1-BID PACKAGE SU-25-005 FINAL rev 2.10.2026.pdf

PDF 8 MB Posted

Attached to
INVITATION TO BID: Stream Stabilization Project at 454 Fairman Road, Muncy Valley, PA 17758 - SU-25-001
Solicitation number
Not on record
Issued by
Susquehanna County, Pennsylvania

About this file

This bid package is for an Emergency Watershed Protection Program stream stabilization project issued by the Sullivan County Commissioners in partnership with the Natural Resources Conservation Service (NRCS) and the Department of Environmental Protection (DEP). The project involves stream bank stabilization at 899 Nordmont Road, Muncy Valley, Pennsylvania 17758, including the installation of 164 feet of grouted R-8 riprap, stream diversion and dewatering work, tree removal, and topsoiling with permanent seeding and mulching of disturbed areas. The project is divided into five lump sum bid items: mobilization and demobilization, stream diversion and dewatering, grouted and non-grouted R-8 riprap installation, topsoiling and seeding, and tree removal. A mandatory pre-bid showing is scheduled for Wednesday, March 18, 2026, at 11:00 AM at the Davidson Township Building in Muncy Valley, Pennsylvania. Sealed bids must be submitted electronically via PennBid by 4:00 PM on Friday, April 3, 2026, with bids to be opened on Tuesday, April 7, 2026, at 10:00 AM at the Sullivan County Courthouse in Laporte, Pennsylvania. The performance period is 14 days upon delivery of the Notice-to-Proceed, with a maximum workweek of 10 hours per day, Monday through Friday, excluding Federal Holidays. All in-stream work must be completed between June 1 and September 30, 2026, unless a variance from the PA Fish and Boat Commission is obtained.

Each bidder must submit a bid bond or certified check equal to 10% of the total bid amount made payable to Sullivan County. The successful bidder must provide a performance bond and payment bond, each in the amount of 100% of the contract value, within ten business days of contract award. The contractor is responsible for furnishing all equipment, labor, materials, supplies, and required borrow and disposal sites, subject to inspector approval. Quality assurance inspection will be provided by NRCS and/or the Sullivan County Conservation District, with all materials requiring pre-use approval. The project is subject to Pennsylvania Prevailing Wage Project Rates as published by the Department of Labor and Industry. Funding is provided through the NRCS Emergency Watershed Protection Program and the Department of Environmental Protection, with the Sullivan County Commissioners serving as the sponsor and responsible party for all contracting documents, awards, payments, bonds, insurance, and warranties.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SU-25-005 Page 1 of 1

DSR NO. SU-25-005

EMERGENCY WATERSHED PROTECTION PROGRAM

BID PACKAGE

I. Bid Package Documents:

A. Bid Schedule B. Location Map C. Workplan Drawings D. Construction Details E. Items of Work F. Erosion and Sedimentation Control Guidelines for Emergency Projects G. Technical Specifications

II. General Bid Information:

A. The project is being prepared for the landowners along the stream. Funding is being provided through the Natural Resources Conservation Service’s (NRCS) Emergency Watershed Protection Program and the Department of Environmental Protection (DEP).

B. The Sponsor for this project is the Sullivan County Commissioners, all contracting documents including award, payments, bonds, insurance, warranties, etc. will be according to the Sponsor’s requirements.

C. All line items shall be bid lump sum.

D. Performance time is 14-days upon delivery of the Notice-To-Proceed. The maximum workweek that will be approved is 10 hours per day, 5-days per week, Monday -Friday. Work shall not take place on Federal Holidays.

E. NRCS and/or the Sullivan County Conservation District shall provide quality assurance inspection for the work, all materials shall be approved by the inspector prior to use.

F. The contractor shall provide all equipment, labor, materials, and supplies necessary to complete the work.

G. The contractor shall provide all required borrow and disposal sites if required. All such sites are subject to approval by the inspector. Borrow and/or disposal sites shall not be located in a floodplain or wetland. Copies of releases signed by the landowner shall be provided to the inspector.

H. A Soil Erosion and Sediment Pollution Control Plan is included in the workplan. The contractor shall be responsible for implementing the plan and maintaining the controls including any additional measures, which may be required to minimize sedimentation.

I. The contractor shall be responsible for locating and protecting all public and private utilities.

BID SCHEDULE

EWP/DSR SOLICITATION NUMBER: SU-25-005

LOCATION: 899 NORDMONT ROAD, MUNCY VALLEY PA. 17758

Item Unit No. QTY Unit Price 1 1 Lump Sum XXX

2 Stream Diversion & Dewatering 1 Lump Sum XXX

3 1 Lump Sum XXX

4 1 Lump Sum XXX

5 1 Lump Sum XXX

Total:

Contractor's Name:

Address:

Phone Number:

Tree Removal

Topsoiling/Seeding/Mulching

Description Mobilization/Demobilization

Total Price

GROUTED R-8 Riprap

Checked By:

Mark Buckwalter, PE - 1/29/2026

MARK

BUCKWALTER

Digitally signed by MARK

BUCKWALTER

Date: 2026.01.29 07:29:03 -05'00'

Mark.Buckwalter Text Box Construction Note- Do not excavate below the foundation of the bridge bottom or wing wall foundations. Ripap thickness to be adjusted accordingly to tie in flush with the bridge invert. The NRCS site inspector shall be present during excavation and riprap placement by the bridge.

Mark.Buckwalter Text Box (See Construction Note)

363-2134-008 / March 31, 2012 / Page 46

FIGURE 3.11

Temporary Cofferdam and Pump Bypass Around In-channel Work Areas

PA DEP

* Sandbags (Standard Construction Detail #3-15), Jersey barriers (Figure 3.13) or other non-erosive material, no earth fill. Do not excavate a sump for the pump intake.

** See Standard Construction Detail # 4-14. For low gradient channels, the rock filter may be replaced by an impervious cofferdam to prevent backflow into the work area.

NOTE: Pump intake shall be maintained a sufficient distance from bottom to prevent sediment from entering the system.

363-2134-008 / March 31, 2012 / Page 47

FIGURE 3.12

In-stream Cofferdam Diversion

* Sandbags (Standard Construction Detail #3-15), Jersey barriers (Figure 3.13) or other non-erosive material, no earth fill.

363-2134-008 / March 31, 2012 / Page 48

STANDARD CONSTRUCTION DETAIL #3-15

Sandbag Diversion Dam or Cofferdam

2 BAG MINIMUM HEIGHT ABOVE NORMAL BASE FLOW

FIGURE 3.13

Jersey Barrier Cofferdam – End View

363-2134-008 / March 31, 2012 / Page 53

DEWATERING WORK AREAS - Wherever water is pumped from a disturbed area, it must be treated for sediment removal prior to discharging to a surface water unless it can be shown that the quality of the water being pumped already meets discharge standards. If a properly functioning sediment basin or sediment trap is available, the pump discharge may be routed through the trap or basin. While pumping, the maximum water level in the trap or basin should not exceed the cleanout elevation.

Water pumped from disturbed areas may not be discharged directly to detention ponds, since they are not designed to be efficient sediment removal structures. Straw bale structures and filter fabric structures are not acceptable for filtering pumped water due to their history of ineffectiveness. Filter bags, as shown in Standard Construction Detail #3-16, and Sump Pits, as shown in Standard Construction Detail #3-17, may be used to filter pumped water as described in the following section.

Other devices for filtering water pumped from excavations will be reviewed on a case-by-case basis.

The topography and conditions of the ground cover between the discharge point and the receiving surface water should be evaluated for potential erosion. Appropriate stabilization measures should be incorporated where needed to prevent erosion.

No filtering device is required for water pumped directly from a stream channel as part of a pump-around bypass system.

PUMPED WATER FILTER BAG - Sediment Removal Efficiency: LOW. This device is not an ABACT for special protection watersheds unless surrounded by a compost sock ring or operated in conjunction with a sump pit. Filter bags may be used to filter water pumped from disturbed areas prior to discharging to surface waters. They may also be used to filter water pumped from the sediment storage areas of sediment basins and sediment traps.

Northampton County Conservation District

The maximum pumping rate for any bag in use or proposed for use on a site should be available at the site at all times during pumping operations. Pumping rates will vary depending on the size of the filter bag, and the type and amount of sediment discharged to the bag.

Filter bags should be installed according to the details shown in Standard Construction Detail #3-16.

363-2134-008 / March 31, 2012 / Page 54

STANDARD CONSTRUCTION DETAIL # 3-16

Pumped Water Filter Bag

Low volume filter bags shall be made from non-woven geotextile material sewn with high strength, double stitched “J” type seams. They shall be capable of trapping particles larger than 150 microns. High volume filter bags shall be made from woven geotextiles that meet the following standards:

Property Test Method Minimum Standard Avg. Wide Width Strength ASTM D-4884 60 lb/in

Grab Tensile ASTM D-4632 205 lb Puncture ASTM D-4833 110 lb

Mullen Burst ASTM D-3786 350 psi UV Resistance ASTM D-4355 70%

AOS % Retained ASTM D-4751 80 Sieve

A suitable means of accessing the bag with machinery required for disposal purposes shall be provided. Filter bags shall be replaced when they become ½ full of sediment. Spare bags shall be kept available for replacement of those that have failed or are filled. Bags shall be placed on straps to facilitate removal unless bags come with lifting straps already attached.

Bags shall be located in well-vegetated (grassy) area, and discharge onto stable, erosion resistant areas. Where this is not possible, a geotextile underlayment and flow path shall be provided. Bags may be placed on filter stone to increase discharge capacity. Bags shall not be placed on slopes greater than 5%. For slopes exceeding 5%, clean rock or other non-erodible and non-polluting material may be placed under the bag to reduce slope steepness.

No downslope sediment barrier is required for most installations. Compost berm or compost filter sock shall be installed below bags located in HQ or EV watersheds, within 50 feet of any receiving surface water or where grassy area is not available.

363-2134-008 / March 31, 2012 / Page 55

(Additional Notes for Standard Construction Detail # 3-16)

The pump discharge hose shall be inserted into the bags in the manner specified by the manufacturer and securely clamped. A piece of PVC pipe is recommended for this purpose.

The pumping rate shall be no greater than 750 gpm or ½ the maximum specified by the manufacturer, whichever is less. Pump intakes shall be floating and screened.

Filter bags shall be inspected daily. If any problem is detected, pumping shall cease immediately and not resume until the problem is corrected.

SUMP PIT - Sediment Removal Efficiency: LOW. This device is not an ABACT for special protection watersheds unless used in conjunction with a pumped water filter bag. For sites where large volumes of water of low to moderate turbidity (i.e. not flowing from or through work areas) must be pumped from work areas, and many filter bags would be required, sump pits (Standard Construction Detail #3-17) can provide a means of filtering the water. They may also be used in conjunction with filter bags to reduce the amount of sediment being pumped into the bags, reducing the number of bags required. Sump pits used in conjunction with filter bags may also be used as an ABACT BMP in special protection watersheds. Sump pits should not be used alone where highly turbid waters are being pumped such as typically results from active work areas.

Sump pits should be located at a low point in the work area so that the water naturally drains toward the pit. The size of the pit required depends upon the amount of water that must be pumped from the work area and the space available.

When used in conjunction with a filter bag, the intake of the pump going to the filter bag should be inserted into the standpipe of the sump pit.

SU-25-005 Page 1 of 4

ITEMS OF WORK

EWP SITE: SU-25-005

1. General Conditions Related to all Work Items:

a. Data concerning the utilities at this site has been obtained from Pennsylvania One-Call

System, Serial No. 20253362413. Accuracy of this data is not guaranteed. The Contractor must contact the PA One-Call System (1-800-242- 1776) at least 3, but not more than 10, working days prior to the commencement of construction for utility information. There are overhead utilities within the work area.

Verify all effected utility locations in job site prior to excavation.

The Contractor is responsible for the protection of any private or public facilities in the work area for the duration of the contract. The Contractor will be responsible for repairing any of their damages to a condition equal to or better than a before work condition. No additional compensation will be made for damaged facility repair.

Location of septic field and transfer lines AND water (Well and buried pipeline) has not been verified.

b. This site is located at 899 Nordmont Road, Muncy Valley, Pa. 17758. The scope of work includes the installation of 164 ft. of GROUTED R-8 riprap, including the two upstream cutoffs. Left bank (House side) riprap will be aprox. 7.2 ft high and right bank will be aprox. 4.3 ft high. Note that on the left bank; 7.2’ could be lower than existing bank height in some locations. In those locations, excess bank height shall be removed.

Adjustments to stabilization height to be made by NRCS inspector as needed. Work also includes final grading and seeding of disturbed areas.

2. Bid Item 1 – Mobilization and Demobilization

a. This item shall include obtaining all work to move equipment and supplies onto and from the site. It is the contractor’s responsibility to comply with all local, state, and federal requirements related to the completion of this work

b. This item shall also include constructing, maintaining, and removing any access roads which are needed to construct the project. The construction limits are not shown on the planview but shall be within a reasonable distance from the streambank being stabilized.

The contractor is responsible for staying within reasonable construction limits and regrading and reseeding all access areas to original condition upon departure. The contractor is also responsible for repairing any areas within and outside of the construction limits back to the original conditions which may have been damaged by the contractor during access. NO machinery shall be driven near the house; damage to foundation walls will be the contractor’s responsibility to repair and outside of the scope of this project.

SU-25-005 Page 2 of 4

c. Implementation of erosion control practices shall be included in this bid item and shall follow the Erosion and Sediment Control Guidelines and Construction Drawings as well as any requirements from the Conservation District.

3. Bid Item 2 – Stream Diversion & Dewatering

a. This item shall include furnishing all materials (barriers, pumps, pipeline, silt bags, etc.) needed to divert stream flow around the work area .

i. Technical Specification - Stream Diversion and Dewatering

1. Work shall be performed from the top of bank as much as possible, however most of the work will require being done from the streambed.

It may be necessary to construct a coffer-dam and pump water around the work area. Dewater the site for the riprap key installation as per the construction drawings.

b. The coffer-dam or stream diversion embankment shall be removed and the stream in that area restored to original condition upon completion of the project.

4. Bid Item 3 – GROUTED & NON-GROUTED R8 Riprap

a. This item shall include furnishing and installing the GROUTED & NON-GROUTED R-8 riprap protection as shown in the construction drawings. This item shall follow technical specification GROUTED R-8 RIPRAP.

The bottom 4.3’ shall be grouted as well as the stream bottom. Riprap above 4.3’ shall not be grouted.

b. Under the Materials and Storage Section - In lieu of B – Geotextile, change to B - Bedding - Bedding shall consist of a uniform layer of AASHTO #1 stone between the earth subgrade and the rock riprap. Bedding material shall come from an approved source listed in the current copy of the Commonwealth of Pennsylvania Department of Transportation Bulletin # 14, "Aggregate Producers".

c. Under the Procedure Section - In lieu of C - Geotextile change to C - Bedding - Use

AASHTO # 1 coarse aggregate. Place the bedding on the prepared area in a uniform layer. No compaction is required. Long slopes may require working the lower portion, complete with riprap, and progressing up the slope in segments.

d. Riprap cutoffs shall be installed on the upstream ends of the slope (Both right and left sections). The cutoffs shall be to the same placement thickness as the bank riprap and installed to the length shown on the construction drawings. Bedding stone is not required in the cutoffs.

e. The NRCS inspector shall approve the source of riprap prior to ordering. Riprap shall be inspected visually and conform to the gradations and specifications of PennDOT Pub 408, Section 850 and as per the size requirements shown on the drawings.

SU-25-005 Page 3 of 4

f. Payment for this bid item and subsidiary items listed below shall be upon completion of this bid item.

g. Subsidiary Items included with Bid Item 3

i. Technical Specification – Excavation

1. Excavate for the key and side-slopes to the depth and slope shown on the construction drawings, ensure the depth also includes the bedding thickness. Material removed shall be utilized to shape the banks and shall follow the Unclassified Fill Specification. Excess material shall be disposed of offsite by the contractor.

ii. Technical Specification – Unclassified Fill

1. Excavated material from the riprap key and cutoff trenches shall be utilized to shape the banks. Excess material shall be disposed of offsite by the contractor.

iii. Technical Specification – Clearing and Grubbing

1. This work shall include clearing and grubbing all vegetation and woody material located where the riprap bank protection is proposed.

Designated trees and shrubbery either marked on site or labeled on the plan view shall not be disturbed.

2. No material is permitted to be burned on site.

5. Bid Item 4 – Topsoiling, Permanent Seeding, and Mulching

a. This item shall include furnishing and installation of topsoil, permanent seeding, and mulching to all disturbed areas. This item shall follow Technical Specifications – Topsoiling, Seeding

b. Existing topsoil shall be stripped and stockpiled where needed to install the proposed work items. Upon successful completion of work items topsoil shall be reinstalled a minimum of 6-inches thick and blended into the natural grade. It shall be lightly compacted with a cultipacker or tracked machine.

c. Excess topsoil shall be hauled off site and exposed of by the contractor, in the event additional topsoil is needed the topsoil shall be hauled in from offsite and shall meet the material specifications listed in the specification.

d. Install permanent seeding, lime, fertilizer, and mulch as per specification on all disturbed areas.

e. Payment for this item shall be lump sum upon completion of this bid item.

SU-25-005 Page 4 of 4

6. Bid Item 5 – Tree Removal

a. This item shall include removing all trees, that are designated on the planview drawing as to be removed.

b. Stumps shall be removed and disposed of off-site by the contractor.

c. Payment for this item shall be lump sum upon completion of this bid item.