This document is an Infection Control Risk Assessment (ICRA) for a construction project to update wayfinding signage on the Hines campus of the Edward Hines Jr. VA Hospital. The project, with number 578-15-008, will be managed by Jake Kanuru and is scheduled to run from October 1, 2023, to December 24, 2024.

The ICRA classifies the construction activities into four types (A-D) and four risk groups (1-4) based on the level of dust, noise, and vibration. It outlines the required actions for the contractor based on the determined project class, which ranges from I to IV. These actions include measures to minimize dust, contain waste, isolate work areas, maintain negative air pressure, and perform cleaning and disinfection at various stages of the project. The document requires signatures from the contractor, project planner, supervisor, and infection control personnel to authorize the work.

View the file

Other files

Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Update Wayfinding Signage on Hines Campus Project or Work-Order Number: 578-15-008

Project Manager or COR: Jake Kanuru Extension: 21149

Building Number: Hines Campus Floor(s)/Room(s):

Start date: 10-01-2023 Projected completion date: 12-24-2024

Construction Activity Infection Control Risk Group

☐ TYPE A: DUST LEVEL Low

Non-invasive activity, low noise, no vibration.

☐ GROUP 1: LOW

Office areas, FMS areas, all non-patient care areas.

☒ TYPE B: DUST LEVEL: Moderate to High

Small scale, short duration, low-moderate noise, low-moderate vibration.

☐ GROUP 2: MEDIUM

All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

☐ TYPE C: DUST LEVEL Moderate to High

Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration

☐ GROUP 3: MEDIUM/HIGH

ED, Radiology/MRI, admissions, food service areas, laboratories.

☐ TYPE D: DUST LEVEL High

Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration

☒ GROUP 4: HIGHEST

Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix Construction Activity Type →

Risk Group

Type

“A”

Type

“B”

Type

“C”

Type

“D”

Group 1 I II II III

Group 2 I II III IV

Group 3 I III III IV

Group 4 III IV IV IV Contractors Actions by Project Class

All personnel will have Emergency Preparedness training/posting/ID card.

CLASS

I

1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly-covered containers.

4. Clean work area upon completion of task including wiping surfaces with disinfectant.

5. Contact EMS for appropriate preparation for return to operation(s).

CLASS

II

In addition to above:

6. Post the signed ICRA at the entrance.

7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)

8. Water mist work surfaces to control dust while cutting.

9. Block off and seal supply air vents. Place filter over return/exhaust vents.

10. Place dust mat or wipe feet at entrance/exit of work area.

11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.

CLASS

III

In addition to above:

12. Install barriers to create a negative pressure ante room and/or workroom.

13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.

14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.

15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.

17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.

CLASS

IV

In addition to above:

18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.

19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.

20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.

Signatures Date

Contractor’s Signature:

(Projects Only)

Project Planner or

Maintenance Worker Signature:

Supervisor Signature:

Infection Control:

VHAHINFraidR Typewritten Text 04/12/2023

2023-04-12T10:35:04-0500
Jagadish Kanuru 380482
2023-04-12T11:30:56-0500
Richard F Fraider 3548196

File details come from the government source that posted it. Updated .