1-607802-25 RFP Exhibit D - Tentative Project Schedule.pdf

PDF 172 KB Posted

Attached to
Clark County Rehabilitation Center State and local contract opportunity
Solicitation number
607802-25
Issued by
Clark County, Nevada

About this file

This document is a tentative project schedule exhibit for a Request for Proposal issued by Clark County, Nevada, for Construction Manager at Risk (CMAR) services for the Clark County Rehabilitation Center, located at APN 123-34-401-004 (Las Vegas Boulevard and Beasley Drive). The RFP is anticipated to be advertised in December 2025 or January 2026 with a 30-day advertisement period, with an anticipated RFP open date in February 2026. The complete RFP and CMAR selection process, including RFP advertisement, short list selection, presentations, Board of County Commissioners preparation and meeting, and request for insurance, is projected to take 4 to 5 months from advertisement to award of preconstruction services. The preconstruction kickoff meeting is anticipated within 10 days of award, followed by preconstruction services including schematic design, design development at 30 percent completion, construction documents at 60 and 95 percent completion, and final Guaranteed Maximum Price proposal submission. The anticipated total preconstruction services duration is 180 days, though specific milestones including design notice to proceed, cost estimate deadlines, GMP proposal negotiation and approval, construction notice to proceed, and multi-phased construction completion dates are listed as to be determined and subject to change based on county needs.

The schedule notes that all dates and durations are anticipated only and are subject to change dependent upon the county's needs. The document clarifies that dates and durations established in the RFP and addendums issued by Purchasing and Contracts supersede all dates listed in this exhibit. The County anticipates ongoing preconstruction services throughout the duration of the entire project. The CMAR is required to provide a detailed schedule including line items for each milestone and review/design duration listed for each GMP delivery. Delivery of multiple GMPs is expected for completion of all services, and the starting and completion of all services will be determined based on the approved schedule.

View the file

Other files for this state and local contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

D-1

EXHIBIT D

OF THE RFP

RFP NO. 607802-25

TENTATIVE PROJECT SCHEDULE

PROJECT IDENTIFICATION:

Project Name: Clark County Rehabilitation Center Project Location: APN: 123-34-401-004 (Las Vegas Blvd. & Beasley Dr.)

RPM Project No.: RP. B0123067

PROPOSED TIMELINE:

Dates and durations listed above are anticipated ONLY and are subject to change dependent upon County’s needs. This document is intended for reference use only. Dates and durations established in the RFP and Addendums issued by Purchasing & Contracts supersede all dates and durations listed herein.

Preconstruction services will commence upon Notice to Proceed and are estimated to last a minimum of 6 months.

COUNTY anticipates ongoing Preconstruction services throughout the duration of the Project.

CMAR TENTATIVE PROJECT SCHEDULE

Project Name: Clark County Rehabilitation Center

Project Location: APN: 123-34-401-004 (Las Vegas Blvd. & Beasley Dr.)

Project No: RP. B0123067 Anticipated RFP Advertisement: December

2025/January 2026 Anticipated RFP Advertisement Duration 30 days

Anticipated RFP Open Date February 2026

Anticipated RFP Response Review & Evaluation Duration 14 Days

Anticipated Notice of Advancement (Short List Identification) 14 Days

Anticipated Duration between Advancement Notification & Submittal Due Dates 17 Days

Anticipated County Administrative Period Prior to Interviews 14 Days

Anticipated Presentation Dates 14 Days

Anticipated Presentation Review & Evaluation Duration 14 Days

Anticipated Notice of Selection and Recommendation to Award;

Includes Anticipated County Administrative (BCC Prep Period) 14 Days

Anticipated BCC Agenda Date: Date after Notice of Selection and Recommendation to Award is issued 2 Months

Anticipated Request for Insurance: 10 Days

Total Anticipated RFP/CMAR Selection Duration Includes RFP Advertisement, Short List Selection, Presentations, BCC Prep, BCC Meeting, Request for Insurance and Award of Preconstruction Services Agreement

4 – 5 Months

Preconstruction Kickoff Meeting 10 Days

Preconstruction Services Design Notice to Proceed Date (START) TBD

Initial Document Evaluation Period TBD

Deadline for Schematic Design Cost Estimate TBD

D-2

Design Development Period TBD

Deadline for 30% Design Development Cost Estimate TBD

Construction Document Development Period TBD

Deadline for 60% Construction Document Cost Estimate TBD

Construction Document Development Period TBD

Deadline for 95% Construction Document Cost Estimate TBD Construction Document Development Period TBD

Deadline for Final GMP Proposal TBD

Anticipated GMP Proposal Negotiation & Review Period TBD

Anticipated GMP Approval Date TBD

Total Anticipated Preconstruction Services Days 180 Days

Delivery of multiple GMP’s is expected for completion of all services. The 180 Days listed above represents anticipated level of effort expected in order to receive all GMPs for completion of all services. These days do not necessarily represent a timeframe for completion of all preconstruction services. Staring & Completion of all services will be determined based on approved schedule. CMAR is to provide a detailed schedule including at minimum, a line item for each of the milestones and review/design durations listed above for each GMP.

Anticipated GMP Contract Award: TBD

Construction Notice to Proceed: TBD

Anticipated Multi-Phased Construction Duration TBD

Certificate of Final Completion/Completion of all Services

TBD

File details come from the government source that posted it. Updated .