511/263214. JLM; Alpena CRTC - Semi-Improved Strip
Solicitation number
RFP 171 260000002178 5
Issued by
Allegan County, Michigan

About this file

This is a Project Statement prepared by the Michigan Department of Technology, Management and Budget (DTMB) for the Alpena Career and Re-Entry Training Center (CRTC) semi-improved strip project. The project involves the development and improvement of a semi-improved airstrip facility at the Alpena CRTC. The statement outlines the scope of work required to bring the airstrip to operational standards, including site preparation, surface treatment, drainage improvements, and associated infrastructure work. The project is identified under contract opportunity 511/263214.JLM and is being undertaken as a capital improvement initiative by the State of Michigan. Specific details regarding response dates, bidder meetings, site visits, contract term, and renewal options are not explicitly detailed in the project statement summary provided.

Pricing terms, set-aside provisions, incumbent contractor information, and detailed funding sources are not specified in the available project statement documentation. The project appears to be a capital construction or improvement undertaking for a state-operated training facility, likely funded through Michigan state appropriations or grants designated for workforce development infrastructure. Additional financial details, procurement procedures, and contracting mechanisms would be contained in the formal solicitation documents accompanying this project statement.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DTMB-0427 (R 04/26)

PROJECT STATEMENT

STATE OF MICHIGAN

DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET

State Facilities Administration

Design and Construction Division 3111 West St. Joseph Street

Lansing, Michigan 48909

FILE NUMBER

511/26324.JLM

PROPOSAL DUE DATE

July 16, 2026

CLIENT AGENCY

Military and Veterans Affairs - Air National Guard (ANG)

PROJECT NAME AND LOCATION

TDVG242013 - Construct Semi-Improved Assault Strip, Alpena Combat Readiness Training Center PROJECT ADDRESS (if applicable) 5884 A Street, Alpena, MI 49707

CLIENT AGENCY CONTACT

Capt Cade MacArthur

TELEPHONE NUMBER

989-354-6496

DTMB - DCD PROJECT DIRECTOR

Josiah L. Meyers

TELEPHONE NUMBER

517-614-7705

WALK-THROUGH INSPECTION DATE, TIME, AND LOCATION:

Tuesday, June 23, 2026 @ 9:30 a.m. ET at building 2 located at the Alpena Combat Readiness Training Center, 5884 A Street, Alpena, MI 49707.

MANDATORY (Check box if Mandatory)

LEIN CHECK For access to Alpena CRTC, an “Entry Access List” (EAL) form will need to be completed by the prospective contractor prior to being admitted to the base. The completed EAL form (attached to this solicitation) should be submitted to the Project Director, Josiah Meyers a minimum of 7 days prior to the site meeting via email MeyersJ11@michigan.gov.

NOTE: An individual is only permitted to represent one bidder at a mandatory walk-through.

PROJECT DESCRIPTION/SERVICES REQUESTED:

The Department of Technology, Management and Budget (DTMB) on behalf of Michigan Department of Military and Veterans Affairs (DMVA), Michigan Air National Guard (MIANG), is requesting professional architectural and engineering services to perform Phase 300-700 Professional Services at the Alpena Combat Readiness Training Center (CRTC), Alpena, Michigan. The intent of this selection process is to contract with a qualified firm to provide ad-hoc professional services to design an approximately 3,500 ft Semi-Improved Assault Landing Strip with a 300 ft runoff on each end for ANG REDHORSE units to construct as a troop-training project. All design submittals must incorporate and meet the requirements of ANGETL 24-02, ANG Design Objectives and Procedures.

Design Submittal Phases: Complete design submittal package for each of the following phases/milestones:

• Phase 300 (A-2, 35% Design Submittal)

• Phase 400 (B-1, 65% Design Submittal)

• Phase 500 (B-2, 100% Pre-Final Design Submittal)

• Phase 500 (B-3, 100% Final Design)

Reference attached Statement of Work (SOW) for full design scope of work.

DMVA has budgeted $3,000,000 for construction of this project.

mailto:MeyersJ11@michigan.gov

Additional Requirements:

• Cost Estimates: An updated detailed cost estimate must accompany each design submittal

• Conduct geotechnical investigation & testing

• Comprehensive topographical site survey

• Phase 600/700 Construction Administration – Not Required

Please NOTE:

• Proposal responses MUST be uploaded to SIGMA VSS.

https://sigma.michigan.gov/PRDVSS1X1/Advantage4

• Please enter the total cost for all phases as the bid amount.

• Firms are encouraged to combine their technical and cost proposals into one (1) attachment for proposal submission.

• Please remember that attachments can be no larger than 25mb.

• Do not wait until just before the 2:00 p.m. solicitation deadline to submit your proposal response.

SIGMA VSS will not allow a proposal to be submitted after 2:00 p.m., even if a portion of the proposal response has been uploaded.

• If you experience issues or have questions regarding your electronic submission, you must contact the SIGMA Help Desk for assistance prior to the 2:00 p.m., solicitation deadline. You may contact the SIGMA Help Desk by telephone at 517.284.0540 or toll-free at 888.734.9749. You may also email the SIGMA Help Desk at sigma-procurement-helpdesk@michigan.gov

• Please email the Design and Construction Contract Specialists if you are having SIGMA VSS issues. Please include your SIGMA ticket number and any supporting documentation (i.e., screenshots) to Anne Watros (WatrosA@michigan.gov) and Don Klein (KleinD4@michigan.gov).

• You may be asked by our contract specialists to email your proposal. Emailed submissions will require DCD approval and will be handled on a case-by-case basis.

• Approved emailed submissions MUST be received prior to 2:00 p.m. deadline to be considered responsive and responsible.

• Responses should not be emailed to the Project Director.

NIGP CODES

92533, 92517, 90607, 90606

DESIRED SCHEDULE OF WORK

Contract Award: September 2026 Design: October 2026 – June 2027 Purchase Materials: July – September 2027 (Pending availability of funds) Construction: TBD

ACCEPTING RFP QUESTIONS UNTIL:

Please do not submit online questions via VSS. ALL questions should be emailed to Josiah Meyers at meyersj11@michigan.gov address no later than 2:00 p.m., Eastern on Thursday, July 9, 2026.

REFERENCE STANDARDS: This project will comply with all codes, standards, regulations, and workers' safety rules that are administered by federal agencies (EPA, OSHA, and DOT), state agencies (DCH, EGLE, DNR, and MIOSHA), and any other local regulations and standards that may apply.

• ANGETL 24-02, ANG Design Objectives and Procedures

• All Applicable Unified Facilities Criteria (UFC’s)

• See Statement of Work for Additional Requirements

This form is required to be a part of the professional service contract. (Authority: 1984 PA 431) Attachment(s):

• 2-Architect-Engineer Statement of Work (SOW)

• 3-ANGETL 24-02, ANG Design Objectives and Procedures

• 4-Entry Access List (EAL) Form

• 5-FY25 Dirt LZ Proposed Siting

• 6-FY25 Dirt LZ Constraints https://sigma.michigan.gov/PRDVSS1X1/Advantage4 mailto:sigma-procurement-helpdesk@michigan.gov mailto:WatrosA@michigan.gov mailto:KleinD4@michigan.gov mailto:meyersj11@michigan.gov