1. AL-1873-9868_SOW.pdf
PDF 1 MB Posted
- Attached to
- BPM Cables (Semi Rigid) for ALS-U
- Solicitation number
- AA-2026-04
- Issued by
-
Department of Energy
About this file
This is a Statement of Work (SOW) for the Advanced Light Source Upgrade (ALS-U) project at Lawrence Berkeley National Laboratory, defining procurement requirements for approximately 1,120 semi-rigid coaxial Beam Position Monitor (BPM) jumper cable assemblies for the upgraded Storage Ring.
The supplier must manufacture, assemble, test, and deliver cable assemblies in three configurations: 525mm low-loss PTFE 141 cables, 650mm low-loss PTFE 141 cables, and an optional (525–725)mm variable-length configuration. All assemblies must feature right-angle SMA connectors rated to 200°C, operate across 0.05–18 GHz frequency range, maintain impedance control within ±10 picoseconds, achieve insertion loss (S21) ≥0.97 at 500MHz with ±0.0015 tolerance, and withstand vacuum bake-out at 200°C without degradation. Non-magnetic materials with permeability μ≤1.08 are required. Each cable must be labeled with color-coded heat shrink sleeves (Blue, Red, Green, White) at 80mm from connectors using format Item-C-XXXX with sequential serial numbering. Delivery comprises a first article (8 units) within 6 weeks, Production Batch 1 (92 units) within 6 weeks following first article approval, and Production Batch 2 (1,024 units) within 12 weeks following batch 1 approval. Hold points of 2 weeks and 12 weeks allow LBNL inspection and installation testing. The supplier must perform 100% testing including visual inspection, TDR length verification, VNA S21 measurement, magnetic permeability verification, and connector quality assessment. Comprehensive documentation requirements include detailed engineering specifications, inspection reports for each cable, certification of 200°C conformance, and submission via the Windchill project portal. Quality assurance obligations include maintaining an effective QA program, completing the ALS-U Supplier Quality Evaluation Survey (AL-1208-0209), submitting deviation requests for approval, and reporting nonconformances within 3 business days with LBNL disposition required before any rework or use-as-is decisions.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 8. Response to Questions 1 - RFP AA-2026-04.pdf | ||
| 2. AL-1816-4231_ACL.pdf | ||
| 5. Price Proposal Schedule, Attachment A RFP AA-2026-04.xlsx | XLSX spreadsheet | |
| 6. Past Performance Reference Information Form, AA-2026-04.docx | DOCX document | |
| 0. RFP, AA-2026-04.pdf | ||
| 4. Rep Cert Form, AA-2026-04.docx | DOCX document | |
| 3. Sample Subcontract, AA-2026-04.pdf | ||
| 7. ALS-U Supplier Quality Evaluation Survey, RFP AA-2026-03.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SOW: SR BPM Semi-Rigid Jumper Cables
Changchun Sun
Release Date: Mar 30 2026 2:36:52 PM PDT
Document Number: AL-1873-9868 Revision: B
Document Status: Released
Document Type: PROJECT MANAGEMENT
Category Code: AL7002
ALS-U - GENERAL
PROJECT MANAGEMENT
O ffi ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
Downloaded by: Changchun Sun at April 02, 2026 08:42:57
AL-1873-9868 Rev. B Doc. Status: Released Page 2 of 17
Advanced Light Source Upgrade Project Lawrence Berkeley National Laboratory
All officially released LBNL documents are watermarked and contain LBNL Document
Control Center release information in the lower-left corner of the document's pages.
Printed hard copies of this document are for reference only.
Table of Contents
Revision History
Approvals
Abbreviations and Acronyms
1 Introduction
1.1 Project Overview
1.2 Description and Requirements
1.3 Roles and Responsibilities
2 Scope of Work
3 Deliverables and Schedule
3.1 Deliverables
3.2 Schedule
3.3 First article
3.4 Production
3.5 Verification summary
4 Management
4.1 Reporting/Communication requirements
4.2 Documentation requirements
4.3 Reviews
4.4 Hold points and what’s required
5 Engineering
5.1 General engineering requirements
5.1.1 The supplier shall provide/supply/manufacture/fabricate
5.1.2 Interface Control Documents reference and detail
6 Fabrication (as applicable)
6.1.1 Build per LBL-xxx process, industry spec., etc
6.1.2 Special production instructions
7 Shipping, Handling, and Storage
7.1 Packaging
8 Quality Assurance
8.1 Quality reporting requirements
8.1.1 Subcontractor Quality program
8.1.2 Deviation requests
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 3 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
8.1.3 Nonconformance reports
8.2 Work Instructions
8.3 Factory Inspection and Test Plan
8.4 ACL upon receipt at LBL
8.5 Other QA documents
9 Applicable Documents
10 References
Appendix A: Verification Table
(To be completed by delivery date)
Appendix B:
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 4 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
REVISION HISTORY
Rev. CM Number Description of Change A Initial Release B Update the Procurement Option for Batch production
APPROVALS
The following individual(s) shall approve this document:
Approver Project Role Changchun Sun CAM Alessandro Ratti Electrical System Lead Jiani Niu Q&A Manager Windchill Approved / Concurred By aratti,jianiniu
ABBREVIATIONS AND ACRONYMS
ALS Advanced Light Source ALS-U Advanced Light Source Upgrade LBNL Lawrence Berkeley National Laboratory University The Regents of the University of California ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 5 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
1 INTRODUCTION
1.1 Project Overview
ALS-U is an upgrade project to the LBNL Advanced Light Source (ALS). The ALS will be upgraded with a Multibend Achromat (MBA) lattice design to provide a soft x-ray source with orders of magnitude increase in brightness and coherence.
This SOW defines the procurement of critical Beam Position Monitor (BPM) jumper cable assemblies required for the upgraded Storage Ring (SR). These semi-rigid coaxial cables are essential for transmitting high-frequency signals from BPM pickups with minimal loss and distortion, ensuring accurate beam position measurement.
The cable assemblies shall be suitable for accelerator environments and must withstand vacuum bake-out temperatures up to 200 °C without degradation of mechanical or electrical integrity.
1.2 Description and Requirements
The purpose of this SOW is to define the requirements for the supplier to manufacture, test, and deliver a total of about 1,120 high-frequency, low-loss semi-rigid 141 coaxial cable assemblies with right angle SMA connectors for the ALS-U Storage Ring BPM system. The BPM jumper cable assembly must meet the following project-specific requirements:
• Precisely controlled impedance and phase matching (+-10 picosecond) to support
BPM measurement accuracy
• Low insertion loss at required operating frequencies 0.05 – 18 GHz to maintain signal integrity (S21 > 0.97 and +- 0.0015 at 500MHz)
• Vacuum bake-able at temperatures up to 200 deg C, with no degradation in electrical or mechanical performance
• Cable and connectors must be non-magnetic, with magnetic permeability μ ≤ 1.08.
• Right-angle SMA connectors on both ends, rated up to 200 deg C
• Mechanical formability and dimensional tolerances compatible with limited space constraints
1.3 Roles and Responsibilities
• University Procurement Representative: See subcontract for details.
• University Technical Representative: See subcontract for details.
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 6 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
• Supplier Project Manager: The selected subcontractor shall identify a single point of contact to interface directly with the LBNL Technical Representative for all technical, programmatic, and schedule matters.
2 SCOPE OF WORK
The supplier shall manufacture, assemble, test, label, document, and deliver the cable assemblies as specified herein and in the attached Applicable Documents. The scope includes:
• Production of assemblies with respective lengths and quantities
• Sourcing and use of low-loss semi-rigid PTFE 141 cable conforming to standard specification and rated at 200 deg C
• Sourcing and use of right angle SMA connectors rated at 200 deg C
• Generating and submitting a First Article Inspection Report (FAIR) for LBNL approval prior to full production.
• Performing 100% production testing per the attached Acceptance Criteria List
(ACL).
• Providing all required test and inspection results together with final cable delivery.
3 DELIVERABLES AND SCHEDULE
3.1 Deliverables
The primary deliverables are the 1,120 tested and accepted cable assemblies. Supporting deliverables include the FAIR, test results, and shipping documents as listed in the table below.
525 mm Low-loss semi-rigid 141 cable:
• Frequency: 0.05 - 18 GHz ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 7 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
• Length: 525 mm -/+ 10 ps
• Connector P1: SMA, Plug, Miter Right Angle
• Connector P2: SMA, Plug, Miter Right Angle
• Cable Type: low-loss PTFE semi-rigid 141 cable
• Label: Located at 80mm from the connectors. Black text printed on color-coded heat shrink sleeves: Blue, Red, Green, and White, represented by the letters “B,”
“R,” “G,” and “W” respectively. Each label’s format is Item-C-XXXX, where C is the color code and XXXX is the serial number, starting at 0001 and incrementing sequentially for each color. Each item shall be supplied in four colors, with equal quantity for each color.
650 mm Low-loss semi-rigid 141 cable:
• Frequency: 0.05 - 18 GHz
• Length: 650 mm -/+10 ps
• Connector P1: SMA, Plug, Miter Right Angle
• Connector P2: SMA, Plug, Miter Right Angle
• Cable Type: low-loss PTFE semi-rigid 141 cable
• Label: Located at 80mm from the connectors. Black text printed on color-coded heat shrink sleeves: Blue, Red, Green, and White, represented by the letters “B,”
“R,” “G,” and “W” respectively. Each label’s format is Item-C-XXXX, where C is the color code and XXXX is the serial number, starting at 0001 and incrementing sequentially for each color. Each item shall be supplied in four colors, with equal quantity for each color.
(525 – 725) mm Low-loss semi-rigid 141 cable: (Option)
• Frequency: 0.05 - 18 GHz
• Length: (525 – 725) mm -/+10 ps
• Connector P1: SMA, Plug, Miter Right Angle
• Connector P2: SMA, Plug, Miter Right Angle
• Cable Type: low-loss PTFE semi-rigid 141 cable
• Label: Located at 80mm from the connectors. Black text printed on color-coded heat shrink sleeves: Blue, Red, Green, and White, represented by the letters “B,”
“R,” “G,” and “W” respectively. Each label’s format is Item-C-XXXX, where C is the color code and XXXX is the serial number, starting at 0001 and incrementing ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 8 of 17
All officially released LBNL documents are watermarked and contain LBNL Document sequentially for each color. Each item shall be supplied in four colors, with equal quantity for each color.
Item No
Item Label Qty Delivery Schedule
1 SMR141-525MM
SMR141-525MM-C-xxxx
First Article, within 6 weeks ARO or sooner
2 SMR141-650MM
SMR141-650MM-C-xxxx
First Article, within 6 weeks ARO or sooner
3 SMR141-525MM
SMR141-525MM-C-xxxx
Production Batch 1, within 6 weeks or sooner upon the first article approval
4 SMR141-650MM
SMR141-650MM-C-xxxx
Production Batch 1, within 6 weeks or sooner upon the first article approval
SMR141-
(Length)MM (Options)
SMR141-(Length)MM-C-xxxx
Production Batch 2, within 12 weeks or sooner upon the first batch approval
Note: The quantity listed in the table for each item represents the total number of cables, which are divided into four color-coded label groups: Blue (B), Red (R), Green (G), and White (W). Each color group must contain the same number of cables. To determine the quantity for each color, divide the total number of cables by four.
3.2 Schedule
• Line Items 1 and 2 shall be delivered within 6 weeks ARO or sooner as the first article
• A Hold Point (Hold Point 1) of 2 weeks will be established in accordance with section 4.4 to allow LBNL team to inspect and test the first article
• Line Items 3 and 4 shall be delivered within 6 weeks or sooner as production batch 1 delivery upon the first article approval (Hold Point 1)
• A second Hold Point (Hold Point 2) of 12 weeks is established in accordance with section 4.4 to allow LBNL team to install and test the cables delivered from the batch 1
• Line Item 5 corresponds to Production Batch 2. The scope will be selected from the Option Table below based on the installation and testing results from Hold
Point 2. The total quantity for the selected options shall be 1,024 units. The selected options shall be delivered within twelve (12) weeks following completion and approval of Hold Point 2.
Option Table for Production Batch 2 ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 9 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
Options Length Qty
525MM - 575MM
0-100 101-200 201-300 301-400 401-500 500+
575MM – 625MM
0-100 101-200 201-300 301-400 401-500 500+
625MM- 675MM
0-100 101-200 201-300 301-400 401-500 500+
675MM-725MM
0-100 101-200 201-300 301-400 401-500 500+
3.3 First article
The first article shall be completed, tested, and approved prior to commencement of production. The supplier shall inspect and test all unit of each part number against all requirements of this SOW. The first article and associated test results shall be delivered to LBNL for review. The first article must be approved in writing by the LBNL Technical and QA representatives before full production proceeds.
3.4 Production
Production shall not commence until LBNL has granted approval of the first article. A hold period of two (2) weeks is anticipated, in accordance with Section 4.4, to allow
LBNL to perform inspection and testing.
Upon receipt of written approval, production may proceed in two batches. A hold point shall be established between the two batches. A hold period of twelve (12) weeks is anticipated, in accordance with Section 4.4, to allow LBNL to install and test the cable assemblies from the first batch.
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 10 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
All production units shall undergo 100% testing in accordance with Section 8.3 and the attached ACL.
3.5 Verification summary
At the time of delivery, the supplier shall follow the instructions in Appendix A; print and complete the table with the correct information. Attachments may be added if needed for further explanations.
4 MANAGEMENT
4.1 Reporting/Communication requirements
• Kick-off Meeting: A virtual meeting within one week of contract award.
• First article submission & Review: Electronic submission via Windchill, followed by a review meeting if discrepancies are found.
• Regular Updates: Monthly email updates from the supplier's Project Manager to the LBNL Technical Representative, summarizing progress against schedule and highlighting any issues.
• Final Delivery Notification: Immediate notification upon shipment, with tracking information and electronic copies of shipping documents.
4.2 Documentation requirements
Upon subcontract award, a Windchill Project portal will be established by LBNL and access provided to the subcontractor. Windchill will be used as the repository for all documentation, QA data, certificates of conformance, test results, models, and drawings.
An electronic copy of all required documentation as noted in this document is required and shall be transmitted to LBNL via the designated Windchill portal. LBNL document
AL-1265-6612: ALS-U BUILD TO SPECIFICATION CAD MODEL AND DRAWING
REQUIREMENTS, identifies the acceptable file formats and requirements for the final drawings and CAD models.
Acceptable document formats include .docx, .xlsx, and other editable Office file formats or as noted in this document.
4.3 Reviews
The First Article production review is required. The LBNL Technical Representative will review the submitted documentation and provide written approval or comments.
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 11 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
The LBNL technical representative will work with the sub-contractor to establish an appropriate timeline and location for all reviews. Reviews may be conducted at either the subcontractor’s or the LBNL site or via web/video conference tools. External, non-
LBNL reviewers may be included at LBNL’s discretion.
4.4 Hold points and what’s required
Written approval from LBNL is required to proceed beyond any identified hold points.
Hold Point 1: Production Batch 1 Release
• Location: After the first article delivery completion, prior to the production Batch
1.
• Period: LBNL is expected to require up to 2 weeks to inspect and test the first article
• Requirement: Written approval from the LBNL Technical Representative
Hold Point 2: Production Batch 2 Release
• Location: After the production batch 1 delivery completion, prior to the production batch 2.
• Period: LBNL is expected to require up to 12 weeks to install and test the production batch 1
• Requirement: Written approval from the LBNL Technical Representative with the selected option
5 ENGINEERING
5.1 General engineering requirements
Document Number
Title
Vendor specified Vendor specified
Vendor shall supply a detailed engineering specification and document for cable and connector assembly for review before the production
5.1.1 The supplier shall provide/supply/manufacture/fabricate ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 12 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
The cable assemblies as described in this SOW and the attached Applicable Documents.
5.1.2 Interface Control Documents reference and detail
The interface between this jumper cable and other subsystem vacuum, magnet and prestaging are defined in ICD AL-1162-3557
6 FABRICATION (AS APPLICABLE)
6.1.1 Build per LBL-xxx process, industry spec., etc.
• Cable assemblies shall be built per vendor internal standards.
• Bulk cable shall be procured and shall conform to standard RF cable requirement.
• Cable connector shall be procured and shall conform to the standard SMA connector
6.1.2 Special production instructions
• Labeling: Each assembly shall have a permanent color coded heat shrink label, located at 80mm from each connector. The label shall contain the assembly Item
Number and a unique serial number.
• Material: supplier specified.
• Length: Assemblies shall be measured and verified center line to center line.
7 SHIPPING, HANDLING, AND STORAGE
7.1 Packaging
Standard packaging is acceptable. Assemblies must be packaged to prevent physical damage, connector crushing, or bending beyond the cable's minimum bend radius during transit.
8 QUALITY ASSURANCE
8.1 Quality reporting requirements
8.1.1 Subcontractor Quality program
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 13 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
The subcontractor shall complete the ALS-U Supplier Quality Evaluation Survey (AL-
1208-0209).
The subcontractor shall maintain and apply an effective QA program for the design, manufacture, testing of all systems and equipment provided
Post-award surveys may be required and shall be supported.
The supplier's quality program is referenced in their Quote and Terms and Conditions
8.1.2 Deviation requests
Any deviations from the dictating LBNL documents must be requested by the subcontractor and approved by LBNL prior to implementation. LBNL will provide a standard deviation request form however, a subcontractor’s existing or internal document may be utilized with LBNL approval.
Deviation requests apply to requests to modify processes or documented drawings.
Deviation requests DO NOT apply to hardware that is built and does not conform to the specification.
Any proposed deviation from this SOW or its Applicable Documents requires a written request and LBNL's written approval prior to implementation.
8.1.3 Nonconformance reports
A nonconformance report provides a summary for products or procedures which do not conform to the defined requirements. Nonconformances may be determined and reported by either the subcontractor or LBNL staff. LBNL will provide a standard nonconformance report form however, a subcontractor’s existing or internal document may be utilized with LBNL approval. Nonconformance reports are to be submitted to
LBNL within 3 business days of the identification.
Nonconformance reports apply to hardware that is built and does not conform to the specification(s). LBNL will provide a written disposition establishing a path forward for each nonconformance. No operations may be performed on the nonconforming item without LBNL’s written disposition or approval to proceed.
Any unit failing the tests in the ACL (Section 8.3) shall be documented on a
Nonconformance Report (NCR). NCRs shall be submitted to LBNL within 3 business days of identification. No disposition (rework, scrap, use-as-is) shall be executed without LBNL's written approval.
8.2 Work Instructions
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 14 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
The supplier shall use their own work instructions for assembly and testing, provided they meet the requirements herein.
8.3 Factory Inspection and Test Plan
The supplier shall perform and document 100% testing of every cable assembly as detailed in the table:
• Visual/Label Inspection: Verify correct labeling.
• Length Verification: Measure using TDR
• S21 (Insertion Loss) Measurement: Measure using VNA across 0.05-18 GHz.
• Verify the magnetic permeability with μ ≤ 1.08
• Connector/Termination Quality: Verify using TDR for impedance integrity
ITEM
NO.
CHARACTERISTIC OR
TEST TO BE
CONDUCTED,
VERIFIED or
WITNESSED
VERIFYING
ENTITY
VERIFICATION
REPORT/ INSPECTION
DATA
1.
Visual inspection:
Check if the cables are correctly labeled and match specifications
Check there is no damage to the cable
Vendor
2.
Measure the length with
TDR. The length shall be within +-10 ps
Vendor
3.
Measure S21 coefficient with VNA. Shall be >= 0.97 and +- 0.0015 at 500 MHz
Vendor
4.
Measure the magnetic permeability for cable and connectors with μ
≤ 1.08
Vendor
5.
Verify connector type.
Measure connector and termination quality with
TDR. Shall be no fault
Vendor ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 15 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
The subcontractor shall provide an Inspection and Test Plan which shall be submitted to the LBNL technical representative for written approval by ALS-U Quality Assurance prior to its required use.
This Inspection and Test Plan shall consist of a plan in the subcontractor’s format listing components, subassemblies, and assemblies; identifying inspections and tests planned for the verification of quality; and identifying documentation/planning for recording the results.
8.4 ACL upon receipt at LBL
The ACL (AL-1816-4231) will be used by LBNL to evaluate and accept all deliverables.
8.5 Other QA documents
Certification of conformance to the 200 °C temperature requirement shall be provided by the vendor and will be inspected by LBNL in accordance with the ACL.
9 APPLICABLE DOCUMENTS
This section identifies applicable documents that are considered to be a part of this document. All information contained in an applicable document shall be valid to the full extent, unless specifically noted within this document. Applicable documents shall be obtained from the LBNL Document Control Center (DCC).
Document Number
Title
AL-1816-4231 SR BPM Jumper Cable Acceptance Criteria List (ACL).
10 REFERENCES
Documents listed in this section are considered reference documents that can be used to better describe, clarify intent, or provide information where the information was obtained from.
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 16 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
APPENDIX A: VERIFICATION TABLE
(To be completed by delivery date)
This appendix summarizes the final set of subcontractor deliverables which are due to LBNL in addition to the other deliverables listed in section 3 above. It is the lab’s expectation that as a final action, the subcontractor will print out this page, and complete the “Complete? (Y/N)” column as part of the completed delivery package. For any “N” (no) response, an explanation in the comments section below shall be provided as to why that deliverable is not complete. It is then up to LBNL to accept the deliverable as is through a waiver, or work with the subcontractor for completion of the task before acceptance of the final delivery.
Item Section Item Complete?
(Y/N)
1 5.1 Detailed engineering specification and document
2 8.3 Inspection report for each cables
3 8.5 Certification of conformance to the 200 °C x N/A
All Government Furnished Property (GFP) and/or materials purchased by LBNL for this project have been returned to and received by LBNL
Comments:
Attachments:
ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
AL-1873-9868 Rev. B Doc. Status: Released Page 17 of 17
All officially released LBNL documents are watermarked and contain LBNL Document
APPENDIX B:
< Text goes here > ci al ly R el ea se d
To th e
LB
N L
D oc um en t C on tr ol
C en te r
Re le as ed
: M ar ch
0t h, D
C C
A ut h K ey : I
YR
Q
H N
W S0
File details come from the government source that posted it. Updated .