10) Infection Control Risk Assessment (ICRA).pdf

PDF 335 KB Posted

Attached to
Z1DA--Demolition: Quarters Buildings and Garages 578-17-044
Solicitation number
36C25223B0024
Issued by

About this file

This document contains an Infection Control Risk Assessment (ICRA) for a demolition and construction project at a Veterans Affairs medical facility. The ICRA outlines four levels of construction activity types from low to high risk based on dust levels and scope of work. It then determines the infection control risk group from 1 to 4 and identifies the corresponding contractor actions required for each of the four project classes. The actions include isolating work areas, installing barriers, maintaining negative air pressure, following personal protective equipment protocols, and coordinating with facility staff on cleaning and disinfection. The attached federal contract opportunity is a solicitation to perform the demolition of quarters buildings and garages identified in the ICRA, issued by the Department of Veterans Affairs Veterans Health Administration VISN 12. The solicitation number and project name and number match those listed in the ICRA.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Infection Control Risk Assessment for Construction / Renovation Projects Project Name: Demolition of Quarters Buildings/Garages Project or Work-Order Number: 578-17-044 Project Manager or COR: Lawrence Doyle Extension: 24017 Building Number: 23 – 29 and 31 - 32 Floor(s)/Room(s): All Floors Start date: 10/1/23 Projected completion date: 1/3/24

Construction Activity Infection Control Risk Group ☐ TYPE A: DUST LEVEL Low

Non-invasive activity, low noise, no vibration.

☒ GROUP 1: LOW

Office areas, FMS areas, all non-patient care areas.

☐ TYPE B: DUST LEVEL: Moderate to High Small scale, short duration, low-moderate noise, low-moderate vibration.

☐ GROUP 2: MEDIUM

All other patient care areas including general medicine floors, ultrasound, Rehab, Occupational Therapy.

☐ TYPE C: DUST LEVEL Moderate to High Requires more than one work shift (independent of working days) to complete, low-moderate noise, moderate–high vibration

☐ GROUP 3: MEDIUM/HIGH

ED, Radiology/MRI, admissions, food service areas, laboratories.

☒ TYPE D: DUST LEVEL High Major demolition and construction activities. Requires consecutive work shifts, moderate-high noise, moderate-high vibration

☐ GROUP 4: HIGHEST

Operating rooms, SPS, ICU’s, Outpatient areas, oncology, anesthesia, post anesthetic recovery, all endoscope areas, Pharmacy, Renal Dialysis

Project Class Determination Matrix Construction Activity Type Risk Group

Type “A”

Type “B”

Type “C”

Type “D”

Group 1 I II II III Group 2 I II III IV Group 3 I III III IV Group 4 III IV IV IV

Contractors Actions by Project Class All personnel will have Emergency Preparedness training/posting/ID card.

CLASS

I

1. Execute work to minimize air-borne dust dispersed into atmosphere from construction operations.

2. Immediately replace any ceiling tile displaced for visual inspection.

3. Contain construction waste before transport in tightly covered containers.

4. Clean work area upon completion of task including wiping surfaces with disinfectant.

5. Contact EMS for appropriate preparation for return to operation(s).

CLASS

II

In addition to above:

6. Post the signed ICRA at the entrance.

7. Isolate work area from patients/staff. Use appropriate temporary barriers and more permanent containment methods (i.e., seal holes in walls, tape gaps in doors, etc.)

8. Water mist work surfaces to control dust while cutting.

9. Block off and seal supply air vents. Place filter over return/exhaust vents.

10. Place dust mat or wipe feet at entrance/exit of work area.

11. Wet mop and/or vacuum w/HEPA filtered vacuum before leaving work areas.

CLASS

III

In addition to above:

12. Install barriers to create a negative pressure ante room and/or workroom.

13. Maintain negative air pressure in work area at all times until completion utilizing HEPA-equipped air filtration units.

14. Vacuum personnel with HEPA vacuum before leaving. Or, Don-Doff coveralls each time leaving work site. All wear shoe covers changed each time exiting the area.

15. Vacuum the entire work area with HEPA vacuums or wet mop with disinfectant at the completion of project.

16. Do not remove barriers until completed project is inspected by Safety, IC-Team, EMS, and Area Manager.

17. Carefully remove barriers to minimize spread of dirt and debris. Contact EMS for final clean.

CLASS

IV

In addition to above:

18. Provide a disinfectant wipe down of any tool carts or waste transports prior to leaving the containment area.

19. Do not remove barriers until terminal clean is performed inside work zone and barriers are included in the cleaning process.

20. Perform 2nd terminal cleaning after removal of barriers. Contact EMS for final clean.

Signatures Date Contractor’s Signature:

(Projects Only)

Project Planner or Maintenance Worker Signature:

4/16/23

Supervisor Signature:

4/16/23

Infection Control:

Infection Control Risk Assessment for Construction / Renovation Projects
Infection Control Risk Group
Project Class Determination Matrix
Construction Activity Type (
( Risk Group
Group 1
I
Group 4
Contractors Actions by Project Class
All personnel will have Emergency Preparedness training/posting/ID card.
CLASS
CLASS
CLASS
CLASS
Signatures
Contractor’s Signature:
(Projects Only)
Project Planner or
Maintenance Worker Signature:
Supervisor Signature:
Infection Control:

Construction Activity

2023-04-16T15:11:15-0500
LAWRENCE P DOYLE 233105
2023-04-16T15:11:46-0500
LAWRENCE P DOYLE 233105
2023-04-17T17:36:01-0500
LEENA JOSE 440414

File details come from the government source that posted it. Updated .