for the demo and removal of the generator? Is the owner retaining the generator or is contractor to dispose of the units? If owner is retaining how far from the sites will they be stored and how will transportation be handled?

Kelly Helsel, Oct 16, 2026 8:11 AM EDT, Public - Answered

All work associated with the generators is to be completed by the EC, including demolition. Owner shall be given the opportunity to keep any existing equipment in the building. Should the Owner not wish to keep the generators, the EC will be responsible for removal and disposal of the equipment. Should the Owner wish to keep the generators, the Owner will be responsible for handling transportation of the generators to the desired storage facility.

#13 - Glenbrook and Apricot GC/EC plan Coordination

PSI Pumping Solutions Inc., Oct 14, 2026 10:28 AM EDT, Not Public - Pending

Please confirm the GC is to demo, furnish and install louver and MOD damper on the side wall locations at both site per the EC plans and remove, rotate and reinstall gravity damper at

Glenbrook only. GC plans seem to indicate differing locations and scope.

Kelly Helsel, Oct 15, 2026 2:22 PM EDT, Public - Answered

All HVAC work will be the responsibility of the EC. This is unclear in the current plans and will be revised as part of Addendum 1. EC will be responsible to demo, furnish, and install the replacement motor actuated intake louvers, as specified in Division 23 of the Project Manual.

Disposal of demo'd materials will also be the responsibility of the EC. The gravity exhaust louvers will not require replacement. It will be the EC's responsibility to connect the proposed generator equipment to the existing gravity louvers as shown in the plan drawings. All other HVAC work, including the installation of the exhaust muffer and black iron exhaust pipes from the proposed generator will also be the responsibility of the EC.

#14 - Apricot coating clarification

PSI Pumping Solutions Inc., Oct 14, 2026 10:33 AM EDT, Not Public - Pending

Section J-J notes to sandblast and reline pointing to the pipe stubs. What is the extent of the reline? Reline would indicate the interior of the pipe. What is the intent? What material is the existing pipe? 099000 3.7 A. 2. b. states to reline stainless steel pump discharge piping inside of wet well. Typically stainless steel doesn't get coated. Please clarify.

Kelly Helsel, Oct 15, 2026 2:22 PM EDT, Public - Answered

The extent of the relining at Apricot is the exterior of the pipe from the interior wet well wall penetration to the flanged elbow (where replacement begins). The intent is to avoid replacing the pipe that penetrations the wet well wall, while still providing a means of rehabilitation to the pipe.

The existing pipe is ductile iron, not stainless steel. The stainless steel callout is indicating the replacement pipe material, not the existing pipe material. This will be more clearly represented in

Addendum 1. 099000 3.7.A.2.b is a misprint. Relining is limited to the existing ductile iron pipe exterior from the wet well interior wall (pipe penetration) to the downward elbow. 099000 will be revised as part of Addendum 1.

#15 - Pipe Penetrations

PSI Pumping Solutions Inc., Oct 14, 2026 10:51 AM EDT, Not Public - Pending

How are the pipe penetrations to be sealed in the new and existing precast concrete?

Kelly Helsel, Oct 15, 2026 2:22 PM EDT, Public - Answered

Link seals shall be provided at pipe penetrations. Non shrink grout shall be used as necessary for repair of concrete at the penetrations.

#16 - Hertzog

PSI Pumping Solutions Inc., Oct 14, 2026 10:54 AM EDT, Not Public - Pending

Confirm pump rails are to remain. Demo section and the New Work section seem to conflict.

Kelly Helsel, Oct 15, 2026 2:22 PM EDT, Public - Answered

All pump rails are to remain at all stations. No replacement of the pump rails are required. At

Hertzog Pump Station, the top of the rails is mounted to a custom stainless steel bracket that spans the clear opening of the access hatch. The stainless steel bracket at the clear opening of the access hatch may need to be replaced when installing the new access hatch. Whether the bracket needs replaced will need to be determined in the field by the contractor. Should the modified location of the access hatch allow for the rails to mount directly to the inside of the clear opening, then replacement of the additional custom steel bracket may not be necessary. Should the modified access hatch not allow for mounting of the rails directly to the opening, and a custom bracket is still required, it is the responsibility of the GC to furnish, fabricate, and install a new

T316 SS bracket.

At the bareville station, the existing bracket that holds the pump rails to the inside wall of the access hatch opening are in poor condition. It is the responsibility of the GC to furnish and replace these brackets.

Pictures of the brackets will be included in Addendum 1

#17 - Glenbrook and Apricot PS

PSI Pumping Solutions Inc., Oct 14, 2026 10:57 AM EDT, Not Public - Pending

Will a wet well vent be required at both of these PS? If so what size and material and location?

Kelly Helsel, Oct 15, 2026 2:23 PM EDT, Public - Answered

Wet well lid is only to be replaced at the Bareville and Hertzog Pump Stations. A 6" PVC

Gooseneck Vent with Insect Screen will be installed in each of the pump station top slabs, in accordance with the drawings.

#18 - Apricot Flow Meter Transmitter

PSI Pumping Solutions Inc., Oct 14, 2026 11:05 AM EDT, Not Public - Pending

Please provide specification or model number of unit to be replaced in kind by EC

Kelly Helsel, Oct 15, 2026 2:23 PM EDT, Public - Answered

The existing meter is an Endress Hauser 4" promag 50. Contractor shall furnish and replace the head unit located in the building. A photograph of the head unit will be included in Addendum 1.

#19 - 333100 2.4 A. Ball Valves

PSI Pumping Solutions Inc., Oct 14, 2026 3:14 PM EDT, Not Public - Pending

Please provide clarification on the 316 SS valve Specification. Specification calls for 3 inch and smaller to be threaded. I was not able to locate any of the named valve series over 2 inch

FNPT. Plan 01C-02 indicates flanged type connections at the valves.

Kelly Helsel, Oct 15, 2026 2:23 PM EDT, Public - Answered

333100 Section 2.4 A.1.c will be modified as part of Addendum 1. No threaded connections will be permitted for the new stainless steel discharge piping at Hertzog and Apricot. All new stainless steel discharge piping shall have flanged joints. All equipment shall have flanged end connections. Plans will be revised to indicate this in Addendum 1.

#20 - SST Coupling w/ Flange Adapter

PSI Pumping Solutions Inc., Oct 14, 2026 3:29 PM EDT, Not Public - Pending

Please provide part number or basis of design of the SST Coupling w/ Flange Adapter per section

D-D on plan sheet 01C-03

Kelly Helsel, Oct 15, 2026 2:23 PM EDT, Public - Answered

The SST Coupling with Flange Adapter is a misleading note and not intended to specify a proprietary coupling with a built in flange adapter. This will be revised in addendum 1. Instead, contractor should provide a standard stainless steel flange adapter on the 3" stainless steel bypass line for connection with the flanged ball valve. All stainless steel piping will be revised to show flanged joints in the valves and wet wells.

#22 - Question 17 follow up

PSI Pumping Solutions Inc., Oct 16, 2026 9:43 AM EDT, Not Public - Pending

Glenbrook and Apricot plans do not show a vent. Is the contractor to core drill and install a vent at each of these locations? If so please indicate preferred location of proposed vents.

Kelly Helsel, Oct 20, 2026 1:24 PM EDT, Public - Answered

A 6-inch PVC gooseneck vent with insect screen shall be installed at both the Glenbrook and

Apricot Pump Stations. The vent installation shall be completed by the General Contractor

(Contract 2026-02) in accordance with the details and locations shown on the revised drawings included with Addendum 1.

#23 - Estimated Cost

PSI Pumping Solutions Inc., Oct 16, 2026 11:21 AM EDT, Not Public - Pending

Is there an engineer estimate per contract available?

Kelly Helsel, Oct 20, 2026 1:24 PM EDT, Public - Answered

The estimated contract values are included in PennBid.

#25 - Permits and Timeline

Uhrig Construction, Oct 20, 2026 10:35 AM EDT, Not Public - Pending

Who is responsible for permits?

Project Manual states that Project Duration is 240 days until final completion. Are we expected to create our own schedule during timeline, or are you going to provide us with hard dates so we can gauge a target start and end date?

Kelly Helsel, Oct 23, 2026 11:24 AM EDT, Public - Answered

Permits are the responsibility of the Owner.

The Contractor shall provide the Owner and Engineer with a construction progress schedule prior to the commencement of construction. Reference General Conditions Article 2 and Specification

Section 013300, Paragraph 1.4.

#29 - Existing Panel Breakers

Garden Spot Electric, Inc., Oct 22, 2026 10:27 AM EDT, Not Public - Pending

Breakers for existing panels are noted to match existing. Please provide this information.

Kelly Helsel, Oct 26, 2026 3:30 PM EDT, Public - Answered

GlennBrook PS SQD QO Loadcenter

Apricot PS SQD NQOD panelboard

Bareville PS ITE CDP-7 Circa 1985

Contractor is encouraged to visit the site to review existing conditions.

#30 - ECBs Glennbrook & Apricot

Garden Spot Electric, Inc., Oct 22, 2026 10:29 AM EDT, Not Public - Pending

The ECBs noted on the onelines for Glennbrook and Apricot have EC adding ECBs but none show up on the plan views. Please provide locations.

Kelly Helsel, Oct 26, 2026 3:30 PM EDT, Public - Answered

The ECBs are small and shall be located at the contractor’s discretion once the ATS and other work is completed. Manage wall space accordingly to allow/plan for the ECBs. Contractor is encouraged to visit the site to review existing conditions.

#26 - Updated Electrical Drawings

Garden Spot Electric, Inc., Oct 22, 2026 10:31 AM EDT, Not Public - Pending

When can contractors expect the updated electrical drawings? The notes now conflict with the

GCs addendum 1 drawings.

Kelly Helsel, Oct 26, 2026 2:01 PM EDT, Public - Answered

Revised Electrical sheets will be provided in Addendum 2. Addendum 2 will be issued on

10/27/26.

#27 - Propane Supplier

DOLI Construction Corporation, Oct 22, 2026 10:59 AM EDT, Not Public - Pending

Who is the current propane supplier for the pump stations?

Kelly Helsel, Oct 26, 2026 2:02 PM EDT, Public - Answered

The Authority's current propane supplier for the pump stations is Sweetwater Propane, Inc.

#31 - SPD Specs

Garden Spot Electric, Inc., Oct 22, 2026 11:39 AM EDT, Not Public - Pending

Where are the specs for the SPDs noted to be replaced? Panel Spec section 262416 references a 264300 SPD Spec which I have not been able to locate.

Kelly Helsel, Oct 26, 2026 3:30 PM EDT, Public - Answered

The SPD specification will be issued with the next Addendum.

#32 - Pull/Tap Boxes Glennbrook/Apricot

Garden Spot Electric, Inc., Oct 22, 2026 12:24 PM EDT, Not Public - Pending

The onelines indicate a new tap box for Glennbrook and repurposing a wireway as a tap box at

Apricot. Where are these boxes located?

Kelly Helsel, Oct 26, 2026 3:30 PM EDT, Public - Answered

These items are located low on the wall below the existing and equipment designated to be replaced.

#28 - Temporary Facilities

Uhrig Construction, Oct 26, 2026 8:11 AM EDT, Not Public - Pending

Is it necessary to have an office in the field?

Who is responsible for any temporary facilities such as heating, water, electric, etc.?

Kelly Helsel, Oct 26, 2026 2:02 PM EDT, Public - Answered

A Temporary Field Office is not required. Requirements for a Temporary Field Office, if provided, can be found in Specification Section 015000. In the case the Contractor decides to utilize temporary facilities, they shall be responsible for all utilities and heating.

#33 - Reline Influent Manhole - Apricot PS

PIM Corporation, Oct 29, 2026 3:16 PM EDT, Not Public - Pending

What is the depth of the influent manhole getting relined at the Apricot PS?

Kelly Helsel, Nov 02, 2026 10:11 AM EST, Public - Answered

Based on the existing as-built drawings, the existing influent manhole at Apricot has an approximate depth of 9.75-feet.

02_Meeting Minutes_Prebid_2026-10-29.pdf
Derek Martin Upper Leacock Township Municipal Authority
Abraham King, PE RETTEW Associates, Inc.
Andrew Ferko, PE RETTEW Associates, Inc.

{"type":"Form","isBackSide":false,"languages":["en-us"],"usedOnDeviceOCR":false}

{"type":"Form","isBackSide":false,"languages":["en-us"],"usedOnDeviceOCR":false}

File details come from the government source that posted it. Updated .