1-Peacock Blocks Demolition- Bid Packet.pdf
PDF 208 KB Posted
- Attached to
- Peacock Blocks Demolition
- Solicitation number
- Not on record
- Issued by
- Salt Lake County, Salt Lake City, Utah
About this file
This is an Invitation for Bids issued by the Salt Lake City Community Reinvestment Agency for the demolition of structures located at 841-865 W. 400 South in Salt Lake City, Utah. The project encompasses the complete demolition and removal of one six-plex building, three single-family homes, and associated outbuildings down to natural ground level in preparation for future development. The mandatory pre-bid meeting is scheduled for October 19, 2026, at 2:00 p.m. at the six-plex location, where bidders will receive site access and tours of all four properties. The deadline for submitting questions is October 27, 2026, at 5:00 p.m., with sealed bids due by November 4, 2026, at 5:00 p.m. Public bid opening will occur on November 4, 2026, at 5:30 p.m., and anticipated award notification is scheduled for November 6, 2026. Attendance at the mandatory pre-bid meeting is required; any bids submitted by contractors who do not attend will be rejected.
Bids must be submitted as a single lump sum contract price with itemized costs for each property and total project cost. All bidders must hold a valid Utah contractor license with appropriate classifications and provide proof of required insurance coverage, including workers' compensation as required by state law, commercial general liability of $1 million per occurrence and $2 million aggregate, commercial automobile liability of $1 million combined single limit, and professional liability of $1 million per claim and annual aggregate. The CRA must be named as an additional insured. Bid proposals cannot exceed 15 pages and must include company experience, contractor license information, project team qualifications, proposed schedule, price breakdown, and a current certificate of insurance. The contractor is responsible for obtaining all permits and permits fees, arranging and paying for third-party compaction testing, providing chemical toilet facilities, deploying storm water pollution prevention measures, and ensuring final site conditions meet specifications. Award of contract will be based on the completeness of the submittal, bidder eligibility, proposed schedule, and price.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
INVITATION FOR BIDS
Peacock Blocks Demolition 841-865 W. 400 South
October 5, 2026
INTRODUCTION
The Salt Lake City Community Reinvestment Agency (CRA) is soliciting sealed competitive bids for the demolition of a six-plex, three single-family homes, and their associated outbuildings. The full scope of work is described below.
BID SCHEDULE
• Bid Publication: October 5, 2026
• Mandatory Pre-bid Meeting: October 19, 2026, 2:00 pm
• Deadline for Questions: October 27, 2026, 5:00 pm
• Deadline for Bids: November 4, 2026, 5:00 pm
• Bid Opening: November 4, 2026, 5:30 pm
• Anticipated Award Notification: November 6, 2026
PRE-BID MEETING
The CRA’s Project Manager will host a mandatory pre-bid meeting at 2:00 p.m. on Monday, October 19, 2026. Interested bidders will meet at the six-plex located at 841–853 W. 400 South, Salt Lake City, where the Project Manager will provide access to the structures and lead site visits of all four properties. Site visits to the remaining three properties will follow directly thereafter.
No bid documents will be distributed at the pre-bid meeting; however, attendance at the pre-bid meeting is mandatory. Bids must be submitted by a Utah-licensed Contractor holding the appropriate license classification(s) to perform the work. Any bid submitted by a bidder who did not attend the mandatory pre-bid meeting will be rejected.
Questions must be submitted via email to Taylee.foulger@slc.gov no later than 5:00 p.m. on Tuesday, October 27, 2026. Any changes to the Scope of Work will be issued by addendum. If an addendum is issued, it must be acknowledged in the submitted bid for the bid to be considered responsive.
Sealed bids must be received by the Project Manager, Taylee Foulger, at Taylee.foulger@slc.gov, no later than 5:00 p.m. on Wednesday, November 4, 2026. Bids will be publicly opened and reviewed at 5:30 p.m. on November 4, 2026. Scan the QR code to attend the public bid opening.
ATTACHED DOCUMENTS
Scope of Work mailto:Taylee.foulger@slc.gov
BID SUBMITTAL INSTRUCTIONS
Bidders shall include the following information in their proposal:
• Company Experience: Provide a brief description of your company and its experience with demolition projects of similar size and scope.
• Contractor License: Provide a copy of your current Utah contractor license and license number. The bidder must hold the appropriate license classification(s) required to perform the work described in the Scope of Work.
• Project Team: Identify the key personnel who will be assigned to the project and provide a brief description of their relevant training, qualifications, and experience.
• Schedule: Provide a proposed schedule for permitting, demolition, site cleanup, and project closeout.
• Price: Provide a line-item bid showing the cost for each property and the total project cost.
• Certificate of Insurance: Provide a current Certificate of Insurance demonstrating compliance with the CRA's insurance requirements. The CRA requires its contractors to maintain the following insurance coverage through an insurance provider currently rated A- or better by A.M. Best Company or listed in the U.S. Treasury Department's current Listing of Approved Sureties (Department Circular 570), as amended:
o Workers' Compensation: As required by State law.
o Commercial General Liability: $1 million per occurrence and $2 million general aggregate. The CRA must be named as an additional insured.
o Commercial Automobile Liability: Combined single limit of at least $1 million per occurrence, or $500,000 per person, $1 million per occurrence, and $250,000 for property damage.
o Professional Liability: $1 million per claim and $1 million annual aggregate.
Bid proposals shall not exceed 15 pages in length. Please email completed bids to Taylee Foulger at Taylee.foulger@slc.gov no later than 5:00 p.m. on November 4, 2026. Bids received after the deadline will not be accepted.
SCOPE OF WORK
PART 1 – GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
A. The project Base Bid consists of demolition of a six-plex (841-853 W. 400 South), three single family homes (857, 859, and 865 W. 400 South) and associated outbuildings down to natural ground level in preparation for future development.
B. The following description is an outline of the work to be accomplished. The Scope of Work is as described in this document and any addenda issued by the Salt Lake City Community Reinvestment Agency (CRA). No drawings or technical specifications are provided. Bidders are responsible for verifying existing site conditions during the mandatory pre-bid site visit.
C. Base Bid: Demolition and removal of all existing buildings down to the lowest level of the structure, including complete removal of all above-ground and below-ground elements such as superstructures, basements, cellars, retaining walls, foundations, and footings. Demolition will proceed down to natural ground level. Demolition will include removing all utility lines and capping at the main. Following demolition, all excavated voids resulting from the removal of substructures shall be backfilled using structural, non-expansive road-base or granular borrow (Class A-1, A-1-a or A-1-b), and lot should be graded to match surrounding levels. All excavations requiring replacement fill of 24" or more shall be compacted to 90% maximum dry density.
Independent, third-party testing is required following compaction of the first lift to verify compaction methods are sufficient to achieve the required density.
CONTRACTOR will be responsible for public safety on and surrounding project properties, providing appropriate barricades or fencing for pedestrian safety during demolition. If the demolition is to take more than 10 days on any site, CONTRACTOR shall install a temporary fence around the perimeter of the property.
D. Additive Alternate: None currently.
1.2 CONTRACT METHOD
A. Perform the Work under a single lump sum contract.
1.3 CONTRACTOR USE OF PREMISES
A. CONTRACTOR shall limit use of the premises for Work, for temporary refuse storage, for temporary dumpster storage, and for access, to allow:
a. Continued operation of any adjacent buildings and businesses.
b. Public access to adjacent properties and sidewalks around the property perimeter.
B. CONTRACTOR ACCESS AND RESPONSIBILITIES
a. CONTRACTOR access to the site during demolition shall be via 400 South, with all large trucks and equipment entering and exiting the site from 400 South.
b. CONTRACTOR shall coordinate use of the premises (including electrical power, potable water, and staging the site) under direction of the CRA and the PROJECT
MANAGER.
C. Utilities: Gas and electrical services have been disconnected prior to demolition.
CONTRACTOR shall remove abandoned gas and electrical lines and connections located within the demolition area. CONTRACTOR shall remove existing water and sewer lines and cap each line at the main. CONTRACTOR shall coordinate with the appropriate utility providers or City departments as necessary to complete the work.
D. All applicable Storm Water Pollution Prevention Plan (SWPPP) measures shall be deployed to minimize silt runoff, mud, and contaminated water from leaving the site.
This shall also include daily policing and sweeping public streets and sidewalks as needed.
E. Hazardous Materials: Asbestos and other identified hazardous materials have been abated prior to demolition under a separate contract and are excluded from the Contractor's scope of work. Abatement clearance documentation will be made available to the selected Contractor upon request. Should suspected hazardous materials be encountered during demolition, Contractor shall stop work in the affected area and notify the CRA's Project Manager immediately.
F. CONTRACTOR shall assume full responsibility for protection and safekeeping of any materials and adjoining surfaces (on or off site) under this Construction Contract. As applicable, CONTRACTOR shall protect all un-affected surfaces from physical damage, spills, splatters, and chemical contamination that may occur during demolition. Perimeter sidewalks are to remain as-is and undamaged. Any sidewalk paving or curb and gutter damaged during demolition shall be replaced by the Contractor.
G. CONTRACTOR shall obtain and pay for use of additional storage or work areas needed for operations under this Construction Contract.
H. CONTRACTOR shall be responsible for obtaining and paying all permits required to complete the work. All permit fees, including those required by Salt Lake City, Salt Lake County, the State of Utah, the EPA, or other governmental entities, shall be included in the CONTRACTOR’s bid proposal.
I. CONTRACTOR shall install temporary barricades to protect the sidewalk and pedestrians from demolition activity and building materials.
J. CONTRACTOR shall install temporary fencing around the perimeter of the properties if the demolition is expected to take more than 10 days per site to complete.
K. CONTRACTOR to provide chemical toilet facilities for construction worker use during the duration of the project. Chemical toilets shall be locked at the end of each day’s activities. Impervious protection or a leak-proof containment pan shall be maintained under chemical toilet facilities to minimize the chance of cleaning solutions and human waste contaminating surrounding surfaces. Chemical toilets shall be serviced at frequent enough intervals as to limit offensive odors and maintain sanitary conditions. Chemical toilet facilities shall include hand sanitizer or hand wash stations for worker use.
Location of chemical toilet to be approved by the CRA representative for this project.
L. CONTRACTOR shall post all applicable OSHA warning signs as required.
M. All concrete shall be demolished and removed from site. This includes all building footings and foundations, all interior sidewalk paving, and all slabs-on-grade. After removal, the excavations shall be filled in with structural, non-expansive road-base fill or granular backfill borrow (Class A-1, A-1-a or A-1-b). All excavations requiring replacement fill of 24" or more shall be compacted to 90% maximum dry density. Independent, third-party testing is required following compaction of the first lift to verify compaction methods are sufficient to achieve the required density. CONTRACTOR shall be responsible for arranging and paying for all required third-party testing, and the cost of such testing shall be included in the CONTRACTOR’s bid. The intent is to leave the site in a leveled condition with no monolithic concrete chunks, potholes, low spots, or truck tire ruts. No additional fill shall be imported to the site beyond what is needed for filling in the excavations. Upon completion of the work, CONTRACTOR shall clean up any remaining debris and remove from site, including sweeping all sidewalk areas and curb and gutters affected by or dirtied by the work.
N. Bidders shall provide a proposed project schedule identifying the anticipated start date and duration for permitting, demolition, cleanup, and closeout. The proposed schedule will be considered as part of the bid evaluation. The final project schedule and site access plan shall be coordinated with the CRA prior to commencement of work. Award of contract will be based on the completeness of the bidder's submittal, bidder eligibility (Utah contractor license and insurance), the proposed schedule, and price.
1.4 OCCUPANCY DURING DEMOLITION
A. The sites are currently vacant with all structures empty and unoccupied. Hazardous material abatement has been completed.
1.5 FINAL SITE CONDITION
A. Upon completion, all four properties shall be free of structures, foundations, slabs, debris, equipment, temporary facilities, and construction materials. Excavated areas shall be properly backfilled and compacted, and the sites shall be left level, stable, and free of significant depressions, ruts, debris, or other hazards. Sidewalks, curbs, gutters, and adjacent public rights-of-way shall be clean and free of construction debris. The CRA shall conduct a final walk-through inspection of all four properties prior to final payment.
CONTRACTOR shall correct any deficiencies identified during the final inspection to the satisfaction of the CRA before final payment is made.