(06) GEOGARD EPDM LAP DETAIL (1).pdf

PDF 132 KB Posted

Attached to
ROOF RENOVATION - ROOF SECTIONS
Solicitation number
RFP BEAL 180000002414 1
Issued by
Ingham County, Michigan

About this file

This is a technical specification document providing detailed design guidance for EPDM (ethylene propylene diene monomer) roofing lap detail installation, likely supporting a state or local infrastructure or facilities maintenance contract. The document outlines the physical specifications and installation methodology for EPDM membrane lap joints, including dimensional requirements, material composition, and construction sequencing. The specifications detail the overlap dimensions, adhesive application requirements, sealing procedures, and quality standards necessary for proper roof membrane installation and waterproofing integrity. No specific quantities, response dates, bid deadlines, site visits, bidders' meetings, award dates, or contract term information is provided in this technical specification document.

The document contains no pricing information, set-asides, incumbent contractor details, funding sources, or other commercial terms. As a technical specification sheet rather than a procurement announcement or bid solicitation, this document functions as a supporting exhibit that would accompany a larger contract opportunity package. It establishes the technical performance standards and construction requirements that bidders must meet and that project contractors must follow during execution, ensuring consistency and quality in roofing system installation across the procuring jurisdiction.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it. Updated .