This is an Addendum #3 to the Coblentz Corner Phase 1 Project procurement issued by Community Strategies Group for a General Contract in Berwick, Pennsylvania. The addendum modifies specifications and drawings for structural repairs and replacement, non-structural framing, roofing, insulation, and exterior finishes. Key changes include revisions to the Contractor Qualification Statement form, insurance requirements, temporary utilities provisions, temporary project signage requirements based on RACP guidelines, and TPO membrane roofing specifications with a basic wind speed of 90 MPH and ultimate design wind speed of 115 MPH. Drawing modifications encompass updates to demolition plans, framing plans, architectural notes (upgraded to 2021 International Codes and 2020 NEC standards), site plans, door and window schedules, wall sections, and roof plans. The addendum clarifies that the Base Bid shall assume 10% of existing steel deterioration requiring replacement and that permit fees are carried by the Owner. Sealed bids were due September 15, 2026 at 1:00 PM via PennBid, with a non-mandatory pre-bid conference held August 26, 2026 at the project site (100 West Front Street, Berwick, PA), and all questions required submission through PennBid by September 8, 2026 at 5:00 PM.
The project requires a Bid Bond equal to 10% of the proposed Contract Sum and Payment and Performance Bonds each equal to 100% of the Contract Sum. The project is subject to Pennsylvania State Prevailing Wage Rate requirements, the Build America Buy America Act (BABA), RACP funding requirements, the Pennsylvania Office of the Budget Domestic Steel Products Procurement Act, and federal MBE/WBE/Section 3 Requirements of 24 CFR Part 75. The Owner retains the right to accept or reject any or all bids. Substantial Completion dates will be adjusted for weather conditions, particularly for demolition and roof replacement work, and will be evaluated considering structural steel lead times and weather coordination requirements.
View the file
Other files
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Coblentz Corner Phase 1 Addendum #3
COBLENTZ CORNER
ADDENDUM #3
09/04/26
TO PROSPECTIVE BIDDERS:
• This Addendum shall be included as part of the Contract Documents and shall supersede all drawings and specifications previously issued. Items in this Addendum apply to all drawings and specification sections, whether referenced or not, involving the portion of the Work added, deleted, modified, or otherwise addressed in the Addendum.
• Acknowledge receipt of this Addendum in the space provided on the Bid Form. Failure to do so may disqualify the Bidder.
CHANGES TO THE PROJECT MANUAL:
1. Cover Pages:
a. Added “Addendum #2: 08/31/26”.
2. Addendum #2:
a. Added Addendum #2 to the specifications.
3. Table of Contents:
a. Added “– ADD2” to the end of all added, revised, or deleted specification sections.
b. Added “Addendum #2: 08/3126”.
4. Bid Packet: A new version of a Contractor Qualification Statement is attached to this Addendum, added to the Project Manual and has been posted to PennBid under Public Notices. Bidders may upload an AIA form or the alternate form.
5. Compliance Forms:
a. The RACP Key Compliance Guidelines are added to this section and are attached to this
Addendum.
6. Section 00-73-16 Insurance Requirements:
a. Deleted 1.2.D.8. referencing “other” insurance.
7. Section 01-45-33 Code Required Special Inspections: The Owner will be responsible for contracting with and paying for a Special Inspection Agency.
8. Section 01-51-00 Temporary Utilities: Removed references to specific contracting trades. All temporary utilities are to be provided by the General Contractor and/or their subcontractors.
9. Section 01-58-13 Temporary Project Signage: Added specific language of the sign based on RACP requirements.
10. Section 07-54-23 Thermoplastic Polyolefin (TPO) Membrane Roofing: Revised as follows:
1. 2.2 ROOFING APPLICATIONS
A. TPO Membrane Roofing: One ply membrane, fully adhered, over vapor retarder and insulation.
2. B.2. 2. Wind Uplift:
b. Design Wind Speed: In accordance with local building code and authorities having jurisdiction (AHJ).
1) Basic Wind Speed: 90 MPH
2) Ultimate Design Wind Speed: 115 MPH
CHANGES TO THE DRAWINGS:
1. D401 – Demolition Roof Plan:
a. Added drawing title.
2. S101 First Floor Framing Plan and S102 Roof Framing Plan:
a. The Base Bid shall assume that 10% of the existing steel is deteriorated and must be replaced.
(NOTE: The revised drawing is NOT attached to this addendum.)
3. A001 – General Architectural Notes:
a. Revised all International Codes from 2018 to 2021.
b. Revised NFPA 70 / NEC from 2017 to 2020.
4. A002 – Site Plan:
a. Revised Drawing Title from C101 to A002.
b. Added Detail 2/A002 – Replacement Sidewalk Detail.
5. A010 – Door Notes & Schedule:
a. Door Schedule – Revised door 101/1 height to 7’-6”.
b. Door Schedule – Revised note for door 101/2.
6. A030 – Window Notes & Schedule:
a. Revised detail 1/A030 – Updated window framing and flashing details, Revised Fypon trim detail at sill.
7. A201 – Elevations:
a. 1/A201 – Added Fypon trim tags.
8. A202 – Elevations:
a. 1/A202 – Added Fypon trim tags.
9. A321 – Wall Sections:
a. Added 5/8” OSB Sheathing and Vapor Barrier on top of metal roof deck for 1, 2 and 3/A321, Deleted one layer of ½” OSB sheathing.
b. 2/A321 – Added ½” OSB sheathing on top and bottom of 2” insulation at PVC soffit.
c. 3/A321 – Revised window and sill trim detailing.
d. Added 2x10 wood blocking for future aluminum canopy support.
10. A322 – Wall Sections:
a. Added 5/8” OSB Sheathing and Vapor Barrier on top of metal roof deck for 1, 2 and 3/A322, Deleted one layer of ½” OSB sheathing.
b. 1, 2 and 3/A322 - Deleted “Parge Coating Below Veneer”
11. A323 – Wall Sections:
a. Added 5/8” OSB Sheathing and Vapor Barrier on top of metal roof deck for 1 and 2/A323.
12. A401 – Roof Plan:
a. Revised listed scale of drawing title from 1/8”=1’-0” to ¼”=1’-0”.
CLARIFICATIONS:
1. All permit fees will be carried by the Owner.
2. The bid shall assume that the entire length of the building on West Front Street is to be excavated to a depth of 5'. The excavation at columns B and C footings shall be to a depth of the existing foundation. All benching or shoring is the responsibility of the contractor. All disturbed areas are to be backfilled as indicated on the structural drawings. If unsuitable conditions are discovered during construction, they will be addressed at that time.
3. The Owner will receive permission to replace the roof flashing/termination at the adjacent building.
The Contractor will not be responsible for negotiating any agreements or any delays caused by their discussions.
4. The Substantial Completion date will be adjusted for weather conditions. It is understood that the work of demolition and roof replacement will require coordination with weather conditions.
5. The Substantial Completion date will be evaluated with the lead time for structural steel and coordination for weather conditions.
END OF ADDENDUM #3