078400 - Firestopping.doc

DOC document 33 KB Posted

Attached to
Z2DA--520-21-1-7032-0001 - Project 520-22-125 Replace Nurse Call System (VA-21-00015374)
Solicitation number
36C25621R0053
Issued by

About this file

This document includes a federal contract opportunity solicitation for replacing a nurse call system and the related project specifications file. The solicitation is a 100% set-aside for service-disabled veteran-owned small businesses to replace the nurse call system at the Gulf Coast Veterans Health Care System in Biloxi, Mississippi. The construction cost for the project ranges from $500,000 to $1,000,000. Interested offerors must check the SAM website for the request for proposals and any amendments, with the proposal due date scheduled for March 1, 2021 and anticipated contract award by April 1, 2021. The 120-day period of performance will commence upon notice to proceed. The project specifications file provides requirements for firestopping systems and smoke stopping seals, including product data and installation instructions.

View the file

Other files

File Type Posted
36C25621R0053 0002.docx DOCX document
Register containing all RFI Inquiries _ Responses.docx DOCX document
Site Visit Sign-In Sheets.pdf PDF
36C25621R0053 0001.docx DOCX document
013323 - Shop Drawings.doc DOC document
EXHIBIT B PAST AND PRESENT PERFORMANCE QUESTIONNAIRE.docx DOCX document
270526 - Grounding and Bonding Communication Systems.doc DOC document
WD General Decision No MS20210050 02-12-2021.pdf PDF
EXHIBIT E SURETY FORM.docx DOCX document
017419 - Construction Waste Management.doc DOC document
275223 - Nurse Call Code Blue System.doc DOC document
271000 - Control Comm and Signal Wiring.doc DOC document
260533 - Raceway and Boxes for Elec Systems.doc DOC document
270511 - Req Communication Install.doc DOC document
36C25621R0053_1.docx DOCX document
EXHIBIT D CONTRACTOR EVALUATION FORM CONSTRUCTION SAFETY.docx DOCX document
SITE VISIT MAP Biloxi VA.pdf PDF
013526 - Safety Requirements.doc DOC document
260511 - Req for Electrical Installation.doc DOC document
262726 - Wiring Devices.doc DOC document
EXHIBIT F REQUEST FOR INFORMATION FORM.docx DOCX document
EXHIBIT A PERFORMANCE RELEVANCY SURVEY.docx DOCX document
010000 - General Requirements.doc DOC document
Drawings for Proj 520-22-125 Replace Nurse Call System.zip ZIP file
260521 - Low Voltage Elec.doc DOC document
260526 - Grounding Bonding Elec.doc DOC document
EXHIBIT C SUBCONTRACTOR INFORMATION AND CONSENT.docx DOCX document
ICRA.pdf PDF
Show all 28

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

520-22-125

SECTION 07 84 00

FIRESTOPPING

PART 1 GENERAL

1.1 DESCRIPTION

A.

Closures of openings in walls, floors, and roof decks against penetration of flame, heat, and smoke or gases in fire resistant rated construction.

B.

Closure of openings in walls against penetration of gases or smoke in smoke partitions.

1.2 RELATED WORK

N/A

1.3 SUBMITTALS

A.

Manufacturers literature, data, and installation instructions for types of firestopping and smoke stopping used.

B.

List of FM, UL, or WH classification number of systems installed.

C.

Certified laboratory test reports for ASTM E814 tests for systems not listed by FM, UL, or WH proposed for use.

1.4 DELIVERY AND STORAGE

A.

Deliver materials in their original unopened containers with manufacturer’s name and product identification.

B.

Store in a location providing protection from damage and exposure to the elements.

1.5 warranty

Firestopping work subject to the terms of the Article “Warranty of Construction”, FAR clause 52.246-21, except extend the warranty period to five years.

1.6 QUALITY ASSURANCE

FM, UL, or WH or other approved laboratory tested products will be acceptable.

1.7 APPLICABLE PUBLICATIONS

A.

Publications listed below form a part of this specification to the extent referenced. Publications are referenced in the text by the basic designation only.

B.

American Society for Testing and Materials (ASTM):

E84-07 Surface Burning Characteristics of Building Materials

E814-06 Fire Tests of Through-Penetration Fire Stops

C.

Factory Mutual Engineering and Research Corporation (FM):

Annual Issue Approval Guide Building Materials

D.

Underwriters Laboratories, Inc. (UL):

Annual Issue Building Materials Directory

Annual Issue Fire Resistance Directory

1479-03 Fire Tests of Through-Penetration Firestops

E.

Warnock Hersey (WH):

Annual Issue Certification Listings

PART 2 - PRODUCTS

2.1 FIRESTOP SYSTEMS

A.

Use either factory built (Firestop Devices) or field erected (through-Penetration Firestop Systems) to form a specific building system maintaining required integrity of the fire barrier and stop the passage of gases or smoke.

B.

Through-penetration firestop systems and firestop devices tested in accordance with ASTM E814 or UL 1479 using the "F" or "T" rating to maintain the same rating and integrity as the fire barrier being sealed. "T" ratings are not required for penetrations smaller than or equal to 100 mm (4 in) nominal pipe or 0.01 m2 (16 sq. in.) in overall cross sectional area.

C.

Products requiring heat activation to seal an opening by its intumescence shall exhibit a demonstrated ability to function as designed to maintain the fire barrier.

D.

Firestop sealants used for firestopping or smoke sealing shall have following properties:

1.

Contain no flammable or toxic solvents.

2.

Have no dangerous or flammable out gassing during the drying or curing of products.

3.

Water-resistant after drying or curing and unaffected by high humidity, condensation or transient water exposure.

4.

When used in exposed areas, shall be capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

E.

Firestopping system or devices used for penetrations by glass pipe, plastic pipe or conduits, unenclosed cables, or other non-metallic materials shall have following properties:

1.

Classified for use with the particular type of penetrating material used.

2.

Penetrations containing loose electrical cables, computer data cables, and communications cables protected using firestopping systems that allow unrestricted cable changes without damage to the seal.

3.

Intumescent products which would expand to seal the opening and act as fire, smoke, toxic fumes, and, water sealant.

F.

Maximum flame spread of 25 and smoke development of 50 when tested in accordance with ASTM E84.

G.

FM, UL, or WH rated or tested by an approved laboratory in accordance with ASTM E814.

H.

Materials to be asbestos free.

2.2 SMOKE STOPPING IN SMOKE PARTITIONS

A.

Use silicone sealant in smoke partitions as specified in Section 07 92 00, JOINT SEALANTS.

B.

Use mineral fiber filler and bond breaker behind sealant.

C.

Sealants shall have a maximum flame spread of 25 and smoke developed of 50 when tested in accordance with E84.

D.

When used in exposed areas capable of being sanded and finished with similar surface treatments as used on the surrounding wall or floor surface.

PART 3 - EXECUTION

3.1 EXAMINATION

Submit product data and installation instructions, as required by article, submittals, after an on site examination of areas to receive firestopping.

3.2 PREPARATION

A.

Remove dirt, grease, oil, loose materials, or other substances that prevent adherence and bonding or application of the firestopping or smoke stopping materials.

B.

Remove insulation on insulated pipe for a distance of 150 mm (six inches) on either side of the fire rated assembly prior to applying the firestopping materials unless the firestopping materials are tested and approved for use on insulated pipes.

3.3 INSTALLATION

A.

Do not begin work until the specified material data and installation instructions of the proposed firestopping systems have been submitted and approved.

B.

Install firestopping systems with smoke stopping in accordance with FM, UL, WH, or other approved system details and installation instructions.

C.

Install smoke stopping seals in smoke partitions.

3.4 CLEAN-UP AND ACCEPTANCE OF WORK

A.

As work on each floor is completed, remove materials, litter, and debris.

B.

Do not move materials and equipment to the next-scheduled work area until completed work is inspected and accepted by the Resident Engineer.

C.

Clean up spills of liquid type materials.

- - - E N D - - -