This amendment modifies a solicitation for renovations to two campgrounds within the Cleveland National Forest in California. The Forest Service seeks to upgrade facilities at El Cariso and Blue Jay campgrounds, including replacing picnic tables, fire rings, and barbeques. Responses to bidder questions clarify that twelve concrete picnic tables and one metal table will be provided for El Cariso, while forty-three concrete tables and seven metal tables are required for Blue Jay. Site work may require limited shrub removal with tree removal prohibited. Construction will take place with campgrounds remaining open, subject to closure on a case-by-case basis.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Copy of Copy of Schedule_of_Items_El_Cariso__Blue_Jay_Campground_Amended.xlsx | XLSX spreadsheet | |
| Copy of Copy of El Cariso Blue Jay Table Schedule Amended.xlsx | XLSX spreadsheet | |
| Amendment No. 2.docx | DOCX document | |
| Copy of Schedule_of_Items_El_Cariso__Blue_Jay_Campground_Amended.xlsx | XLSX spreadsheet | |
| Specifications_Package2.docx | DOCX document | |
| FX-30 Series Campfire Ring.pdf | ||
| Specifications_Package.docx | DOCX document | |
| Q-20 Series Charcoal Grill.pdf | ||
| Copy of Copy of El Cariso Blue Jay Table Schedule (version 1).xlsx | XLSX spreadsheet | |
| Fire Plan_67882.docx | DOCX document | |
| Wage Determination.pdf | ||
| BT238-W8 revA.pdf | ||
| 127EAW23R0027.pdf | ||
| Blue Jay Site Plan.pdf | ||
| El Cariso CG Site Plan.pdf | ||
| USFS - 104FSS - Picnic_Table_Specs.pdf |
Show all 16
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
2. AMENDMENT/MODIFICATION NUMBER
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQUISITION NUMBER |
| 5. PROJECT NUMBER (If applicable) |
| A00001 |
| 5/19/23 |
| 1094211 |
| 6. ISSUED BY |
| CODE |
| 7. ADMINISTERED BY (If other than Item 6) |
| CODE |
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONSAMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
1. CONTRACT ID CODE
| PAGE | OF PAGES |
| 1 | 2 |
USDA, Forest Service 3237 Peacekeeper Way Suite 101 McClellan Park, Ca. 95652 USDA Forest Service Construction Contracting 3237 Peacekeeper Way, Suite 101 McClellan, CA 95652
8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code)
ALL PROSPECTIVE OFFERORS
(X) 9A. AMENDMENT OF SOLICITATION NUMBER
127EAW23R0027
9B. DATED (SEE ITEM 11)
4/28/2023
10A. MODIFICATION OF CONTRACT/ORDER NUMBER
10B. DATED (SEE ITEM 13)
CODE
FACILITY CODE
The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended.
Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:
(a) By completing items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required) N/A
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
| CHECK ONE |
| A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NUMBER IN ITEM 10A. |
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not is required to sign this document and return 1 copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
GAOA Renovate El Cariso & BlueJay CGs Cleveland National Forest, California
1. See Attachment 1 to this amendment for RFIs response and information.
2. Reference Section J, Delete Attachment 10, “Specifications Package” and substitute Attachment No. 2, “Specifications Package, Revised” to this amendment.
3. Reference Section B-1,” Schedule of Items”, Delete and substitute Attachment No. 3, “Schedule of Items, Revised” to this amendment.
BIDDERS SHOULD ACKNOWLEDGE RECEIPT OF THIS AMENDMENT IN THE BID.
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (Type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print) |
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
(Signature of person authorized to sign)
(Signature of Contracting Officer)
ATTACHMENT NO. 1 RFI RESPONSE
RFI No. 1:
Specification 32 30 00 PART 2 – PRODUCTS
2.1 Picnic table shall be concrete and shall be in accordance with Division 3, Concrete. Concrete table shall be Outdoor Creations INC. Model # 104FSS with No Logo and Kahlua color, or approved equal.
The Bid Sheet under Option 1, Shows Concrete Picnic Tables Model # 114FSS, and Fire Rings Model #114FSS. See attached, page 6 and 7.
Is this a typo?
Please advise.
Please provide information.
Response:
The concrete tables are supposed to be the 104FSS table with a logo.
The specifications for the barbecue and fire pits are supposed to be the same as El Cariso Campground. Furnish and install Fire Ring. Shall be Pilot Rock INC. (Q-20 Series Charcoal Grill) or approved equal. Furnish and install Barbeque. Shall be Pilot Rock INC. (FX-30 Series Campfire Ring) or approved equal
RFI No.2.
Specification 01 11 00 Statement of Work “Includes….” and “Option 1” paragraph states:
“All metal picnic tables (PMB-8WR) calls out for metal tables. The specification below calls for Concrete Picnic Tables.
Specification 32 30 00 PART 2 – PRODUCTS
2.1 Picnic table shall be concrete and shall be in accordance with Division 3, Concrete. Concrete table shall be Outdoor Creations INC. Model # 104FSS with No Logo and Kahlua color, or approved equal.
1. Are both styles of picnic tables to be used for this project?
2. If so, how many of each style, concrete, and metal picnic tables will be required for this project?
Please provide information.
Response:
The concrete tables are supposed to be the 104FSS table with a logo. The table quantities for both campgrounds for the concrete tables are correct for all the tables for the campgrounds but the contractors will only need to order 12 concrete tables for El Cariso and the USFS will be furnishing the other 11 concrete tables and 1 will be metal prefabricated. For Blue Jay Campground the table quantity will be 43 concrete tables and 7 metal prefabricated tables.
RFI No. 3:
After reviewing the site, the Blue Jay Campgrounds, Campsite No. 29.
Can shrubbery be allowed to be removed to allow access to the campsite?
Response: Shrubbery removal is permitted by a site-by-site basis, but trees cannot be removed
RFI No. 4:
The specification shows the hours and days of the week of operation, and no work on Saturdays, Sundays, and Federal Holidays.
Does not show if the campgrounds will be off-limits to the public.
Will both campgrounds be completely closed to the public during construction? Please advise.
Response: Depending on the time of construction, site closures will be on a case-by case basis. Campgrounds will be open during construction.