NIH Division 50 Construction Cost Template.xlsx
XLSX spreadsheet 247 KB Posted
- Solicitation number
- 109584
About this file
This document is a Pre-Solicitation Notice for a $25-100 million Design-Build construction project to improve the medium voltage electrical infrastructure and provide standby power for chilled water generation at the National Institutes of Health's Central Utility Plant in Research Triangle Park, North Carolina.
The key objectives are to correct medium voltage and low voltage duct bank issues, replace an existing medium voltage feeder, install above-ground medium voltage switches, construct a new medium voltage generator yard and electrical vault to provide uninterruptible chilled water production and harden power distribution to critical facilities. The anticipated RFP release date is August 23, 2024 with a bid closing on September 23, 2024. The government is assessing the market's ability to provide the required services, including securing financial resources, implementing project management plans, and meeting bonding requirements. Based on responses, the requirement may be set aside for small businesses or procured through full and open competition.
View the file
Other files
Show all 18
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INSTRUCTIONS
| SECTION B - PRICING SHEETS INSTRUCTIONS: | |
| CSI DIVISION WORKSHEETS: | |
| 1 | CSI DIVISION WORKSHEETS ARE LINKED TO THE SUMMARY PAGE. ENTER THE PROJECT C NUMBER ON THE SUMMARY PAGE AND IT WILL POPULATE ALL THE SHEETS. |
| 2 | USE 50 DIVISIONS OF CONSTRUCTION AS DEFINED BY CSI MASTERFORMAT |
| 3 | CREATE A CSI DIVISION WORKSHEET FOR EACH DIVISION OF WORK REQUIRED TO COMPLETE THE PROJECT |
| 4 | LIST EACH WORK ITEM TO BE PERFORMED BY THE PRIME AND ITS ASSOCIATED MATERIAL AND LABOR COSTS. (ADD ADDITIONAL ROWS AS NECESSARY). |
| 5 | IDENTIFY EACH SUBCONTRACTOR, ENTERING SUBCONTRACTOR'S TOTAL MATERIAL AND LABOR COSTS. |
BACKUP SHALL BE PROVIDED FOR EACH SUBCONTRACTOR. (PRIME CONTRACTOR MAY ELECT TO MODIFY THIS SPREADHSHEET TO PROIVDE SUBCONTRACTOR BACK-UP DETAIL SIMILAR TO PRIME CONTRACTOR'S DETAIL.)
| 6 | INSERT A PERCENTAGE (i.e. 5 FOR 5%) FOR OVERHEAD APPLIED TO SUBCONTRACTOR(S) |
| 7 | INSERT A PERCENTAGE (i.e. 5 FOR 5%) FOR PROFIT APPLIED TO SUBCONTRACTOR(S) |
| 8 | A TOTAL DIVISION COST WILL CALCULATE AS COST DATA IS ENTERED FOR PRIME COSTS, SUBCONTRACTOR(S) COSTS AND PERCENTAGE VAULES. |
| SUMMARY PAGE:. | |
| 9 | THE SUMMARY PAGE WORK ITEMS ARE LINKED TO A CORRESPONDING CSI DIVISION WORKSHEET. |
| 10 | INSERT A PERCENTAGE (i.e. 10 FOR 10%) FOR OVERHEAD APPLIED TO PRIME WORK |
| 11 | INSERT A PERCENTAGE (i.e. 10 FOR 10%) FOR PROFIT APPLIED TO PRIME WORK |
| 12 | INSERT PRICE OF PREFORMANCE / PAYMENT BOND |
| 13 | A TOTAL CONTRACT PRICE WILL CALCUALTE AS COST DATA IS POPULATED FROM LINKED CSI DIVISION WORKSHEETS. |
SUMMARY
Work Request Number C115933
TABLE B-1 -- PROPOSAL SUMMARY OF COSTS *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT
| DIV. #: | ITEM DESCRIPTION | |
| (Use CSI Division Worksheet to back-up all pricing information for each Division listed in Table) | (A) | |
| MATERIALS | (B) | |
| LABOR | (C) = (A) + (B) | |
| SUBTOTAL COST | (D) | |
| SUBCONTRACTOR COSTS | (E) = (C) + (D) |
TOTAL COST
| 01 | GENERAL REQUIREMENTS | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 2 | Existing Conditions | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 3 | Concrete | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 4 | Masonry | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 5 | Metals | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 6 | Wood, Plastics, and Composites | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 7 | Thermal and Moisture Protection | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 8 | Openings | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 9 | Finishes | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 10 | Specialties | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 11 | Equipment | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 13 | Special Construction | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 14 | Conveying Systems | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 21 | Fire Suppression | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 22 | Plumbing | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 23 | HVAC | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 25 | Integrated Automation | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 26 | ELECTRICAL | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 27 | Communications | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 28 | Electrical Safety and Security | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 31 | Earthwork | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 32 | Exterior Improvements | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 33 | Utilities | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
| 34 | Transportation | $ - 0 | $ - 0 | $ - 0 | $ - 0 | $ - 0 |
SUBTOTAL - 1: $ - 0 $ - 0 $ - 0
OVERHEAD (% * subtotal 1 (C)) : (INSERT %) 0% $ - 0
SUBTOTAL- 2 (subtotal 1 (C ) + overhead): $ - 0
PROFIT (% * subtotal 2): (INSERT %) 0% $ - 0
SUBTOTAL - 3 (subtotal 2 + profit): $ - 0
TOTAL SUBCONTRACTOR COSTS (subtotal 1 (D)): $ - 0
SUBTOTAL - 4 (subtotal 3 + total subcontractor costs): $ - 0
PERFORMANCE / PAYMENT BOND: $ - 0
TOTAL CONTRACT PRICE (subtotal 4 + bond): $ - 0
Attachment #4, NIH Division 50 Construction Cost Template FOR OFFICIAL USE ONLY
SOURCE SELECTION SENSITIVE INFORMATION-SEE FAR 2.101 & 3.104
Multiple Award Construction Contract (MACC)
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 1
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 01 | GENERAL REQUIREMENTS | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
FOR OFFICIAL USE ONLY
SOURCE SELECTION SENSITIVE INFORMATION-SEE FAR 2.101 & 3.104
Multiple Award Construction Contract (MACC) Seed Project November 19, 2018
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 2
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 2 | Existing Conditions | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 3
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 3 | Concrete | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 4
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 4 | Masonry | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 5
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 5 | Metals | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 6
Work Request Number C115933
FOR OFFICIAL USE ONLY
Source Selection Sensitive Information—See FAR 2.101 & 3.104
| Multiple Award Construction Contract (MACC) | *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | ||
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 6 | Wood, Plastics, and Composites | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
FOR OFFICIAL USE ONLY
SOURCE SELECTION SENSITIVE INFORMATION-SEE FAR 2.101 & 3.104
Multiple Award Construction Contract (MACC) Seed Project November 19, 2018
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 7
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 7 | Thermal and Moisture Protection | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 8
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 8 | Openings | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 9
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 9 | Finishes | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 10
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 10 | Specialties | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 11
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 11 | Equipment | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 13
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 13 | Special Construction | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 14
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #:* DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 14 | Conveying Systems | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 21
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 21 | Fire Suppression | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 22
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 22 | Plumbing | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P&P of &N
Division 23
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #:* DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 23 | HVAC | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 25
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 25 | Integrated Automation | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 26
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 26 | ELECTRICAL | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | |||||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 27
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #:* DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 27 | Communications | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 28
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #:* DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 28 | Electrical Safety and Security | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 31
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 31 | Earthwork | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 32
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 32 | Exterior Improvements | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 33
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 33 | Utilities | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N
Division 34
Work Request Number C115933
| *USE 50 DIVISIONS AS DEFINED CSI's MASTERFORMAT | |
| TABLE B-2 -- PRICING WORKSHEET BACKUP | Repeat worksheet for each CSI Division of Construction as required |
DIV. #: DIVISION DESCRIPTION: QUANTITY MATERIALS LABOR (G) = (D) + (F)
TOTAL ITEM COST
| 34 | Transportation | (A) | |
| No. Units | (B) | ||
| Unit Meas. | (C) | ||
| $ Per Unit | (D) = (A) *(C) | ||
| Subtotal | (E) | ||
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| ITEM # | PRIME WORK ITEMS | ||||||
| 1 | $ - 0 | $ - 0 | $ - 0 | ||||
| 2 | $ - 0 | $ - 0 | $ - 0 | ||||
| 3 | $ - 0 | $ - 0 | $ - 0 | ||||
| 4 | $ - 0 | $ - 0 | $ - 0 | ||||
| 5 | $ - 0 | $ - 0 | $ - 0 | ||||
| 6 | $ - 0 | $ - 0 | $ - 0 | ||||
| 7 | $ - 0 | $ - 0 | $ - 0 | ||||
| 8 | $ - 0 | $ - 0 | $ - 0 | ||||
| 9 | $ - 0 | $ - 0 | $ - 0 | ||||
| 10 | $ - 0 | $ - 0 | $ - 0 | ||||
| 11 | $ - 0 | $ - 0 | $ - 0 | ||||
| 12 | $ - 0 | $ - 0 | $ - 0 | ||||
| 13 | $ - 0 | $ - 0 | $ - 0 | ||||
| 14 | $ - 0 | $ - 0 | $ - 0 | ||||
| 15 | $ - 0 | $ - 0 | $ - 0 | ||||
| 1 - PRIME SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 | ||||
| SUBCONTRACTOR(S) WORK ITEMS* | |||||||
| (Provide separate back-up for each subcontractor listed) | QUANTITY | MATERIALS | LABOR | (G) = (D) + (F) |
TOTAL ITEM COST
| (A) | ||
| No. Units | (B) | |
| Unit Meas. | (C) | |
| $ Per Unit | (D) = (A) *(C) | |
| Subtotal | (E) | |
| $ Per Unit | (F) = (A) * (E) |
Subtotal
| 1 | $ - 0 | $ - 0 | $ - 0 | |
| 2 | $ - 0 | $ - 0 | $ - 0 | |
| 3 | $ - 0 | $ - 0 | $ - 0 | |
| 4 | $ - 0 | $ - 0 | $ - 0 | |
| 5 | $ - 0 | $ - 0 | $ - 0 | |
| 6 | $ - 0 | $ - 0 | $ - 0 | |
| 7 | $ - 0 | $ - 0 | $ - 0 | |
| 8 | $ - 0 | $ - 0 | $ - 0 | |
| 9 | $ - 0 | $ - 0 | $ - 0 | |
| 10 | $ - 0 | $ - 0 | $ - 0 | |
| 11 | $ - 0 | $ - 0 | $ - 0 | |
| 12 | $ - 0 | $ - 0 | $ - 0 | |
| 13 | $ - 0 | $ - 0 | $ - 0 | |
| 14 | $ - 0 | $ - 0 | $ - 0 | |
| 15 | $ - 0 | $ - 0 | $ - 0 | |
| 2 - SUBCONTRACTOR SUBTOTAL: | $ - 0 | $ - 0 | $ - 0 |
3 - PRIME OVERHEAD ON SUBCONTRACTOR (% * Subcontractor (G)): (INSERT)% 5% $ - 0
4 - SUBTOTAL (SUM 2 + 3): $ - 0
5 - PRIME PROFIT ON SUBCONTRACTOR (% * Subtotal 4): (INSERT)% 5% $ - 0
6 - TOTAL SUBCONTRACTOR (SUM 4 +5): $ - 0
TOTAL DIVISION (SUM 1 + 6): $ - 0
&"Arial,Regular"&12&F &"Arial,Regular"&12Page &P of &N image1.png image2.png
File details come from the government source that posted it. Updated .