072820-VA Break Room Bid Set.pdf
PDF 8 MB Posted
- Attached to
- Security System Installation and Monitoring Federal contract opportunity
- Solicitation number
- 36C25521Q05350001
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 110117 Original Floor Plans.pdf | ||
| 072720-VA Break Room Casework Revisions.pdf | ||
| 36C25521Q0535 0001.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CODE INFORMATION DRAWING INDEX
VICINITY MAP
V A C O U N S E L I N G S E R V I C E S 1 2 9 3 5 N O R T H O U T E R 4 0
T O W N & C O U N T R Y, M O 6 3 1 4 1
TITLE SHEETA0.00
IS
SU
ED
F
OR
P
RO
GR
ES
S
SE
T
DA
TE
.3 0.
GENERAL NOTESA1.01
KEY PLAN
X
KEYED NOTE
X
X
DETAIL SYMBOL
DETAIL NUMBER
SHEET LOCATION
A
COLUMN SYMBOL
ELEVATION SYMBOL
ELEVATION NUMBER
SHEET LOCATION
PX
X
X
X
RECEPTION
AREA
REVISION NUMBER PARTITION TYPE
DOOR SYMBOL
DOOR TYPE
HARDWARE GROUP
ROOM SYMBOL
ROOM NAME
ROOM NUMBER
FINISH SYSTEM SYMBOLFINISH SYMBOLX X X
X EQUIPMENT SYMBOL
X'-X"
A.C.T.
CEILING SYMBOL
CEILING HEIGHT
CEILING MATERIAL
4.01
ARCHITECTURAL
X
CONTACT INFORMATION
CONTRACTOR:
TBD
X
X
X
WALL MOUNTED DUPLEX OUTLET
WALL MOUNTED QUADPLEX OUTLET
WALL MOUNTED UNIPLEX OUTLET
W.M. DEDICATED UNIPLEX OUTLET
W.M. DEDICATED DUPLEX OUTLET
W.M. DEDICATED QUADPLEX OUTLET
WALL MOUNTED JUNCTION BOX
J
J
CEILING MOUNTED JUNCTION BOX
P
POWER POLE
J
WALL MOUNTED PHONE JACK
WALL MOUNTED VOICE / DATA JACK
WALL MOUNTED CABLE JACK
FLOOR MOUNTED UNIPLEX OUTLET
FLOOR MOUNTED DUPLEX OUTLET
FLOOR MOUNTED QUADPLEX OUTLET
F.M. DEDICATED UNIPLEX OUTLET
F.M. DEDICATED DUPLEX OUTLET
FLOOR MOUNTED DEDICATED QUADPLEX
OUTLET
FLOOR MOUNTED JUNCTION BOX
FLOOR MOUNTED PHONE JACK
FLOOR MOUNTED VOICE/DATA JACK
FLOOR MOUNTED CABLE JACK
T
THERMOSTAT
SD
SMOKE DETECTOR
S
SPEAKER
CM
CARBON MONOXIDE DETECTOR
EXISTING WALL
EXISTING WALL TO BE REMOVED
NEW WALL
NEW PARTIAL HEIGHT WALL
EXISTING DOOR NEW DOOR NEW PAIR OF DOORS
*INDICATES
ACTIVE
LEAF
EXISTING DOOR TO BE DEMOLISHED
EXISTING PARTIAL HEIGHT WALL
DEMOLITION PLAN & FLOOR PLANA2.01
REFLECTED CEILING PLAN & INTERIOR DETAILSA3.01
SYMBOLS
S
S
V
WALL SCONCE FIXTURE
PENDANT LIGHT FIXTURE
EXIT SIGN/EMERGENCY LIGHT
SURFACE MOUNTED FIXTURE
RECESSED DOWNLIGHT
FLUORESCENT FIXTURE
LIGHT/EXHAUST COMBO
EXHAUST FAN
VACUUM PORT
LIGHT SWITCH
3 WAY LIGHT SWITCH
UTILITY LIGHT
CEILING FAN
A0.00
TITLE SHEET
MSW/RCW
RCW
ARCHITECTURAL: 2015 INTERNATIONAL BUILDING CODE WITH CITY AMENDMENTS
ELECTRICAL: 2014 NATIONAL ELECTRICAL CODE
MECHANICAL: 2015 INTERNATIONAL MECHANICAL CODE WITH CITY AMENDMENTS
PLUMBING: 2015 UNIFORM PLUMBING CODE
BUILDING CONSTRUCTION TYPE: IIB
BUILDING USE GROUP: (B) BUSINESS
BUILDING FIRE PROTECTION: PARTIALLY SPRINKLERED
SUITE FIRE PROTECTION: FULLY SPRINKLERED
NUMBER OF STORIES: 2
TENANT SEPARATION: 0 HOUR
STAIR ENCLOSURES: 1 HOUR
TOTAL BUILDING GROSS AREA = 41,691 S.F.
EXISTING TENANT LEASE AREA PER ANSI/BOMA (USEABLE)= 7,286 U.S.F.
EXISTING TENANT LEASE AREA PER ANSI/BOMA (RENATABLE)= 8,306 R.S.F.
BREAK ROOM EXPANSION= 59 S.F.
NEW TENANT LEASE AREA PER ANSI/BOMA (USEABLE)= 7,345 U.S.F.
NEW TENANT LEASE AREA PER ANSI/BOMA (RENATABLE)= 8,365 R.S.F.
TABLE 1004.1.2 MAXIMUM FLOOR AREA ALLOWANCES PER OCCUPANT
OCCUPANCY LOAD:
1/100 = OFFICE AREAS
OCCUPANT LOAD:
1/100: 7,345 U.S.F. = 74 OCCUPANTS
EXITING WIDTH:
74 X .20 = 15 EXITING INCHES REQUIRED.
(3) OPENINGS AT (34") SHOWN FOR A TOTAL OF
102 EXITING INCHES PROVIDED FOR A TOTAL
CAPACITY OF 510 EXITING OCCUPANTS.
NOTE: CHANGE ORDERS CANNOT BE APPROVED ONSITE AND/OR BY THE
GENERAL CONTRACTOR. THEY MUST BE APPROVED IN WRITING BY THE
TENANT'S/OWNER'S REPRESENTATIVE ONLY.
ARCHITECT:
ALIGNED STUDIO, LLC
13100 MANCHESTER ROAD, SUITE 225
ST. LOUIS, MISSOURI 63131
314.317.0060
CONTACT: MICKI WEHMEIER OR RANDY WINZEN
micki@aligned-studio.com randy@aligned-studio.com
BUILDING MANAGER:
COZAD PROPERTY MANAGEMENT COMPANY
16 SUNNEN DRIVE, SUITE 164
ST. LOUIS, MISSOURI 63143
314.782.3000
CONTACT: DON KELLY
dkelly@cozadgroup.com
AREA OF WORK
VA SPECIFIC GENERAL NOTESA1.02
VA SPECIFIC GENERAL NOTESA1.03
VA SPECIFIC GENERAL NOTESA1.04
VA SPECIFIC GENERAL NOTESA1.05
NOTE: G.C. TO PROVIDE PRICING FOR SUPPLYING AND INSTALLING CAT5e (MIN,)
COMMUNICATION CABLES AND BRACKETS PER REQUIREMENTS ESTABLISHED BY THE TENANT
FOR TENANT PROVIDED API'S . FINAL HOOK-UPS TO BE COMPLETED BY THE TENANT IT
DEPARTMENT.
ADDITIONAL WORK
REVISIONS
ALIGNED
STUDIO, LLC
ARCHITECTURE + DESIGN
MISSOURI CERTIFICATE OF AUTHORITY
No. 2016030702
DRAWN BY:
REVIEWED BY:
13100 MANCHESTER
JOB NO.
DATE:
CONTACT:
314.317.0060
SUITE 225
ST. LOUIS, MO 63131
www.aligned-studio.com
OF
CO
NS
TR
UC
TI
ON
D
OC
UM
EN
TS
F
OR
DE
PA
RT
ME
NT
O
F
VE
TE
RA
NS
AF
FA
IR
S
BR
EA
K
RO
OM
E
XP
AN
SI
ON
NO
RT
H
OU
TE
R
TO
W N
AN
D
CO
UN
TR
Y, M
IS
SO
UR
I
MICKI WEHMEIER
micki@aligned-studio.com
RANDY WINZEN
randy@aligned-studio.com
1976.1
07.28.20
X
X
X
X
IS
SU
ED
F
OR
B
ID
S
ET
DA
TE
.2 8.
X
X
X
X
X
X
X
X http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com http://www.ketiv.com AutoCAD SHX Text D.F.
GENERAL CONDITIONS FOR THE CONTRACT FOR CONSTRUCTION GOVERNING THE WORK SHALL BE AIA DOCUMENT A201 GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION 1997 EDITION. COPIES OF WHICH ARE AVAILABLE FOR REVIEW AT THE OFFICE OF THE ARCHITECT OR WHICH MAY BE PURCHASED DIRECTLY FROM THE AMERICAN INSTITUTE OF ARCHITECTS ST. LOUIS, CHAPTER 911 WASHINGTON AVE. ST. LOUIS, MO PHONE: 314.621.3484.
1. ANY REFERENCE TO "ARCHITECT" SHALL MEAN ALIGNED STUDIO, LLC. ANY REFERENCE TO "OWNER" OR "BUILDING MANAGER" SHALL REFER TO THE OWNER OF THE BUILDING, ANY REFERENCE TO G.C. SHALL INDICATE THE GENERAL CONTRACTOR AND/OR SUBCONTRACTORS. ANY REFERENCE TO TENANT
MEANS THE END USER.
2. ALL WORK IN THESE CONSTRUCTION DOCUMENTS SHALL BE PERFORMED BY THE GENERAL CONTRACTOR OR HIS/HER SUBCONTRACTORS, UNLESS NOTED OTHERWISE. REFER TO COVER SHEET FOR INDEX OF DRAWINGS THAT ARE INCLUDED IN THE CONSTRUCTION DOCUMENTS.
3. BY SUBMITTING A BID, THE GENERAL CONTRACTOR CERTIFIES THAT HE/SHE AND HIS/HER SUBCONTRACTORS HAVE REVIEWED ALL GENERAL NOTES, SPECIFICATIONS AND DRAWINGS, VISITED THE SITE AND ARE FAMILIAR WITH THE SCOPE OF WORK AND EXISTING CONDITIONS. IF GENERAL CONTRACTOR SEES A DISCREPANCY DURING SITE VISIT, OR DURING BIDDING, HE/SHE SHALL BRING IT TO THE ATTENTION OF THE ARCHITECT BEFORE THE SUBMISSION OF
HIS/HER BID.
4. THE GENERAL CONTRACTOR AND ALL SUBCONTRACTORS ARE RESPONSIBLE FOR VERIFYING ALL CONTRACT DOCUMENTS AND EXISTING FIELD CONDITIONS.
GENERAL CONTRACTOR SHALL CONFIRM THAT THE WORK IS BUILDABLE AS SHOWN PRIOR TO PROVIDING CONSTRUCTION BIDS. IF THERE ARE ANY DISCREPANCIES OR QUESTIONS, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR OBTAINING CLARIFICATION FROM THE ARCHITECT BEFORE SUBMITTING CONSTRUCTION BIDS. GENERAL CONTRACTOR TO INCLUDE PRELIMINARY SCHEDULES OF WORK WITH BID.
5. BY SUBMISSION OF BID CONTRACTORS AND SUBCONTRACTORS CERTIFY THAT THEY AGREE TO ALL BUILDING RULES AND REGULATIONS AS PROVIDED BY
OWNER AND BUILDING MANAGER DURING CONSTRUCTION.
6. G.C. SHALL INSPECT ALL EXISTING CONDITIONS IN PROJECT AREAS TO IDENTIFY WORK REQUIRED TO BE REFURBISHED AND/OR REPAIRED FROM "AS-IS" CONDITIONS TO "LIKE NEW" CONDITIONS. FAILURE TO ADEQUATELY IDENTIFY ALL VISIBLE WORK PRIOR TO BIDDING WILL WAIVE ALL FUTURE CLAIMS FOR
EXTRA COSTS.
7. NEW CONSTRUCTION SHALL MATCH EXISTING "BUILDING STANDARDS" EXCEPT AS NOTED OTHERWISE. VERIFY EXISTING CONSTRUCTION IN FIELD AND
REPORT ANY DISCREPANCIES TO ARCHITECT AND BUILDING OWNER.
8. UPON AWARD OF BID, THE GENERAL CONTRACTOR SHALL SUBMIT A FINAL SCHEDULE COORDINATING CONSTRUCTION TIME FOR ALL SUBCONTRACTORS' AND
GENERAL CONTRACTOR'S WORK.
9. DO NOT DISASSEMBLE DRAWING SETS FOR DISTRIBUTION TO SUBCONTRACTORS. SUBCONTRACTORS ARE REQUIRED HAVE A FULL SET OF DRAWINGS FOR BIDDING AND CONSTRUCTION PURPOSES. BY SUBMISSION OF HIS/HER BID THE CONTRACTOR WARRANTS THAT ALL SUB CONTRACTORS HAVE REVIEWED THE
ENTIRE DRAWING SET AND IS INTIMATELY FAMILIAR WITH THE ENTIRE SCOPE OF WORK.
10. TENANT SPACES ADJACENT TO EACH SIDE OF THIS SUITE SHALL BE LEFT IN GOOD CONDITION INCLUDING FINISHES, LIGHTING, POWER, ETC.
11. INCLUDE REQUIRED FLOOR PREP. THIS INCLUDES ANY LEVELING AND PATCHING OF SUB-FLOOR IN BID.
12. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR REQUESTING AND COORDINATING ALL BUILDING DEPARTMENT INSPECTIONS, APPROVALS FOR ENTIRE SCOPE OF WORK, AND INDEPENDENT 3RD PARTY TESTING. G.C. SHALL ALSO OBTAIN THE FINAL "CERTIFICATE OF OCCUPANCY".
13. UNLESS NOTED OTHERWISE, GENERAL CONTRACTOR TO PROVIDE AND PURCHASE ALL PERMITS AND CERTIFICATIONS REQUIRED FOR THE FULFILLMENT OF THE WORK. GENERAL CONTRACTOR AND SUBCONTRACTORS SHALL COMPLY WITH ALL LAWS, BUILDING CODES, ORDINANCES, RULES AND REGULATIONS REQUIRED. ALL PERMITS MUST BE ON SITE AND AVAILABLE TO BUILDING INSPECTORS AT ALL TIMES.
14. GENERAL CONTRACTOR SHALL PURCHASE AND MAINTAIN CERTIFICATIONS OF INSURANCE WITH RESPECT TO WORKMAN'S COMPENSATION PUBLIC LIABILITY AND PROPERTY DAMAGE AS REQUIRED BY LAW AND ANY ADDITIONAL BONDS OR INSURANCE REQUESTED BY THE OWNER PRIOR TO BEGINNING WORK, PER LANDLORD'S REQUIREMENTS. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR INITIATING, MAINTAINING AND SUPERVISING ALL SAFETY PRECAUTIONS IN
CONNECTION WITH THIS WORK.
15. DELIVERY OF MATERIALS SHALL ENTER BUILDING AT POINT DESIGNATED BY THE BUILDING OWNER AND FOLLOW PREDETERMINED ROUTE THROUGH BUILDING TO WORKSPACE. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE SECURITY, CONDUCT AND DISCIPLINE OF ALL WORKERS, AND SECURITY OF THE WORK SITE AND STORED MATERIALS, ETC. WHILE ON SITE PER BUILDING MANAGER/OWNER. ALL DELIVERIES WILL BE SCHEDULED WITH PROPERTY
MANAGER PRIOR DELIVERY DATES.
16. GENERAL CONTRACTOR SHALL PROVIDE TEMPORARY PROTECTION FOR TENANT'S FURNITURE AND EQUIPMENT DURING CONSTRUCTION.
17. WHEN CHANGE ORDERS HAVE BEEN REQUESTED BY TENANT, CONTRACTOR SHALL SUBMIT WRITTEN PRICES WITH UNIT BREAKDOWNS, AND INDICATE IF CONSTRUCTION COMPLETION DATE IS AFFECTED. CONTRACTOR SHALL OBTAIN ARCHITECT, OWNER AND TENANT'S WRITTEN APPROVAL OF CHANGE ORDERS PRIOR TO IMPLEMENTATION. CONTRACTOR SHALL TAKE RESPONSIBILITY FOR FULL PAYMENT OF CHANGE ORDERS, AND LATENESS IN COMPLETING CONSTRUCTION WORK, IF IMPLEMENTED WITHOUT TENANT'S WRITTEN APPROVAL. THE TENANT'S VERBAL INSTRUCTIONS SHALL NOT IMPLY APPROVAL.
REVISION TO CONSTRUCTION DOCUMENTS SHALL ONLY BE AUTHORIZED IF IN WRITING BY THE ARCHITECT.
18. IF ANY DISCREPANCIES EXIST IN THE CONTRACT DOCUMENTS/SPECIFICATIONS, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR CLARIFYING WITH THE ARCHITECT. THE ARCHITECT ONLY, SHALL INTERPRET THE CONTRACT DOCUMENTS AND SPECIFICATIONS. THE GENERAL CONTRACTOR SHALL RESOLVE FIELD
CONDITIONS NOT SHOWN IN CONTRACT DOCUMENTS WITH ARCHITECT.
19. UNDER NO CIRCUMSTANCES SHALL ANY MEASUREMENT BE SCALED FROM THESE DOCUMENTS. ANY DISCREPANCIES/MISSING DIMENSIONS SHOULD BE
BROUGHT TO THE ARCHITECT'S ATTENTION PRIOR TO CONSTRUCTION.
20. SUBMIT TO THE ARCHITECT WITHIN FIVE (5) DAYS OF COMMENCEMENT OF WORK, CONFIRMATION WITH DELIVERY DATES ON ORDERS OF MATERIALS AND EQUIPMENT WITH LONG LEAD TIMES, WHICH COULD PREVENT MEETING OF SPECIFIED CONSTRUCTION DATES. GENERAL CONTRACTOR SHALL INCUR ADDITIONAL EXPENSES REQUIRED TO PROCURE ITEMS. DELAYING TENANT'S SCHEDULE IF ARCHITECT IS NOT NOTIFIED OF LEADTIME PROBLEMS.
21. NOTIFY THE ARCHITECT OF ALL BUILDING ITEMS RELATING TO BOTH WALLS AND CEILING (FIRE HORNS, SPEAKERS, SMOKE DETECTORS, SPRINKLERS, ETC.)
NOT INDICATED IN THESE DOCUMENTS FOR EXACT LOCATION/RELOCATION BEFORE PROCEEDING WITH CONSTRUCTION.
22. GENERAL CONTRACTOR TO FURNISH AND INSTALL ALL MANUFACTURED ITEMS, MATERIALS AND EQUIPMENT IN ACCORDANCE WITH THE MANUFACTURER'S RECOMMENDED SPECIFICATIONS, OR THE SPECIFICATIONS AS DESCRIBED IN THESE DRAWINGS, WHICHEVER IS MORE STRINGENT.
23. PROVIDE SEPARATE TRASH REMOVAL SERVICES DURING DEMOLITION AND NEW CONSTRUCTION AND PROVIDE THOROUGH CLEANING OF ANY AFFECTED PUBLIC SPACES BEFORE LEAVING THE PREMISES EACH DAY. ALL MATERIALS SHALL BE DISPOSED OF IN A PROPER AND CODE COMPLIANT MANNER.
COORDINATE LOCATION OF DUMPSTER IF REQUIRED WITH BUILDING OWNER/MANAGER. LOCATION MUST BE APPROVED BY BUILDING MANAGEMENT PRIOR TO
DELIVERY.
24. THE CONTRACTOR IS TO VERIFY THE SIZE OF ALL LANDLORD/TENANT SUPPLIED ITEMS PRIOR TO THE INSTALLATION AND COMMENCEMENT OF WORK AND
ADVISE THE ARCHITECT OR LANDLORD/TENANT OF DISCREPANCIES.
25. ANY MODIFICATIONS TO EXISTING CONDITIONS NOT INDICATED ON PLAN AS A RESULT OF THE BUILDING REVIEW PROCESS SHALL BE INCLUDED INTO THE
PROJECT CONSTRUCTION COST AND NOT INDICATED AS AN EXTRA COST.
26. HAZARDOUS MATERIALS: CLIENT, OWNER, TENANT AND G.C. ACKNOWLEDGES THAT OWNER IS SOLELY RESPONSIBLE FOR COMPLIANCE WITH ALL FEDERAL, STATE AND LOCAL LAWS RELATING TO THE ENVIRONMENT INCLUDING, WITHOUT LIMITATION, THE NATIONAL EMISSIONS STANDARDS FOR HAZARDOUS AIR
POLLUTANTS AND THE OCCUPATIONAL SAFETY AND HEALTH ACT.
27. ARCHITECT AND ARCHITECT'S EMPLOYEES, CONSULTANTS AND OTHER AFFILIATES SHALL HAVE NO RESPONSIBILITY FOR THE DISCOVERY, PRESENCE, HANDLING, REMOVAL OR DISPOSAL OF OR EXPOSURE OF PERSONS TO HAZARDOUS MATERIALS IN ANY FORM, INCLUDING WITHOUT LIMITATION ASBESTOS, ASBESTOS PRODUCTS, POLYCHLORINATED BIPHENYL (PCB) OR OTHER TOXIC SUBSTANCES.
1. THE GENERAL CONTRACTOR SHALL PROTECT ALL PREFINISHED DOORS DURING THE CONSTRUCTION PERIOD. DOORS THAT ARE DAMAGED AS A RESULT OF THE GENERAL CONTRACTOR OR HIS SUBCONTRACTORS WORK DURING THIS PERIOD SHALL BE REPAIRED AND REFINISHED BY THE GENERAL CONTRACTOR AT HIS
COST.
2. DIMENSIONS GIVEN FOR DOORS AND FRAMES ARE NOMINAL DIMENSIONS ONLY. FRAME TOLERANCES, CEILING CLEARANCES AND UNDERCUTS ARE TO BE
COORDINATED WITH DETAILS AND SITE CONDITIONS AS SHOWN.
3. THE GENERAL CONTRACTOR SHALL CONFIRM THAT ALL HINGES, ETC. CONFORM TO THE WEIGHT LOADS OF SCHEDULED DOORS PRIOR TO ORDERING DOORS
AND FRAMES.
4. THE GENERAL CONTRACTOR SHALL PROVIDE HARDWARE FOR FIRE-RATED OPENINGS IN COMPLIANCE WITH NFPA STANDARD NO. 80.
5. ALL DOORS IN THE MEANS OF EGRESS SHALL PROVIDE HARDWARE NOT REQUIRING A KEY OR SPECIAL KNOWLEDGE FOR EXIT OPERATION FROM THE EGRESS SIDE OF THE DOOR. ALL DOOR HARDWARE SHALL MEET OR EXCEED ALL APPLICABLE CODE COMPLIANCE. ALL DOORS EQUIPPED WITH SPECIAL LOCKING HARDWARE SHALL COMPLY WITH CRITERIA ESTABLISHED IN CURRENT APPLICABLE CODES. REFER TO CODE DATA BLOCK.
6. THE GENERAL CONTRACTOR SHALL PROVIDE ALL MISCELLANEOUS PIECES, SILENCERS, SEALS, DOOR STOPS, ETC. AS REQUIRED FOR A COMPLETE INSTALLATION OF ALL INTERIOR DOORS. ALL DOORSTOPS TO BE FLOOR MOUNTED AT A 90-DEGREE ANGLE TO THE DOOR OPENING, UNLESS NOTED OTHERWISE.
7. ALL KEYING SHALL BE BY THE GENERAL CONTRACTOR. GENERAL CONTRACTOR SHALL MEET WITH OWNER AND TENANT REPRESENTATIVE TO COORDINATE AND DETERMINE KEYING REQUIREMENTS. ALL LOCKS SHALL BE KEYED TO THE BUILDING MASTER SYSTEM. FURNISH TWO (2) MASTER AND ONE (1) GRAND
MASTER AND KEYING SCHEDULE TO OWNER/BUILDING MANAGER.
8. ALL DOOR LEVERS SHALL BE MOUNTED 42" A.F.F., UNLESS NOTED OTHERWISE.
9. EXTERIOR FINISH AND COLOR OF CORRIDOR DOORS SHALL MATCH BUILDING STANDARD CORRIDOR FINISHES.
21. SOUND INSULATION USED IN PARTITIONS SHALL BE (SIX) 6 P.C.F. THERMAFIBER, FRICTION FIT. INSULATION SHALL FIT SNUGLY IN PLACE AGAINST STUDS.
SOUND INSULATION USED IN WALLS AND PARTITIONS ABOVE THE CEILING AS DETAILED SHALL HAVE A MAXIMUM FLAME SPREAD OF 25, AND SHALL BE 24" X 48", (THREE) 3" UNFACED MINERAL FIBER DESIGNED TO ABSORB SOUND AND SPECIFICALLY MANUFACTURED FOR USE ABOVE SUSPENDED CEILINGS. WHERE SOUND INSULATION IS REQUIRED AT PARTITIONS, GENERAL CONTRACTOR TO ALSO PROVIDE SOUND BATTS AT CEILING AS WELL AS SOUND BOOTS ON RETURN
AND SUPPLY DUCTWORK (48" EITHER SIDE OF PARTITION).
22. ALL WOOD BLOCKING SHALL BE FIRE TREATED. PROVIDE WOOD BLOCKING IN ALL PARTITIONS WHICH RECEIVE SHELVING, CABINETS, COUNTERS, FURNITURE, ETC. VERIFY/CONFIRM PRIOR TO SUBMISSION OF BID.
23. COMPLETE THE TAPING, SPACKLING AND SANDING OF ANY UNFINISHED JOINTS AT ALL EXISTING DRYWALL CONSTRUCTION.
IP-2 (DRYWALL CEILINGS): FLAT FINISH U.N.O.
1ST COAT- PRIMER/SEALER TINTED TO FINAL COLOR.
2ND COAT- FLAT LATEX CEILING PAINT.
QUALITY: HIGH
IP-3 (EXPOSED FERROUS AND GALVANIZED METAL):
ALKYD- SEMI-GLOSS FINISH U.N.O.
1ST COAT- SHOP PRIMED: FOR TOUCH-UP USE ALKYD PRIMER
TINTED TO MATCH FINAL COATS.
2ND AND 3RD COATS: ALKYD SEMI-GLOSS ENAMEL.
QUALITY: TOP OF THE LINE
IP-4 (OPEN OR CLOSED GRAIN CATALYZED LACQUER A.W.I. SYSTEM TR-2 CUSTOM GRADE SATIN WOOD, TRANSPARENT FINISH): FINISH, PARTIALLY FILLED PORE.
STAIN 1ST COAT- WATER REDUCED SEALER
SAND- 220 GRIT
2ND AND 3RD COATS- WATER REDUCIBLE ACRYLIC LACQUER
EXTERIOR PAINT SYSTEMS:
EP-1 (GALVANIZED METALS): ALKYD- GLOSS FINISH U.N.O.
1ST COAT- GALVANIZED AND ALUMINUM PRIMER.
2ND COAT- GLID-GUARD RED OXIDE PRIMER.
3RD AND 4TH COATS- ALKYD INDUSTRIAL ENAMEL.
EP-2 (FERROUS METALS): LOW-GLOSS FINISH U.N.O.
1ST COAT- GLID-GUARD RED OXIDE PRIMER.
2ND AND 3RD COATS- SERIES SPREAD LUSTER ENAMEL.
12. ALL SCHEDULED WALLCOVERING SHALL BE DIRECT GLUED. FABRIC WALLCOVERINGS SHALL HAVE GLUE APPLIED TO WALL AND NOT TO FABRIC. SEE MANUFACTURER'S WRITTEN INSTRUCTIONS. ALL WALLCOVERING SEAMS SHALL BE INCONSPICUOUS. CONTACT ARCHITECT IMMEDIATELY IF SEAMS CANNOT BE
CONCEALED OR IF ANY QUESTIONS ARISE.
13. CONTRACTOR SHALL OBTAIN MANUFACTURER'S SPECIFICATIONS AND ADHERE STRICTLY TO THE WRITTEN INSTALLATION PROCEDURES.
14. IN THE EVENT OF IMPERFECTIONS IN THE MATERIAL, PATTERN OR COLOR MATCH, THE SUBCONTRACTOR SHALL IMMEDIATELY CONTACT THE GENERAL CONTRACTOR AND ARCHITECT. DO NOT RESUME INSTALLATION WITHOUT SPECIFIC DIRECTION FROM THE ARCHITECT AND GENERAL CONTRACTOR.
15. ALL WALLCOVERINGS MUST MEET LOCAL, COUNTY, STATE AND FEDERAL FLAMMABILITY REGULATIONS.
16. ALL SEAMS SHALL BE OF HIGH QUALITY STANDARDS, PATTERNED MATCHED AND INCONSPICUOUS. MUST USE A NEW RAZOR BLADE FOR EACH NEW CUT ON
FABRIC WALLCOVERING.
17. CLEAN ALL JOINTS AND EDGES AFTER COMPLETION OF INSTALLATION.
18. FIELD TOUCH-UP SHALL BE THE RESPONSIBILITY OF THE GENERAL CONTRACTOR AND SHALL INCLUDE THE FILLING AND TOUCH-UP OF EXPOSED JOB MADE NAIL OR SCREW HOLES, REFINISHING OF RAW SURFACES RESULTING FROM JOB FITTING, REPAIR OF JOB INFLICTED SCRATCHES AND MARS, AND FINAL CLEANING
UP OF THE FINISHED SURFACES.
19. CONTRACTOR SHALL MEET WITH ARCHITECT TO REVIEW AND APPROVE ALL STONE SLAB MATERIALS AND JOINT LINES PRIOR TO ORDER PLACEMENT.
CONTRACTOR TO COORDINATE WITH ARCHITECT AS NOT TO INTERFERE WITH PROJECT SCHEDULE.
20. NO TRIM PIECES OR REDUCER STRIPS ARE TO BE USED BETWEEN FLOORING AND OR WALL FINISH CHANGES UNLESS NOTED OTHERWISE.
21. THE GENERAL CONTRACTOR SHALL SWEEP AND CLEAN THE FLOOR SLAB AS REQUIRED TO ACCEPT SCHEDULED FLOORING PRIOR TO THE INSTALLATION OF
ALL FLOOR OR DETAILED COVERING.
22. THE GENERAL CONTRACTOR SHALL REMOVE ALL EXCESS FLOOR ADHESIVES FROM ADJACENT SURFACES AFTER FLOOR COVERING INSTALLATION. THE GENERAL CONTRACTOR SHALL USE ONLY THOSE CHEMICALS RECOMMENDED BY THE FLOOR COVERING MANUFACTURERS, AND THOROUGHLY CLEAN THOSE
SURFACES AFTER THE CHEMICAL CLEANING.
23. ALL CARPET SEAMS AND CUT EDGES SHALL BE PREPARED WITH SEAM SEALER PRIOR TO SEAMING PER MANUFACTURER'S RECOMMENDATION AND
SPECIFICATIONS.
24. THE GENERAL CONTRACTOR SHALL CONFIRM AND PREPARE ALL FLOORS TO RECEIVE FLOOR COVERING TO LEVELNESS REQUIREMENT OF MANUFACTURER
FINISHES. CONFIRM REQUIREMENTS PRIOR TO SUBMITTING BID.
25. CARPET INSTALLER SHALL PROVIDE LATEX LEVELING TO REPAIR SURFACE IMPERFECTIONS AND AT TRANSITIONS TO STONE OR CERAMIC TILE FLOORING FOR SMOOTH TRANSITION. GENERAL CONTRACTOR SHALL COORDINATE FLOOR PREPARATION WITH OTHER SUB-CONTRACTORS.
26. STONE TILE SHALL BE THIN-SET DIRECTLY OVER CONCRETE SLAB. EXAMINE SLAB FOR CRACKS AND IMPERFECTIONS. PROVIDE LATEX LEVELING TO REPAIR IMPERFECTIONS PRIOR TO TILE INSTALLATION. INFORM ARCHITECT IMMEDIATELY IF IMPERFECTIONS CANNOT BE REMOVED OR CORRECTED.
27. LAY FLOORING IN PATTERN(S) SHOWN ON PLANS. THE GENERAL CONTRACTOR SHALL INSTALL VINYL TILE WITH GRAIN RUNNING IN ONE DIRECTION. DO
NOT CHECKERBOARD TILE DIRECTION / GRAIN UNLESS OTHERWISE NOTED.
28. INSTALL STONE TILE LEVEL WITH JOINTS NOT TO EXCEED 1/8" IN WIDTH.
29. APPLY ONE COAT OF SEALANT TO ALL TILE PRIOR TO INSTALLATION. AFTER GROUT HAS CURED 28 DAYS, APPLY A SECOND COAT OF SEALANT TO ALL NEW WALL AND FLOOR TILE AND GROUT JOINTS AS SPECIFIED. REFER TO FINISH SPECIFICATIONS.
30. ONCE FLOORING TILE IS INSTALLED, REMOVE EXCESS GROUT/ADHESIVE FROM SURFACE AND SEAMS ONLY WITH CHEMICALS RECOMMENDED BY
MANUFACTURER. THOROUGHLY CLEAN SURFACE AFTER INSTALLATION.
31. CENTER TRANSITION OF FLOOR COVERINGS OCCURRING IN DOOR OPENINGS UNDER THE CENTER LINE OF THE DOOR IN THE CLOSED POSITION, U.N.O.
32. WHERE OCCURS, ALL WOOD BASES SHALL BE SITE PAINTED OR SHOP STAINED, BRUSHED OIL BASE EGGSHELL ENAMEL FINISH, OR STAINED, UNLESS
OTHERWISE NOTED. VISIBLE BRUSH STROKES ARE NOT ACCEPTABLE.
33. WHERE OCCURS, WOOD WALLCOVERING SHALL BE PROVIDED ONLY AS SPECIFIED, NO EXCEPTIONS. INSTALLATION SHALL BE WITHIN MANUFACTURER'S
SPECIFIED GUIDELINES, NO EXCEPTIONS.
34. ALL SUBCONTRACTORS MUST BE PRE-APPROVED OR A PART OF SUBCONTRACTOR OUTLINE, NO EXCEPTIONS.
35. IF SPECIFICATIONS INDICATED "TO MATCH EXISTING" THEN THE CONTRACTOR IS RESPONSIBLE FOR MATCHING THE TYPE, QUALITY, COLOR AND
CONSTRUCTION / WORKMANSHIP OF THE ITEM TO BE MATCHED.
36. GENERAL CONTRACTOR TO COORDINATE ALL PAINTING, STAINING AND SEALING WITH BUILDING MANAGEMENT IN ADVANCE TO CONTROL ANY ODOR ISSUES.
NO EXCEPTIONS.
37. ANY FINISH SPECIFICATIONS OF AND OR CONTAINING NATURAL STONE SHALL RECEIVE SEALER PER FINISH PRODUCT MANUFACTURER REPRESENTATIVES
RECOMMENDATION.
I. GENERAL CONDITIONS II. CONSTRUCTION (CONTINUED)
III. DOORS, FRAMES AND HARDWARE
1. THE GENERAL CONTRACTOR SHALL PROVIDE FINISH SAMPLES OF ALL MILLWORK FINISHES / MATERIALS, PROFILE SAMPLES OF ALL WOOD BASES / TRIM PIECES AND SHOP DRAWINGS FOR ALL MILLWORK PRIOR TO CONSTRUCTION IN A TIMELY MANNER SO NOT TO DELAY PROJECT COMPLETION DATE.
2. ALL MILLWORK SHALL BE CONSTRUCTED IN ACCORDANCE WITH AWI STANDARDS' MOST RECENT EDITION FOR "PREMIUM GRADE" MILLWORK AND CABINETRY
QUALITY AND DETAILING.
3. ALL HARDWARE SHALL BE HEAVY DUTY CONSTRUCTION. ALL HINGES SHALL BE CONCEALED, SELF-CLOSING AND ALL DRAWER GLIDES SHALL BE FULL EXTENSION, UNLESS NOTED OTHERWISE. ALL MILLWORK DOORS SHALL BE SECURED WITH MAGNETIC CATCHES AND HAVE SCHEDULED LOCKS AND DOOR PULLS.
REFER TO TYPICAL ELEVATION FOR FINISH AND LOCATION. ALL MILLWORK DOORS TO HAVE HINGES RESTRICTED TO 90° OPENING TO PREVENT DAMAGE TO
ADJACENT SURFACE.
4. COORDINATE PROJECTION DEPTH OF DOOR PULLS WITH CABINET END FILLER PANELS AT ALL LOCATIONS PERPENDICULAR TO A PARTITION OR ANY OTHER
ADJACENT OBSTRUCTION TO PREVENT DAMAGE TO ADJACENT SURFACE.
5. SCRIBE ALL MILLWORK TO ADJACENT SURFACE. VERIFY EXISTING CONDITIONS IN FIELD PRIOR TO FABRICATION. SCRIBE ALL BASE CABINETS, WALL CABINETS, FILLER PANELS AND COUNTER TOPS TO FLOORS, WALLS AND CEILINGS AS REQUIRED. GAPS BETWEEN CASEWORK AND ADJACENT SURFACES ARE UNACCEPTABLE.
6. PROVIDE FASTENER PLUGS TO COVER SCREW HEADS AT ALL CABINET INTERIORS.
7. ALL CASEWORK SHALL ADHERE TO MOST CURRENT AWI SECTION 400-PREMIUM QUALITY; FLUSH OVERLAY CONSTRUCTION, AND MEDIUM DENSITY
"FIBERBOARD" SUBSTRATE (NOT PARTICLEBOARD) FOR PLASTIC LAMINATE AND WOOD VENEER.
8. AWI SECTION 200 SHALL GOVERN ALL WOOD WALL PANELING. VENEERED TWO (2) SIDES TO CONTROL CONTRACTION AND EXPANSION.
9. ALL RUNNING TRIM SHALL BE ADHERE TO AWI SECTION 300-PREMIUM GRADE.
10. AWI SECTION 1500 SHALL GOVERN ALL CASEWORK CONCERNING WALL PANELING AND RUNNING TRIM. CUSTOM GRADE CATALYZED LACQUER AWI SYSTEM TR-2, TRANSPARENT FINISH, 40 SATIN 30-50 SHEEN, OPEN PORE: NO WASH COAT, INCLUDE STAIN, SEALER, SAND AND TWO (2) TOP COATS.
11. FOR PLASTIC LAMINATE PRODUCTS, ALL EXPOSED SURFACES, ALL SEMI-EXPOSED SURFACES AND ALL BALANCING FACES OF LAMINATED PANELS SHALL BE PLASTIC LAMINATE. FOR WOOD PRODUCTS, ALL EXPOSED SURFACES AND ALL SEMI-EXPOSED SURFACES SHALL BE WOOD VENEER WITH VENEERED OR SOLID WOOD EDGES (INCLUDING BOTH SIDES OF DOORS AND DRAWER FRONTS). FOR ALL OTHER INTERIOR, SURFACES SHALL BE "MELAMINE" OR APPROVED EQUAL CABINET LINER. MINIMUM VENEER AND OVERLAY THICKNESS. TOP AND SHELF EDGE: 0.050" THICK MINIMUM; VERTICAL SURFACES: 0.028" THICK MINIMUM;
HORIZONTAL SURFACES: 0.050" THICK MINIMUM; CABINET LINER: 0.020" THICK MINIMUM. REFER TO FINISH ELEVATIONS FOR COLOR SPECIFICATIONS.
BUILDING MANAGEMENT WILL NOT ALLOW ANY ON SITE LAMINATING.
12. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL APPLIANCE, VENDING AND EQUIPMENT DIMENSIONS PRIOR TO PRODUCTION OF MILLWORK.
13. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING, LOCATING AND INSTALLING ALL FIRE RETARDANT BLOCKING REQUIRED TO ADEQUATELY
SUPPORT MILLWORK PIECES AND THE RELATED LOADING.
14. THE HEADS OF ALL FASTENERS IN WOOD FRAMES, TRIM, ETC. SHALL BE SUNK, FILLED SMOOTH AND BLENDED WITH FINAL FINISH.
15. IT IS THE CONTRACTORS RESPONSIBILITY TO VERIFY REQUIREMENTS FOR STRUCTURAL STABILITY AND INTEGRITY OF THE CASEWORK. ANY DISCREPANCIES IN THE DESIGN INTENT SHOULD BE BROUGHT TO THE ATTENTION OF THE ARCHITECT BEFORE COMMENCEMENT OF THE WORK.
16. THE ARCHITECT SHALL REVIEW SHOP DRAWINGS SOLELY FOR THEIR CONFORMANCE WITH DESIGN INTENT, AND INFORMATION GIVEN IN THE CONSTRUCTION DOCUMENTS. THE ARCHITECT SHALL NOT BE RESPONSIBLE FOR ANY ASPECTS OF SHOP DRAWING SUBMISSIONS THAT AFFECT OR ARE AFFECTED BY WORKMANSHIP AND MATERIALS THAT ARE DEFECTIVE OR FAIL TO CONFORM THE REQUIREMENTS OF THE DRAWINGS, SPECIFICATIONS OR RELATED DOCUMENTS.
GLAZING PUBLICATIONS: COMPLY WITH PUBLISHED RECOMMENDATIONS OF GLASS PRODUCT MANUFACTURERS AND ORGANIZATIONS BELOW, UNLESS MORE STRINGENT REQUIREMENTS ARE INDICATED BY LOCAL MUNICIPALITY. VERIFY CODE COMPLIANCE WITH IBC SECTION 2406 AND TABLE 2406.2(1) AND (2) AND THE RECOMMENDATIONS OF THE CONSUMER PRODUCTS SAFETY COMMISSION. REFER TO THESE PUBLICATIONS FOR GLAZING TERMS NOT OTHERWISE DEFINED IN
THIS SECTION OR IN REFERENCED STANDARDS.
GANA'S "LAMINATED GLASS DESIGN GUIDE"
1. GANA PUBLICATIONS: GANA'S "GLAZING MANUAL" AND "LAMINATED GLASS DESIGN GUIDE."
2. AAMA PUBLICATIONS: AAMA GDSG-1, "GLASS DESIGN FOR SLOPED GLAZING," AND AAMA TIR-A7, "SLOPED GLAZING GUIDELINES."
3. SIGMA PUBLICATIONS: SIGMA TM-3000, "VERTICAL GLAZING GUIDELINES," AND SIGMA TB-3001, "SLOPED GLAZING GUIDELINES."
2. ALL GLASS SHALL BE ORDERED WITHOUT MANUFACTURERS STAMP AND FREE OF BLEMISHES AND TONG MARKS.
3. PROVIDE TEMPERED OR FIRE RATED GLASS AS SHOWN ON PLAN AND REQUIRED BY CODE. ALL LABELS MUST BE VISIBLE AFTER INSTALLATION FOR
VERIFICATION BY AUTHORITIES, AND REMOVED DURING FINAL CLEAN UP.
FIRE-RATED WINDOW ASSEMBLIES: ASSEMBLIES COMPLYING WITH NFPA 80 THAT ARE LISTED AND LABELED BY A TESTING AND INSPECTING AGENCY ACCEPTABLE TO AUTHORITIES HAVING JURISDICTION, FOR FIRE RATINGS INDICATED, BASED ON TESTING ACCORDING TO NFPA 257.
SAFETY GLASS: CATEGORY II MATERIALS COMPLYING WITH TESTING REQUIREMENTS IN 16 CFR 1201 AND ANSI Z97.1.
4. FIELD VERIFY GLAZING OPENINGS PRIOR TO ORDERING GLASS.
1. THE GENERAL CONTRACTOR SHALL SUBMIT FOR THE ARCHITECT'S APPROVAL, SAMPLES OF ALL REVEALS, TRIM PIECES, ETC. AND 12" X 12" FINISH SAMPLES OF ALL SPECIFIED MATERIALS PRIOR TO ORDERING. PROVIDE SAMPLES IN A TIMELY MANNER AS NOT TO DELAY THE PROJECT COMPLETION DATE.
2. THE GENERAL CONTRACTOR SHALL PROVIDE PROTECTIVE COVERINGS FOR CARPETS, FURNISHINGS AND EXISTING FINISHES IN AREAS OF CONSTRUCTION AND SHALL BE RESPONSIBLE FOR THE REPAIR OF ANY DAMAGE CAUSED BY THE WORK OF THE GENERAL CONTRACTOR AND ALL SUBCONTRACTORS.
IV. MILLWORK
V. GLASS AND GLAZING
VI. FINISHES
1. LAYOUT THE TOTAL WORK AREA PRIOR TO PROCEEDING WITH CONSTRUCTION TO ALLOW THE ARCHITECT THE OPPORTUNITY TO REVIEW ANY CONFLICTS IN
THE FIELD.
2. NO DRILLING, CORING, ETC. IS ALLOWED IN FLOOR SLABS OF THE BUILDING WITHOUT PRIOR CONSENT OF THE BUILDING MANAGER AND REVIEW BY THE OWNER'S STRUCTURAL ENGINEER. X-RAY (OR USE OF OTHER SIMILAR MEANS) FLOOR SLAB AS REQUIRED TO CONFIRM LOCATION OF OBJECTS EMBEDDED IN OR ATTACHED TO SLAB PRIOR TO PENETRATION. NO DRILLING OR POWER WORK SHALL TAKE PLACE DURING NORMAL BUSINESS HOURS AS DIRECTED BY
BUILDING OWNER UNLESS SCHEDULED IN ADVANCE WITH THE PROPERTY MANAGER..
3. ALL PARTITIONS SHALL BE TYPE "P1" UNLESS NOTED OTHERWISE, AND ALL DIMENSIONS ARE TO FINISH FACE OF PARTITION UNLESS NOTED OTHERWISE.
4. WHERE PARTITIONS TERMINATE AT WINDOW MULLIONS, CENTER THE PARTITION ON THE MULLION UNLESS OTHERWISE NOTED. DO NOT FASTEN, CAULK OR
GLUE TO WINDOW MULLIONS. REFER TO DETAILS REFERENCED ON PLANS.
5. DIMENSIONS NOTED "HOLD" ARE CRITICAL AND SHALL SET PRECEDENT FOR LAYOUT OF PARTITIONS.
6. "ALIGN" MEANS SIMILAR COMPONENTS OR CONSTRUCTION, (E.G., WALLS, JAMBS, ETC.) SHALL BE IN LINE ACROSS VOIDS.
7. "TYPICAL" MEANS IDENTICAL FOR ALL APPARENT SAME CONDITIONS. "SIMILAR" MEANS COMPARABLE CHARACTERISTICS FOR THE CONDITION NOTED.
"OPPOSITE OR OH" MEANS SIMILAR COMPONENTS OR CONSTRUCTION ON OTHER SIDE.
8. ANY DIMENSION NOTED "VERIFY" OR "AS REQUIRED" MUST BE RE-MEASURED ON SITE AND CONFIRMED WITH THE ARCHITECT PRIOR TO PROCEEDING WITH
CONSTRUCTION.
9. ALL HEIGHTS ARE DIMENSIONED FROM FINISH FLOOR UNLESS NOTED OTHERWISE.
10. DOOR FRAMES OCCURRING ADJACENT TO INTERSECTING PARTITIONS SHALL BE INSTALLED 4" FROM THE BACK EDGE OF JAMB TO THE FACE OF THE
ADJACENT PARTITION UNLESS NOTED OTHERWISE.
11. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR VERIFYING ALL EQUIPMENT SIZES, REQUIREMENTS AND INSTALLATION METHODS WHERE NOTED, "TENANT/OWNER PROVIDED..........GENERAL CONTRACTOR TO INSTALL" PRIOR TO CONSTRUCTION NOTIFY ARCHITECT/TENANT OF ANY DISCREPANCIES)..
12. NEW GYPSUM CONSTRUCTION MEETING EXISTING CONSTRUCTION IN THE SAME PLANE SHALL BE FLUSH WITH NO VISIBLE JOINTS.
13. ALL GYPSUM BOARD CONSTRUCTION SHALL BE PLUMB AND IN TRUE STRAIGHT LINES AND SHALL CONFORM TO ASTM C840 AND ASTM C475/C475M-02 AS
WELL AS MANUFACTURER'S WRITTEN STANDARDS OF CONSTRUCTION.
14. ALL EXTERIOR CORNERS SHALL HAVE METAL CORNER BEADS. ALL PARTITIONS SHALL HAVE FILL BEAD AT TOP OF WALL AS DETAILED.
15. GYPSUM WALLBOARD ON PARTITIONS REQUIRING A RATING OF ONE-HOUR OR MORE SHALL BE TAPED AND THE SCREWS SPOTTED WHETHER OR NOT WALL
TREATMENT IS SCHEDULED.
16. DRYWALL SHALL BE SCREWED TO METAL STUDS AND FINISHED WITH (3) COATS OF TAPE/COMPOUND, SANDING BETWEEN COATS AND AFTER FINAL COAT.
II. CONSTRUCTION
4. THE GENERAL CONTRACTOR IS RESPONSIBLE FOR THE SELECTION AND APPLICATION OF THE APPROPRIATE PAINT/STAIN / SEAL FOR SPECIALTY APPLICATIONS, I.E. METAL, CONCRETE, STRUCTURE, ETC. AND THE CONFIRMATION OF THESE TYPES WITH THE ARCHITECT PRIOR TO ORDERING / APPLICATION.
5. NO FINISH / MATERIAL SUBSTITUTIONS WILL BE ACCEPTED, UNLESS REVIEWED BY ARCHITECT AND APPROVED IN WRITING.
6. ALL WALL / CEILING REVEALS AND TRIM SHALL BE PAINTED TO MATCH ADJACENT SURFACES, UNLESS NOTED OTHERWISE.
7. ALL WALLS SHALL BE SMOOTH ROLLED EGGSHELL LATEX ENAMEL UNLESS NOTED OTHERWISE. ALL PAINT SHALL BE MANUFACTURERS PREMIUM GRADE WASHABLE LATEX FINISH. CEILINGS SHALL BE SMOOTH ROLLED WITH FLAT LATEX ENAMEL UNLESS OTHERWISE NOTED ON PLANS. REFER TO FINISH
SPECIFICATIONS AND REFLECTED CEILING PLAN FOR PAINT TYPE AND COLOR.
8. ALL DOORS AND FRAMES SHALL BE FINISHED PER THE FINISH PLAN AND SPECIFICATIONS. ALL PAINTED METAL DOOR FRAMES TO RECEIVE THREE (3) FINISH
COATS SEMI-GLOSS ALKYD ENAMEL, SPRAYED IN THE FIELD.
VI. FINISHES (CONTINUED) VII. LIGHTING (CONTINUED)
1. ALL ELECTRICAL WORK SHALL BE "DESIGN/BUILD" BY THE ELECTRICAL CONTRACTOR. INDIVIDUAL ELECTRICAL COMPONENTS, WHICH INCLUDES BUT IS NOT LIMITED TO LIGHT FIXTURES, ELECTRICAL OUTLETS, PHONE, DATE AND ETC. AS SHOWN, ARE NOT TO BE USED AS ARCHITECTURAL GUIDELINES FOR LOCATION OF THESE ITEMS IN THE SPACE. REFER TO ARCHITECTURAL DRAWINGS FOR SPECIFIC LOCATIONS. THE SPECIFIC SIZING & ENGINEERING OF THESE COMPONENTS, TO ENSURE ACCEPTABLE OPERATION OF THE INDIVIDUAL SYSTEMS AND CONFORMANCE WITH APPLICABLE CODES AND REGULATIONS, ARE THE RESPONSIBILITY OF THE DESIGN/BUILD ELECTRICAL CONTRACTOR. THE DESIGN/BUILD ELECTRICAL CONTRACTOR SHALL PRODUCE DRAWINGS AS REQUIRED FOR PERMITS, AT NO EXPENSE TO THE OWNER, ARCHITECT OR TENANT. UPON COMPLETION ALL TRADES SHALL PROVIDE OWNER WITH COMPLETE RECORD SET OF DRAWINGS (OFTEN REFERRED TO AS "AS-BUILTS"). THE LANDLORD, TENANT AND ARCHITECT SHALL ASSUME NO RESPONSIBILITY FOR THE PROPER DESIGN AND
INSTALLATION OF THE ELECTRICAL SYSTEMS.
2. ALL ELECTRICAL/DATA AND COMMUNICATION RECEPTACLES SHALL BE LOCATED VERTICALLY 1'-6" A.F.F., UNLESS NOTED OTHERWISE. REFER TO PLANS, ELEVATIONS AND DETAILS FOR CENTERLINE OF MOUNTING HEIGHTS. MATCH EXISTING HEIGHT IF ADA COMPLIANT, MINIMUM 1'-3" A.F.F.
3. ALL SWITCHES/DIMMERS/LIGHT CONTROLS SHALL ALIGN WITH ADJACENT DOOR HARDWARE, AND BE LOCATED 6" FROM THE OUTSIDE OF THE DOOR
FRAME/WINDOW FRAME, UNLESS NOTED OTHERWISE.
4. ELECTRICAL OUTLETS WITHIN 6'-0" OF SINKS AND OTHER WATER SOURCES SHALL BE GFI.
5. IF ANY EXPOSED ITEM IN THE CEILING REQUIRES RELOCATION DUE TO CONFLICT OR DISCREPANCIES, DO NOT PROCEED WITHOUT CLARIFICATION FROM THE ARCHITECT. VERIFY THE COMPATIBILITY OF ALL LIGHT FIXTURES WITH CEILING MATERIALS AND ADJACENT CONSTRUCTION.
6. PROVIDE RATED ASSEMBLY AT ALL SLAB AND WALL PENETRATIONS. INCLUDING PENETRATIONS WHERE RECEPTACLES ETC. WERE REMOVED DURING DEMOLITION. ALL EXISTING AND NEW PENETRATIONS SHALL BE PROVIDED WITH RATED ASSEMBLIES TO MATCH RATING OF WALL OR FLOOR RESPECTIVELY.
REFER TO HILTI FIRESTOPPING SCHEDULE FOR TYPICAL RATED ASSEMBLY PENETRATION REQUIREMENTS
7. VERIFY POWER REQUIREMENTS FOR ALL APPLIANCES, SPECIAL EQUIPMENT, OWNER SUPPLIED EQUIPMENT, ETC.
8. ALL FURNITURE IS N.I.C. (NOT IN CONTRACT) TENANT TO SUPPLY AND INSTALL- ELECTRICAL CONTRACTOR SHALL PROVIDE POWER AND MAKE FINAL HOOK
UP OF SYSTEMS FURNITURE USING TENANT PROVIDED PIGTAIL OR WHIP CONNECTOR.
9. PROVIDE THE ARCHITECT WITH SWITCHING/DIMMING DRAWINGS AND THE LAYOUT OF THE REQUIRED EMERGENCY LIGHTING PRIOR TO PROCEEDING WITH
CONSTRUCTION.
10. INSTALL ALL WET AREA DEVICES, RECEPTACLES AND FIXTURES IN COMPLIANCE AND ACCORDANCE WITH MANUFACTURERS SPECIFICATIONS, AS WELL AS ALL APPLICABLE CODES, LAWS AND REGULATIONS. DEVICE FINISHES TO MATCH DEVICES IN NON-WET AREAS. ALL DEVICES WITHIN THE AREA SHALL MATCH IN
STYLE AND COLOR.
11. THE CONTRACT DOCUMENTS INDICATE DEVICE LOCATION, SPECIFICATION, TYPE ONLY WITHIN A SPACE OR AT A SINGLE LOCATION. ALL EXISTING DEVICES TO BE RE-USED SHALL BE CHANGED TO MATCH NEW, UNLESS OTHERWISE NOTED. ALL DEVICES/COVER PLATES WITHIN AN AREA OF ROOM SHALL MATCH IN
STYLE, COLOR AND SIZE.
12. ALL SWITCHES AND RECEPTACLES DIMMERS SHALL BE OF SAME STYLE AND MANUFACTURER. REMOVE ALL ABANDONED RECEPTACLES NOT SHOWN ON
PLANS. DEVICE COVER PLATES SHALL BE COMMERCIAL QUALITY "HARD PLASTIC" U.N.O.
13. SUPPLY AND INSTALL EXIT LIGHTS, AUDIO ALARMS AND EMERGENCY LIGHTING CIRCUITRY AS REQUIRED BY GOVERNING BUILDING CODES. THE ELECTRICAL SUBCONTRACTOR IS RESPONSIBLE FOR CONFIRMING THE LOCATION OF ALL DEVICES WITH THE ARCHITECT PRIOR TO BEGINNING CONSTRUCTION.
14. ELECTRICAL CONTRACTORS SHALL PROVIDE 3/4" CONDUIT AND BOX WITH A PULL STRING FOR OWNER/TENANT TELEPHONE/DATA AT LOCATIONS SHOWN ON PLAN. STUB CONDUIT TO ABOVE CEILING. COORDINATE ONLY, THE INSTALLATION OF TELEPHONE AND COMPUTER CABLES, JACKS AND EQUIPMENT WITH TENANT AND OWNER. WIRING TO BE COMPLETE BEFORE INSTALLATION OF CEILING TILES. COORDINATE WITH TENANT'S CABLE CONTRACTOR ON ALL ITEMS INCLUDING EXISTING CABLE TO REMAIN. ALL NEW CABLE LOCATED ABOVE CEILING SHALL BE PLENUM RATED.
15. FLOOR RECEPTACLES FOR POWER, TELEPHONE, DATA, ETC. SHALL BE FLUSH TYPE (PROVIDE SPECIFICATION AND CATALOG CUT SHEET TO ARCHITECT). ALL FLOOR PENETRATIONS MUST BE X-RAYED AND COORDINATED WITH STRUCTURAL CONSULTANT AND BUILDING MANAGEMENT.
16. DO NOT MOUNT THERMOSTATS, SWITCHES OR OUTLETS AT A/V BOARDS, WALL CABINETS OR WOOD WALL PANELING. COORDINATE LOCATIONS WITH
FURNITURE INSTALLER AND ARCHITECT.
17. DO NOT ATTACH CABLING TO CEILING SUSPENSION WIRES. ATTACH TO BUILDING STRUCTURE ONLY.
18. PROVIDE TYPED PANEL DIRECTORIES AT ALL NEW AND MODIFIED PANEL BOARDS UPON COMPLETION OF CONSTRUCTION.
22. CONTRACTOR SHALL BE RESPONSIBLE FOR NUMBERS OF FIXTURES ON CIRCUITS AND CODE COMPLIANCE.
23. MANUFACTURER AND/OR GENERAL CONTRACTOR SHALL SUBMIT FOR APPROVAL OF THE SHOP DRAWINGS OF ALL CUSTOM FIXTURES PRIOR TO FABRICATION
OF SAME.
24. ALL COMPONENT PARTS OF ARCHITECTURAL LIGHTING INSTALLATIONS (I.E. LINEAR FIXTURES) SHALL BE PROVIDED BY GENERAL CONTRACTOR. COLOR AND
FINISH SPECIFICATION SHALL BE BY THE ARCHITECT.
25. ELECTRICAL CONTRACTOR SHALL VERIFY CEILING CONSTRUCTION FOR EACH FIXTURE TYPE AND LOCATION AND SHALL COORDINATE TRIM DETAILS WITH
ARCHITECT PRIOR TO ORDERING.
26. BY APPROVING AND SUBMITTING SHOP DRAWINGS, PRODUCT DATA, SAMPLES AND SIMILAR SUBMITTALS, THE GENERAL CONTRACTOR CONFIRMS THAT HE/SHE HAS DETERMINED AND VERIFIED MATERIALS, FIELD MEASUREMENTS AND FIELD CONSTRUCTION CRITERIA, AND HAS CHECKED AND COORDINATED THE INFORMATION CONTAINED WITHIN SUCH SUBMITTALS WITH THE REQUIREMENTS OF THE WORK AND OF THE CONTRACT DOCUMENTS.
27. UNLESS OTHERWISE SPECIFIED, VOLTAGES OF ALL LAMPS SHALL BE DETERMINED BY ELECTRICAL ENGINEER. COORDINATE PROPER LAMP BASE TYPES WITH
SOCKETS PROVIDED IN SPECIFIED FIXTURE.
28. MANUFACTURER AND/OR GENERAL CONTRACTOR SHALL BE RESPONSIBLE TO ASSURE THAT ALL FIXTURES SPECIFIED FOR EXTERIOR USE SHALL BE TREATED
WITH A WEATHER-RESISTANT COATING TO PROTECT FROM CORROSION.
29. ALL NEW FLUORESCENT LAMPS SHALL MATCH BUILDING STANDARD "KELVIN" TEMPERATURE COLOR.
1. PRIOR TO THE PUNCHLIST, TEST ALL ELECTRICAL, FIRE PROTECTION, PLUMBING, HVAC AND RELATED EQUIPMENT. ALL DOORS, HARDWARE, MILLWORK AND GENERAL FINISHES SHALL BE INSPECTED FOR COMPLETENESS OF INSTALLATION AND SMOOTHNESS OF OPERATION.
2. PRIOR TO THE FINAL PUNCHLIST, CLEAN SPACE GENERALLY INCLUDING REMOVAL OF ALL CONSTRUCTION DEBRIS, WIPE DOWN ALL WALLS, CEILING, GLASS, MILLWORK, ETC. AND CLEANING OF FLOOR COVERING, LIGHT FIXTURES, RECEPTACLES, ETC.
3. AFTER COMPLETION OF PUNCHLIST, PROVIDE FINAL THOROUGH CLEANING SERVICES INCLUDING CARPET SHAMPOOING, FINAL CLEANING OF GLASS AND
WINDOW BLINDS, MILLWORK AND DOORS.
4. AFTER COMPLETION OF PUNCHLIST, SUPPLY THE OWNER/TENANT WITH A PROJECT MANUAL THAT SHALL INCLUDE ALL WARRANTIES WITH CONTRACT INFORMATION AS WELL AS CLEANING, REPAIR AND MAINTENANCE INSTRUCTIONS TO COVER ALL AREAS OF CONSTRUCTION.
5. REMOVE ALL LABELS, STICKERS, ETC. FROM APPLIANCES AND PROVIDE TO CLIENT. REMOVE ANY RESIDUE FROM LABELS.
6. PROVIDE REDLINED "RECORD SET" DOCUMENTS FROM EACH SUBCONTRACTOR TO ARCHITECT/OWNER UPON PROJECT COMPLETION.
7. PROVIDE TENANT WITH A LIST OF ALL RE-SUPPLY VENDORS TO INCLUDE NAMES, ADDRESSES AND PHONE NUMBERS AND WEBSITES.
NOTE:
GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR VERIFYING VERTICAL SPAN OF FRAMING ASSEMBLIES AND VERIFYING THE STUD GAUGE AND DEPTH LIMITS ARE NOT EXCEEDED, PRIOR TO ORDERING MATERIALS. ARCHITECT SHALL BE NOTIFIED IMMEDIATELY IF ANY DISCREPANCIES ARE FOUND. THE SCHEDULE BELOW IS BASED ON PUBLISHED DIETRICH METAL FRAMING CHARTS. ARCHITECT SHALL NOT ASSUME LIABILITY FOR ANY MODIFICATIONS OR ALTERATIONS TO THESE PUBLISHED STANDARDS BY
DIETRICH METALS.
THIS LIMITING HEIGHTS DATA IS FROM ASTM C754. DIETRICH METAL FRAMING LIMITING HEIGHTS IS USED AS THE DESIGN BASIS. THIS INFORMATION IS ONLY PROVIDED AS A REFERENCE, AND ALIGNED STUDIO, LLC WILL NOT BE RESPONSIBLE FOR THE PERFORMANCE OF WALLS BASED ON THIS TABLE.
CONSULT CURRENT INFORMATION FROM ASTM C754 AND SSMA (STEEL STUD MANUFACTURERS
ASSOCIATION), AND THE STUD MANUFACTURERS FOR LIMITING HEIGHTS CHARACTERISTICS OF THEIR
PARTICULAR PRODUCTS.
LIMITING HEIGHTS APPLY TO WALLS CONSTRUCTED WITH MINIMUM 1/2" THICKNESS OF GYPSUM BOARD
AND WITH A MINIMUM OF ONE FULL-HEIGHT LAYER ON BOTH SIDES OF THE STUD FRAMING.
LIMITING HEIGHTS ARE BASED ON TESTS CONDUCTED WITH GYPSUM BOARD ATTACHED WITH SCREWS
SPACED 12" O.C. TO FRAMING MEMBERS.
VIII. ELECTRICAL, COMMUNICATIONS AND DATA
X. FINAL PUNCHLIST, CLEAN UP AND PROJECT CLOSE OUT
1. MECHANICAL ENGINEERING WILL BE HANDLED BY KARLA RITTER OF K. RITTER CONSULTING ENGINEERS. ALL PLUMBING AND FIRE PROTECTION WORK SHALL BE "DESIGN/BUILD" BY RESPECTIVE CONTRACTORS. INDIVIDUAL MECHANICAL, SPRINKLER AND PLUMBING COMPONENTS, WHICH INCLUDE BUT ARE NOT LIMITED TO SPRINKLER HEADS, THERMOSTATS, HVAC GRILLS, AND ETC. AS SHOWN, ARE TO BE USED AS ARCHITECTURAL GUIDELINES FOR LOCATION OF THESE ITEMS IN THE SPACE. THE SPECIFIC SIZING AND ENGINEERING OF THESE COMPONENTS, TO ENSURE ACCEPTABLE OPERATION OF THE INDIVIDUAL SYSTEMS AND CONFORMANCE WITH APPLICABLE CODES AND REGULATIONS, ARE THE RESPONSIBILITY OF THE DESIGN BUILD CONTRACTOR AND HIS DESIGN BUILD SUBCONTRACTORS. THE SUBCONTRACTOR SHALL PRODUCE DRAWINGS AS REQUIRED FOR PERMITS, AT NO EXPENSE TO THE OWNER, ARCHITECT OR TENANT.
UPON COMPLETION, ALL TRADES SHALL PROVIDE OWNER WITH A COMPLETE RECORD SET OF DRAWINGS (OFTEN REFERRED TO AS "AS-BUILTS"). THE LANDLORD, TENANT AND ARCHITECT SHALL ASSUME NO RESPONSIBILITY FOR THE PROPER DESIGN AND INSTALLATION OF MECHANICAL, PLUMBING OR FIRE
PROTECTION SYSTEMS.
IX. MECHANICAL / PLUMBING / FIRE SAFETY
INTERIOR FRAMING LIMITING HEIGHTS
STUD
SPACING
(INCHES)
DESIGN
LIMIT
(PSF)
ALLOWABLE
DEFLECTION
SPAN SSMA CODESTUD DEPTH (INCHES)
1 5/8 - STN 25 GA.
1 5/8 - STE 20 GA.
1 5/8 - STX 20 GA. 16
16 5
L / 360
L / 360
L / 360
6-0
7-3
8-5
16 5
L / 360
L / 360
L / 360
2 1/2 - STN 25 GA.
2 1/2 - STE 20 GA.
2 1/2 - STX 20 GA.
9-10
10-6
11-2
L / 360
L / 360
L / 360
L / 360
L / 360
L / 360
3 5/8 - STN 25 GA.
3 5/8 - STN 25 GA.
3 5/8 - STE 20 GA.
3 5/8 - STE 20 GA.
3 5/8 - STX 20 GA.
3 5/8 - STX 20 GA.
12-4
11-7
13-7
12-0
14-10
16-8
362S125-28
362S125-28
4 - STN 25 GA.
4 - STN 25 GA.
4 - STE 20 GA.
4 - STE 20 GA.
6 - STN 25 GA.
6 - STN 25 GA.
6 - STE 20 GA.
6 - STE 20 GA.
L / 360
L / 360
L / 360
L / 360
L / 360
L / 360
L / 360
L / 360
13-4
12-4
15-2
13-5
17-11
16-9
20-3
17-8
MOST COMMON UL SYSTEMS THROUGH CONCRETE FLOOR / WALL OR BLOCK WALL
UL SYSTEMPENETRANT
C - AJ - 1226METAL PIPE
PVC 3" MAXIMUM
PVC 6" MAXIMUM
PVC 12" MAXIMUM
CABLE BUNDLE
METAL PIPE WITH GLASS FIBER INSULATION
SHEET METAL DUCT
MULTIPLE PENETRANTS
METAL PIPE WITH AB / PVC INSULATION
C - AJ - 2168
C - AJ - 2243
C - AJ - 2115
C - AJ - 3180
C - AJ - 5091
C - AJ - 5090
C - AJ - 7051
C - AJ - 8099
MOST COMMON UL SYSTEMS THROUGH GYPSUM BOARD PARTITIONS
UL SYSTEMPENETRANT
W - L - 1054METAL PIPE
PVC 3" MAXIMUM
PVC 6" MAXIMUM
PVC 12" MAXIMUM
CABLE BUNDLE
METAL PIPE WITH GLASS FIBER INSULATION
SHEET METAL DUCT
MULTIPLE PENETRANTS
METAL PIPE WITH AB / PVC INSULATION
W - L - 2128
W - L - 2078
W - L - 2315
W - L - 3065
W - L - 5029
W - L - 5028
W - L - 7040
W - L - 8004
MOST COMMON UL SYSTEMS FOR TOP OF WALL JOINTS WITH GYPSUM BOARD PARTITIONS
UL SYSTEM (CP - 606)DECK TYPE / WALL ORIENTATION UL SYSTEM (CP - 672)
HW - D - 0045PERPENDICULAR TO METAL DECK HW - D - 0042
HW - D - 0184
HW - D - 0209
HW - D - 0077
PARALLEL TO METAL DECK
FLAT CONCRETE
CUT TO PROFILE (CASTLE CUT)
HW - D - 0049
HW - D - 0106
N. A.
MOST COMMON UL SYSTEMS FOR TOP OF WALL JOINTS WITH CONCRETE / BLOCK PARTITIONS
UL SYSTEM (CP - 606)DECK TYPE / WALL ORIENTATION UL SYSTEM (CP - 672)
PERPENDICULAR TO METAL DECK
PARALLEL TO METAL DECK
FLAT CONCRETE
HW - D - 008
N. A.
HW - D - 0268
HW - D - 1037
HW - D - 0181
HW - D - 0097
1. THESE PLANS REPRESENT OUR INTERPRETATION OF A LIMITED NUMBER OR THE TITLE III PROVISIONS OF THE AMERICANS WITH DISABILITIES ACT (ADA), FOR THE SCOPE OF WORK INDICATED ONLY. ALIGNED STUDIO, LLC SHALL ASSUME NO RESPONSIBILITY FOR DEVIATIONS AND/OR DELETIONS FROM THESE DRAWINGS BY BUILDING OWNERS, PROPERTY MANAGERS, CONTRACTORS, ETC. ALIGNED STUDIO, LLC SHALL ASSUME NO RESPONSIBILITY FOR ANY WORK REQUIRED BY THE ADA WHICH IS NOT SPECIFICALLY INDICATED ON THESE DRAWINGS. NO LIABILITY SHALL BE ASSUMED FOR DECISIONS OR COMMITMENTS
MADE ON THE BASIS OF THE ADA INFORMATION PRESENTED ON THESE DRAWINGS.
XI. AMERICANS WITH DISABILITIES ACT (ADA)
3. ALL SURFACES SHALL BE PROPERLY PREPARED AS REQUIRED TO RECEIVE SPECIFIED FINISH INCLUDING WALLCOVERING, FLOORING, PAINT, STONE, ETC.
EACH FINISH SUBCONTRACTOR SHALL INSPECT SURFACES TO RECEIVE FINISHES AND REPORT UNFAVORABLE CONDITIONS AND SUBSTRATES TO THE GENERAL CONTRACTOR BEFORE PROCEEDING WITH THE WORK. GENERAL CONTRACTOR SHALL NOTIFY ARCHITECT IMMEDIATELY. GENERAL CONTRACTOR SHALL BE RESPONSIBLE FOR REWORK OF ANY SUBSTRATES SEEMED UNACCEPTABLE FOR FINISH APPLICATION. PROVIDE USG 'DUROCK' CEMENT BOARD (OR APPROVED
EQUAL) AS A SUBSTRATE FOR ALL CERAMIC, PORCELAIN OR STONE TILE FINISHES.
VII. LIGHTING
1. VERIFY THE COMPATIBILITY OF ALL LIGHT FIXTURES WITH CEILING MATERIALS, ADJACENT CONSTRUCTION AND ADJACENT FINISHES PRIOR TO SUBMITTING SHOP DRAWINGS, ORDERING FIXTURES AND NOTIFYING THE ARCHITECT OF ANY CONFLICTS WITH THE PROPOSED INSTALLATION.
2. PROVIDE ALL MISCELLANEOUS HARDWARE, ATTACHMENT DEVICES, TRANSFORMERS, ETC. AS NECESSARY TO PROVIDE A COMPLETED INSTALLATION.
3. ALL CEILING PENETRATIONS SHALL BE CHECKED AND CONFIRMED BUILDABLE BEFORE ANY RELATED ELEMENTS ARE CONSTRUCTED. IF ANY LIGHT FIXTURE CANNOT BE INSTALLED DUE TO CONFLICTS WITH SPRINKLERS, BEAMS, H.V.A.C., ETC. OR ANY DISCREPANCIES OR QUESTIONS ARISE, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR NOTIFYING THE ARCHITECT IMMEDIATELY. DO NOT PROCEED WITH THE WORK WITHOUT THE APPROVAL OF THE ARCHITECT. IF WORK PROCEEDS WITHOUT THE ARCHITECT'S APPROVAL/CONFIRMATION REWORK/RELOCATION WILL BE AT THE GENERAL CONTRACTOR'S EXPENSE.
17. ALL DRYWALL CEILINGS SHALL BE LEVEL AND WITH NO VISIBLE JOINTS OR IMPERFECTIONS. CONTROL JOINTS WILL ONLY BE LOCATED AS SPECIFICALLY NOTED IN CONSTRUCTION DOCUMENTS. CONTRACTOR TO NOTIFY ARCHITECT IMMEDIATELY PRIOR TO CONSTRUCTION IF C.J. ARE RECOMMENDED, BUT NOT
INDICATE ON THE DRAWINGS.
18. NO ACCESS PANELS SHALL BE ALLOWED IN DRYWALL CEILINGS WITHOUT PRIOR APPROVAL FROM ARCHITECT, UNLESS NOTED OTHERWISE ON PLANS. IF ACCESS PANEL IS REQUIRED TO ACCESS EQUIPMENT ABOVE, LOCATION SHALL BE COORDINATED WITH ARCHITECT PRIOR TO CONSTRUCTION.
19. ALL CEILING PENETRATIONS SHOULD BE CONFIRMED AS BUILDABLE BEFORE CONSTRUCTION. IF THERE ARE ANY DISCREPANCIES OR OTHER COORDINATION QUESTIONS, THE GENERAL CONTRACTOR IS RESPONSIBLE FOR OBTAINING A CLARIFICATION FROM THE ARCHITECT BEFORE PROCEEDING WITH THE WORK IN
QUESTION OR ANY RELATED/ADJACENT WORK.
20. EXPOSED ITEMS IN THE CEILING THAT REQUIRE RELOCATION DUE TO CONFLICT, SHALL BE INCLUDED IN THIS WORK.
9. PERFORM PREPARATION AND CLEANING PROCEDURES IN STRICT ACCORDANCE WITH PAINT MANUFACTURER'S INSTRUCTION. APPLY PAINT IN ACCORDANCE WITH MANUFACTURER'S DIRECTIONS. USE APPLICATORS AND TECHNIQUES BEST SUITED FOR THE SUBSTRATE AND TYPE OF MATERIAL BEING APPLIED AS
SPECIFIED BY THE MANUFACTURER.
10. PROVIDE PRIMERS AND OTHER UNDERCOAT PAINT PRODUCED BY THE SAME MANUFACTURER AS FINISH COATS. USE ONLY THINNERS APPROVED BY THE PAINT MANUFACTURER, AND USE ONLY WITHIN RECOMMENDED TEMPERATURE AND HUMIDITY LIMITS.
11. PREVIOUSLY UNFINISHED SURFACES SHALL RECEIVE ONE COAT-TINTED PRIMER AND TWO COATS FINISH PAINT. ALL OTHER SURFACES SHALL RECEIVE TWO
COATS FINISH PAINT.
INTERIOR PAINT SYSTEMS:
IP-1 (DRYWALL WALLS): EGGSHELL FINISH U.N.O.
1ST COAT- PRIMER/SEALER TINTED TO FINAL COLOR.
2ND COAT- EGGSHELL LATEX ENAMEL.
3RD COAT- EGGSHELL LATEX ENAMEL.
QUALITY: TOP OF THE LINE
4. LAY OUT THE…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .