08 - Ayala Park Swings Project - Section H - Geotechnical Report.pdf

PDF 21 MB Posted

Attached to
BLOOMINGTON RECREATION AND PARK DISTRICT - AYALA PARK SWINGS PROJECT
Solicitation number
SPD126-SPDPA-6204
Issued by
San Bernardino County, California

About this file

This is a Geotechnical Report prepared for the Bloomington Recreation and Park District in Bloomington, California, relating to the Ayala Park Swings Project (Project No. 30.30.0205). The report documents subsurface conditions and geotechnical findings specific to the project site where the district plans to remove existing landscaping, furnish and install rubber playground surface, swings, shade sails, fencing, and complete various landscape repairs within Ayala Park. The geotechnical engineer emphasizes that this report was prepared specifically for this client, project, and site, and contains professional opinions about subsurface conditions derived from sampling and testing procedures.

The report includes critical guidance regarding the report's continued applicability and reliability. The geotechnical engineer cautions that the report's conclusions may be affected by changes to the project scope, site conditions, structural design, elevation, configuration, weight, or composition of the design team. The engineer advises that actual sitewide subsurface conditions may differ significantly from those indicated in the report and recommends that the geotechnical engineer remain retained throughout the design and construction phases to provide informed guidance. The report explicitly warns against relying on executive summaries or selected elements only, and advises that any project modifications, passage of time, changed subsurface conditions, or regulatory changes be communicated to the geotechnical engineer for assessment before application of the report's recommendations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION H

GEOTECHNICAL REPORT

AYALA PARK

SWINGS PROJECT

FOR

BLOOMINGTON RECREATION AND PARK DISTRICT

BLOOMINGTON, CALIFORNIA

PROJECT NO.: 30.30.0205

Geotechnical engineers structure their services to meet the specific needs of their clients. A geotechnical-engineering study conducted for a given civil engineer will not likely meet the needs of a civil-

Typical changes that could erode the reliability of this report include those that affect:

• the site’s size or shape;

• the function of the proposed structure, as when it’s changed from a parking garage to an office building, or from a light-industrial plant to a refrigerated warehouse;

• the elevation, configuration, location, orientation, or weight of the proposed structure;

• the composition of the design team; or

• project ownership.

As a general rule, inform your geotechnical engineer of project changes – even minor ones – and request an assessment of their impact.

if your geotechnical engineer prepared it:

• for a different client;

• for a different project;

• for a different site (that may or may not include all or a works constructor or even a different civil engineer. Because each geotechnical-engineering study is unique, each geotechnical-engineering report is unique, prepared for the client.

. No one except authorized client representatives should rely on this geotechnical-engineering report without first conferring with the geotechnical engineer who prepared it.

Costly problems have occurred because those relying on a geotechnical-engineering report did not read it . Do not rely on an executive summary. Do not read selected elements only.

Your geotechnical engineer considered unique, project-specific factors when designing the study behind this report and developing the confirmation-dependent recommendations the report conveys. A few typical factors include:

• the client’s goals, objectives, budget, schedule, and risk-management preferences;

• the general nature of the structure involved, its size, configuration, and performance criteria;

• the structure’s location and orientation on the site; and

• other planned or existing site improvements, such as retaining walls, access roads, parking lots, and underground utilities.

portion of the original site); or

• before important events occurred at the site or adjacent to it; e.g., man-made events like construction or environmental remediation, or natural events like floods, droughts, earthquakes, or groundwater fluctuations.

Note, too, that it could be unwise to rely on a geotechnical-engineering report whose reliability may have been affected by the passage of time, because of factors like changed subsurface conditions; new or modified codes, standards, or regulations; or new techniques or tools.

, and, in general, about the continued reliability of this report, contact your geotechnical engineer before applying it. A minor amount of additional testing or analysis – if any is required at all – could prevent major problems.

Before construction begins, geotechnical engineers explore a site’s subsurface through various sampling and testing procedures.

. The data derived from that sampling and testing were reviewed by your geotechnical engineer, who then applied professional judgment to form opinions about subsurface conditions throughout the site. Actual sitewide-subsurface conditions may differ – maybe significantly – from those indicated in this report. Confront that risk by retaining your geotechnical engineer to serve on the design team from project start to project finish, so the individual can provide informed guidance quickly, whenever needed.

File details come from the government source that posted it. Updated .