1-Attachment 1 Draft A101 2017 .pdf
PDF 266 KB Posted
- Solicitation number
- CSP 26-024JO
- Issued by
- Travis County, Texas
About this file
This is an AIA Document A101-2017 Standard Form of Agreement between Pflugerville Independent School District (PfISD) and a contractor for the turnkey replacement of baseball and softball turf at Hendrickson High School and Weiss High School. The agreement is dated May 30, 2020, and incorporates by reference AIA Document A201-2017 General Conditions of the Contract for Construction. The contractor's responsibilities include full execution of all work as described in the contract documents. The date of commencement shall be established through a notice to proceed issued by the owner, and substantial completion of the entire work is to be determined and included in a final modification to the agreement. The contract will be managed by Brandon Cardwell, Executive Director of Facilities and Support Services for PfISD, located at 1401 West Pecan Street, Pflugerville, Texas 78660.
The contract sum is to be determined at $0.00 in the draft document, subject to additions and deductions per the contract documents. Progress payments shall be made monthly based on applications for payment submitted by the contractor and certificates issued by the architect, with the owner making payment no later than the last day of the following month or within forty-five days of application receipt. The owner may withhold five percent retainage from each progress payment prior to substantial completion. Final payment constituting the entire unpaid balance shall be made within thirty days after the architect issues the final certificate for payment. Liquidated damages are established at $750 per project per day for delays past the substantial completion date. The contract incorporates payment provisions under the Texas Prompt Pay Act, Texas Government Code Chapter 2251, with interest accruing on unpaid amounts. Dispute resolution shall be resolved through litigation in a court of competent jurisdiction, and the contractor shall provide all insurance and bonds as set forth in the general conditions and contract documents.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AIA
Document A101TM – 2017
Standard Form of Agreement Between Owner and Contractor where the basis of payment is a Stipulated Sum
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
User Notes: (1130452037)
ADDITIONS AND DELETIONS:
The author of this document has added information needed for its completion.
The author may also have revised the text of the original AIA standard form.
An Additions and Deletions
Report that notes added information as well as revisions to the standard form text is available from the author and should be reviewed.
This document has important legal consequences.
Consultation with an attorney is encouraged with respect to its completion or modification.
The parties should complete
A101™–2017, Exhibit A, Insurance and Bonds, contemporaneously with this
Agreement. AIA Document
A201™–2017, General
Conditions of the Contract for Construction, is adopted in this document by reference. Do not use with other general conditions unless this document is modified.
ELECTRONIC COPYING of any portion of this AIA® Document to another electronic file is prohibited and constitutes a violation of copyright laws as set forth in the footer of this document.
AGREEMENT made as of the 30th day of May in the year 2020
BETWEEN the Owner:
Pflugerville Independent School District
1401 West Pecan
Pflugerville, Texas 78660
Phone: 512-594-0000 and the Contractor:
To Be Determined for the following Project:
The Architect:
The Owner and Contractor agree as follows.
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
TABLE OF ARTICLES
1 THE CONTRACT DOCUMENTS
2 THE WORK OF THIS CONTRACT
3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
4 CONTRACT SUM
5 PAYMENTS
6 DISPUTE RESOLUTION
7 TERMINATION OR SUSPENSION
8 MISCELLANEOUS PROVISIONS
9 ENUMERATION OF CONTRACT DOCUMENTS
EXHIBIT A INSURANCE AND BONDS
ARTICLE 1 THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, Conditions of the Contract (General, Supplementary, and other
Conditions), Drawings, Specifications, Addenda issued prior to execution of this Agreement, other documents listed in this Agreement, and Modifications issued after execution of this Agreement, all of which form the Contract, and are as fully a part of the Contract as if attached to this Agreement or repeated herein. The Contract represents the entire and integrated agreement between the parties hereto and supersedes prior negotiations, representations, or agreements, either written or oral. An enumeration of the Contract Documents, other than a Modification, appears in
Article 9.
ARTICLE 2 THE WORK OF THIS CONTRACT
The Contractor shall fully execute the Work described in the Contract Documents, except as specifically indicated in the Contract Documents to be the responsibility of others.
ARTICLE 3 DATE OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
§ 3.1 The date of commencement of the Work shall be:
A date set forth in a notice to proceed issued by the Owner.
§ 3.3 Substantial Completion § 3.3.1 Subject to adjustments of the Contract Time as provided in the Contract Documents, the Contractor shall achieve Substantial Completion of the entire Work:
- To Be Determined.
§ 3.3.2 Subject to adjustments of the Contract Time as provided in the Contract Documents, if portions of the Work are to be completed prior to Substantial Completion of the entire Work, the Contractor shall achieve Substantial
Completion of such portions by the following dates:
Portion of Work Substantial Completion Date
§ 3.3.3 If the Contractor fails to achieve Substantial Completion as provided in this Section 3.3, liquidated damages, if any, shall be assessed as set forth in Section 4.5.
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
ARTICLE 4 CONTRACT SUM
§ 4.1 The Owner shall pay the Contractor the Contract Sum in current funds for the Contractor’s performance of the
Contract. The Contract Sum shall be To Be Determined ($0.00 ), subject to additions and deductions as provided in the Contract Documents.
§ 4.2 Alternates § 4.2.1 Alternates, if any, included in the Contract Sum:
§ 4.2.2 Subject to the conditions noted below, the following alternates may be accepted by the Owner following execution of this Agreement. Upon acceptance, the Owner shall issue a Modification to this Agreement.
§ 4.3 Allowances, if any, included in the Contract Sum:
§ 4.4 Unit prices:
§ 4.5 Liquidated damages shall be:
Liquidated damages shall be charged for each calendar day of delay the project is delayed past the date of substantial completion as addressed within this document. For the project, the liquidated damages shall be stipulated as $750 per project, per day.
§ 4.6 Other:
Not Applicable
ARTICLE 5 PAYMENTS
§ 5.1 Progress Payments § 5.1.1 Based upon Applications for Payment submitted to the Architect by the Contractor and Certificates for
Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the
Contractor as provided below and elsewhere in the Contract Documents.
§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of the month.
§ 5.1.3 Provided that an Application for Payment is received by the Architect not later than the last day of a month, the Owner shall make payment of the amount certified to the Contractor not later than the last day of the following month. If an Application for Payment is received by the Architect after the application date fixed above, payment of the amount certified shall be made by the Owner not later than forty-five ( 45 ) days after the Architect receives the
Application for Payment.
§ 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the
Contractor in accordance with the Contract Documents. The schedule of values shall allocate the entire Contract
Sum among the various portions of the Work. The schedule of values shall be prepared in such form, and supported by such data to substantiate its accuracy, as the Architect may require. This schedule of values shall be used as a basis for reviewing the Contractor’s Applications for Payment.
§ 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end of the period covered by the Application for Payment.
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
§ 5.1.6 In accordance with AIA Document A201™–2017, General Conditions of the Contract for Construction, and subject to other provisions of the Contract Documents, the amount of each progress payment shall be computed as follows:
§ 5.1.6.1 The amount of each progress payment shall first include:
.1 That portion of the Contract Sum properly allocable to completed Work;
.2 That portion of the Contract Sum properly allocable to materials and equipment delivered and suitably stored at the site for subsequent incorporation in the completed construction, or, if approved in advance by the Owner, suitably stored off the site at a location agreed upon in writing; and
.3 That portion of Construction Change Directives that the Architect determines, in the Architect’s professional judgment, to be reasonably justified.
§ 5.1.6.2 The amount of each progress payment shall then be reduced by:
.1 The aggregate of any amounts previously paid by the Owner;
.2 The amount, if any, for Work that remains uncorrected and for which the Architect has previously withheld a Certificate for Payment as provided in Article 9 of AIA Document A201–2017;
.3 Any amount for which the Contractor does not intend to pay a Subcontractor or material supplier, unless the Work has been performed by others the Contractor intends to pay;
.4 For Work performed or defects discovered since the last payment application, any amount for which the Architect may withhold payment, or nullify a Certificate of Payment in whole or in part, as provided in Article 9 of AIA Document A201–2017; and
.5 Retainage withheld pursuant to Section 5.1.7.
§ 5.1.7 Retainage § 5.1.7.1 For each progress payment made prior to Substantial Completion of the Work, the Owner may withhold the following amount, as retainage, from the payment otherwise due:
5%
§ 5.1.7.1.1 The following items are not subject to retainage:
§ 5.1.7.2 Reduction or limitation of retainage, if any, shall be as follows:
§ 5.1.7.3 Except as set forth in this Section 5.1.7.3, upon Substantial Completion of the Work, the Contractor may submit an Application for Payment that includes the retainage withheld from prior Applications for Payment pursuant to this Section 5.1.7. The Application for Payment submitted at Substantial Completion shall not include retainage as follows:
§ 5.1.8 If final completion of the Work is materially delayed through no fault of the Contractor, the Owner shall pay the Contractor any additional amounts in accordance with Article 9 of AIA Document A201–2017.
§ 5.1.9 Except with the Owner’s prior approval, the Contractor shall not make advance payments to suppliers for materials or equipment which have not been delivered and stored at the site.
§ 5.2 Final Payment § 5.2.1 Final payment, constituting the entire unpaid balance of the Contract Sum, shall be made by the Owner to the
Contractor when
.1 the Contractor has fully performed the Contract except for the Contractor’s responsibility to correct
Work as provided in Article 12 of AIA Document A201–2017, and to satisfy other requirements, if any, which extend beyond final payment; and
.2 a final Certificate for Payment has been issued by the Architect.
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
§ 5.2.2 The Owner’s final payment to the Contractor shall be made no later than 30 days after the issuance of the
Architect’s final Certificate for Payment.
§ 5.3 Interest Payments due and unpaid under the Contract shall bear interest as provided by the Prompt Pay Act, Texas
Government Code Chapter 2251.
ARTICLE 6 DISPUTE RESOLUTION
§ 6.1 Initial Decision Maker The Architect for each project will serve as the Initial Decision Maker pursuant to Article 15 of AIA Document
A201–2017.
§ 6.2 Binding Dispute Resolution For any Claim subject to, but not resolved by, mediation pursuant to Article 15 of AIA Document A201–2017, the method of binding dispute resolution shall be as follows:
[ X ] Litigation in a court of competent jurisdiction
ARTICLE 7 TERMINATION OR SUSPENSION
§ 7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document
A201–2017.
§ 7.1.1 If the Contract is terminated for the Owner’s convenience in accordance with Article 14 of AIA Document
A201–2017, then the Owner shall pay the Contractor a termination fee as follows:
In the event of such termination, the Contractor shall be compensated for all work performed prior to the effective date of termination
§ 7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201–2017.
ARTICLE 8 MISCELLANEOUS PROVISIONS
§ 8.1 Where reference is made in this Agreement to a provision of AIA Document A201–2017 or another Contract
Document, the reference refers to that provision as amended or supplemented by other provisions of the Contract
Documents.
§ 8.2 The Owner’s representative:
Brandon Cardwell
Pflugerville Independent School District Executive Director of Facilities and Support Services
1401 West Pecan Street
Pflugerville, Texas 78660
Phone: 512-594-0200
Fax: 512-594-0246
Email: brandon.cardwell@pfisd.net
§ 8.3 The Contractor’s representative:
§ 8.4 Neither the Owner’s nor the Contractor’s representative shall be changed without ten days’ prior notice to the other party.
mailto:brandon.cardwell@pfisd.net
AIA Document A101™ – 2017. Copyright © 1915, 1918, 1925, 1937, 1951, 1958, 1961, 1963, 1967, 1974, 1977, 1987, 1991, 1997, 2007 and 2017 by The American Institute of Architects. All rights reserved. WARNING: This AIA® Document is protected by U.S. Copyright Law and
International Treaties. Unauthorized reproduction or distribution of this AIA® Document, or any portion of it, may result in severe civil and criminal penalties, and will be prosecuted to the maximum extent possible under the law. This draft was produced by AIA software at
10:41:45 ET on 11/19/2019 under Order No.3950979810 which expires on 11/03/2020, and is not for resale.
§ 8.5 Insurance and Bonds § 8.5.1 The Owner and the Contractor shall purchase and maintain insurance as set forth in AIA Document A201™–
2017, General Conditions of the Contract for Construction, and elsewhere in the Contract Documents.
§ 8.5.2 The Contractor shall provide bonds as set forth in AIA Document A201™–2017 General Conditions of the
Contract for Construction, and elsewhere in the Contract Documents.
§ 8.6 Notice in electronic format, pursuant to Article 1 of AIA Document A201–2017, may be given in accordance with AIA Document E203™–2013, Building Information Modeling and Digital Data Exhibit, if completed, or as otherwise set forth below:
§ 8.7 Other provisions:
ARTICLE 9 ENUMERATION OF CONTRACT DOCUMENTS
§ 9.1 This Agreement is comprised of the following documents:
.1 AIA Document A101™–2017, Standard Form of Agreement Between Owner and Contractor
.2 AIA Document A201™–2017, General Conditions of the Contract for Construction
.3 PfISD CSP Document
§ 9.2 Other Exhibits
.1 Not Applicable
This Agreement entered into as of the day and year first written above.
OWNER (Signature) CONTRACTOR (Signature)
Dr. Douglas Killian, Superintendent of Schools To Be Determined
(Printed name and title) (Printed name and title)
File details come from the government source that posted it. Updated .