This is a Safety Requirements Attachment for the Greens Bayou Mid-Reach Channel Conveyance Improvements (Segment 1) project at John F. Kennedy Boulevard, administered by the Harris County Flood Control District in Texas with funding from CDBG-DR/GLO. The attachment establishes mandatory heat protection and adverse weather safety requirements that must be incorporated into the project's Safety Plan. The Prime Contractor is required to include provisions protecting workers from heat-related and cold-related illnesses, with specific provisions for extreme heat conditions when temperatures or heat index exceed 90 degrees, including acclimatization measures, water availability, rest periods, and shade provisions. During extended periods of adverse weather, the Prime Contractor must provide accommodations as deemed necessary to maintain worker safety.
Vendors acknowledge and agree to comply with these heat protection safety requirements by signing the Bid Acknowledgement upon submission. This requirement applies to all weather-related safety measures throughout project execution and is a binding condition of participation in the bidding process for this Harris County Flood Control District project.
View the file
Other files
Show all 25
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Attachment FF
Heat Protection Safety Requirement
Guidance for all weather-related safety of workers, including but not limited to, extreme heat, cold weather or any adverse weather conditions shall be included in the project
Safety Plan. At a minimum, this must include provisions for keeping workers safe from heat related and/or cold related illnesses throughout the execution of their work. During extended periods of adverse weather conditions, the Prime Contractor shall provide accommodations to the workers as deemed necessary. This may include a project specific Heat Awareness Plan when temperatures reach over 90 degrees (temperature or heat index) with provisions for acclimatization, water, rest and shade.
Vendor understands by signing the Bid Acknowledgement at the time of submission that they agree to follow this heat protection safety requirement.