3-Additional Grouted Riprap Conditions SU-25-001.pdf
PDF 46 KB Posted
- Attached to
- INVITATION TO BID: Stream Stabilization Project at 454 Fairman Road, Muncy Valley, PA 17758 - SU-25-001
- Solicitation number
- Not on record
- Issued by
- Susquehanna County, Pennsylvania
About this file
This is an additional conditions specification document for grouted riprap work on an Emergency Watershed Protection Project managed by the Natural Resources Conservation Service (NRCS), the Department of Environmental Protection (DEP), and the Sullivan County Conservation District in Pennsylvania. The document outlines specific environmental and construction requirements for Bid Item 3, Grouted R-8 Riprap installation, which is part of a stream stabilization project. The work involves 164 feet of grouted R-8 riprap installation at either 899 Nordmont Road or 454 Fairman Road in Muncy Valley, PA, depending on the specific bid package. The mandatory pre-bid showing is scheduled for Wednesday, March 18, 2026, at 11:00 AM (for the Nordmont Road site) or Wednesday, May 27, 2026, at 11:00 AM (for the Fairman Road site), both at the Davidson Township Building in Muncy Valley. Sealed bids are due electronically via PennBid by 4:00 PM on Friday, April 3, 2026 (Nordmont Road) or Friday, June 12, 2026 (Fairman Road), with bid openings scheduled for Tuesday, April 7, 2026, or Tuesday, June 16, 2026, respectively, at the Sullivan County Courthouse. Work must be completed within 14 to 28 days of receiving the Notice-to-Proceed, depending on the project site.
The grouted riprap conditions require anti-washout admixture in the grout mix, sealed diversion dike systems, off-site concrete washout areas, and continuous pH monitoring of stream water 25 feet downstream of the diversion dike system at 15-minute intervals during grout placement. Grout placement operations must cease if pH levels reach 9.0 or greater, and work cannot resume until baseline pH readings are achieved and the diversion dike system is repaired or sealed. These conditions are subsidiary items included with the grouted riprap bid item and are mandatory permit requirements. Bidders must provide a 10% bid bond or certified check, with the successful bidder required to furnish 100% performance and payment bonds within ten business days of award. All work is subject to Pennsylvania Prevailing Wage Project Rates, and quality assurance inspection will be provided by NRCS and/or the Sullivan County Conservation District, with all materials requiring pre-use approval. Funding is provided through the NRCS Emergency Watershed Protection Program and the Department of Environmental Protection.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SU-25-001
EWP SITE: SU-25-001
ADDITIONAL CONDITIONS FOR GROUTED RIPRAP-
1. Anti-washout admixture must be used in grout mix.
2. Diversion dike system must be sealed to prevent or minimize migration of the water from the work areas to the stream flow.
3. Concrete washout areas must be located off site and in a location where wash material cannot reach a stream or wetland area.
4. PH monitoring of stream water must be performed during grout placement operations.
5. Monitoring must be performed 25 feet downstream of diversion dike system.
6. A log must be kept with reading taken at the following intervals:
a. Prior to grout placement operations to establish a baseline reading.
b. Every 15 minutes during the grout placement operation.
7. Grout placement operation must stop if pH levels reach 9.0 or greater.
a. If grout placement operations are stopped due to pH level, diversion dike system must be repaired or sealed prior to grout placement operations resuming.
b. Grout placement operations may not resume until pH levels reach baseline reading.
8. Diversion dike system may not be removed until the contained water reaches baseline readings.
These additional conditions are to be considered subsidiary items included with Bid Item 3, Grouted R8 Riprap
These items are a condition of the permit.