This is a Statement of Work (SOW) for the repair and replacement of main distribution and branch panel boards in Building 6002 at Tinker Air Force Base, Oklahoma.

The project (WWYK050751, Work Task 1119970) requires comprehensive electrical, architectural, mechanical, and fire protection work. Key deliverables include disconnecting and removing existing electrical feeders, circuits, and equipment; installing a new 800-ampere main distribution panelboard (6002-PNL-1) and 225-ampere branch panelboard (6002-PNL-2) in a newly constructed electrical room; running a new 80-foot service entrance from the utility transformer with conduit, conductors, and grounding systems; installing LED lighting with battery backup; modifying the fire alarm system to accommodate new notification devices; providing two new upright sprinklers; rebalancing the HVAC system; and performing all associated demolition, site preparation, testing, and inspection. The Contractor must submit a baseline construction schedule within ten calendar days of Notice to Proceed and maintain monthly progress reports. Key personnel requirements include a Project Manager with minimum ten years' experience, a Quality Control Manager, a Site Safety and Health Officer, and a Project Superintendent with minimum five years' construction experience. All personnel must obtain AFMC Form 387 identification badges prior to commencing work. The Contractor must establish a quality control program per specification section 01 45 00.00 10, comply with EM 385-1-1 safety requirements, and coordinate with government activities regarding utility outages, material submittals, and inspections. Work shall occur during normal duty hours (0700–1600 Monday–Friday), with any outside-hours work to meet schedule at no additional cost to the Government. The project includes Energy Star product requirements for LED lighting and fixtures, with provisions for justification if designated products cannot be used.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Statement of Work - 1 of 26 MACB Preliminary (35%) SOW_v2_Mar 24

STATEMENT OF WORK

REPAIR/REPLACE MAIN DISTRIBUTION & BRANCH PANEL BOARDS, B6002

Project #: WWYK050751 Work Task #: 1119970

Revision: 0 Issued: June 10, 2025

1. SCOPE

1.1 GENERAL

The work to be performed under the terms of this Order consists of furnishing all materials, labor, plant, tools, transportation, equipment, testing services, quality control and incidentals required to accomplish the repair/replacement of the main distribution & branch panel boards, building 6002 at Tinker Air Force Base (AFB), Oklahoma (reference the project drawings for additional location information).

The Contractor shall perform a site investigation to verify existing conditions. If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400.

The Contractor shall be responsible for identifying the necessary logistical, architectural, and structural work elements required to perform the work as described herein. Assemblies, framework, fixtures, or apparatus not readily identified on the project drawings, specifications, or this Statement of Work (SOW) shall be provided by the Contractor as required for a complete, fully operating, and functioning system or systems ready for use by the Government.

Information such as floor plan layouts and dimensions; structural, mechanical, and electrical data;

and location of underground utilities provided by the Government for existing and new construction are based on available as-built documentation, field observation, and equipment selected as design basis by the Government. This information is to be considered approximate and shall be field verified by the Contractor.

1.2 DEFINITIONS

1.2.1 Contracting Officer (CO)

An individual with the authority to enter into, administer, and/or terminate contracts and make related determinations and findings. The term includes certain authorized representatives of the contracting officer acting within the limits of their authority as delegated by the CO.

The CO is the ONLY person authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the contract.

1.2.2 Contracting Officer’s Representative (COR)

An individual designated by the Contracting Officer to perform specific technical or administrative functions.

The COR is not authorized to make any commitments or changes that will affect price, quality, quantity, delivery, or any other term or condition of the Order. It shall be the Contractor’s responsibility to contact the CO concerning any matters where the Contractor believes that the direction received from the COR may affect price, quality, quantity, delivery, or any other term or condition of the Order prior to performing work or purchase of material.

10 Jun 25 Statement of Work - 2 of 26 WWYK050751

1.3 CONTRACTOR PERSONNEL

1.3.1 General Requirements

The Contractor shall ensure that employees and subcontractor employees have current/valid licenses and certifications necessary to perform their functions. Any cost or time associated with obtaining licenses or certifications shall be at the Contractor’s expense.

Personnel shall be easily recognized as a Contractor employee or sub-contractor. This may be accomplished by wearing distinctive clothing bearing the name of the company or by wearing appropriate badges that contain the company name and employee name. The badge shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times. The badge shall clearly identify the individual as a contractor employee.

1.3.2 Key Personnel

The Contractor shall, at a minimum, provide the following key personnel. Submit resumes for personnel fulfilling each of the key positions described below within five (5) calendar days after

NTP.

Exceptions or variances to experience requirements must have prior approval from the Contracting Officer (CO)/Contracting Officer's Representative (COR); exceptions/variances will be considered where the Contractor can demonstrate comparable experience and/or competency.

Forward any requests for variance to the CO; include resumes for personnel listing the qualifications to be considered (e.g. education, experience, professional certifications, etc.).

Required experience levels shall be maintained throughout the duration of the agreement. When personnel changes are required, resumes and a revised organization chart shall be submitted to the CO within five (5) business days of a vacated or filled position.

One Contractor employee may hold up to two (2) key positions; exceptions are noted below (e.g.

a Project Superintendent cannot fulfill the role of the Quality Control Manager). Contractor employees holding more than one key position must meet the minimum requirements for both positions.

1.3.2.1 Project Manager (PM)

The PM will be responsible for the overall performance of this Order. The PM shall have a minimum of ten (10) years combined experience in the following positions: Project Superintendent, Quality Control Manager, Project Manager, Project Engineer, or Construction Manager with general contracting firm engaged in multi-trade commercial construction contracts. The individual must have at least two (2) years' experience as a Project/Program Manager. Provide the name of PM, in writing, to the CO upon award of the Order.

The Contractor shall designate an Alternate PM who may act on behalf of the Contractor when the PM is absent. Qualifications for the Alternate are the same as for the PM. Provide the name of the Alternate, in writing, to the CO upon award of the Order.

The PM or Alternate shall have direct oversight of all project planning, design, and construction activities. The PM shall provide overall Order management, including full authority to develop proposals, negotiate, and sign modifications to Orders; provide

10 Jun 25 Statement of Work - 3 of 26 WWYK050751 subcontract administration; review material submittals and shop drawings; and shall attend all status meetings, site visits and pre-final/final inspections.

The CO must be able to contact the PM or Alternate by phone at all times. Throughout the life of this agreement, the PM or Alternate shall be available to meet with the CO at Tinker AFB one (1) hour during normal duty hours.

1.3.2.2 Quality Control Manager (QCM)

The QCM is responsible for management of the Contractor Quality Control (CQC) Program. The QCM shall have the minimum qualifications set forth in specification section 01 45 00.00 10, Quality Control (for purposes of this SOW, QCM is equivalent to CQC System Manager).

The Contractor shall designate an Alternate QCM who may act on behalf of the Contractor when the QCM is absent. Qualifications for the Alternate(s) are the same as for the QCM.

Contractor may designate additional quality control (QC) staff as specified in 01 45 00.00 10 (e.g. Assistant QC Manager or QC specialists).

Provide the names of QC staff to the CO upon award of the Order, as a part of the Quality Control Plan.

The QCM and their staff shall coordinate and review all material and shop drawing submittals, including those of subcontractors, offsite fabricators, and suppliers; prepare quality control (QC) reports; schedule and coordinate testing procedures; and attend all status meetings, site visits, and pre-final/final inspections.

The Contractor's QC staff shall maintain a presence at the site at all times when work is being performed to ensure that the materials and workmanship are in accordance with the project drawings and technical specifications, as well as approved shop drawings and material submittals. The QCM or Alternate shall visit the project site daily.

For additional information regarding the requirements for Contractor’s Quality Control Program, refer to specification section 01 45 00.00 10.

The QCM can serve as the Site Safety and Health Officer.

1.3.2.3 Site Safety and Health Officer (SSHO)

The SSHO is responsible for management of the Contractor Health and Safety Program (for purposes of this SOW, the Health and Safety Program is equivalent to Safety and Occupational Health Program in EM 385-1-1, U.S. Army Corps of Engineers Safety and Health Requirements Manual). The SSHO shall have the minimum qualifications set forth in EM 385-1-1.

The Contractor shall designate an Alternate SSHO who may act on behalf of the Contractor when the SSHO is absent. Qualifications for the Alternate(s) are the same as for the SSHO.

Provide the names of the SSHO and Alternate to the CO upon award of the Order as a part of the Health and Safety Plan.

The SSHO or Alternate shall visit the construction site daily to ensure full compliance with all health and safety requirements.

10 Jun 25 Statement of Work - 4 of 26 WWYK050751

When the SSHO or Alternate is not on site, a Designated Representative (DR) may be used (reference EM 385-1-1). The SSHO, an Alternate, or a DR shall be on the construction site at all times when work is being performed.

1.3.2.4 Project Superintendent

The Superintendent must have a minimum of five (5) years’ experience in construction with at least two (2) of those years as a superintendent on commercial projects similar in size and complexity to the requirements of this Order. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance.

The Contractor may designate an Alternate Superintendent, who may act on behalf of the Contractor when the Superintendent is absent. Qualifications for the Alternate are the same as for the Superintendent, except previous experience as a superintendent is not required; subcontractors will not be used as Alternates.

Provide the names of the Superintendent and the Alternate to the CO upon award of the Order.

The Superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence for the Order. Superintendents shall provide on-site supervision, submit progress reports; schedule and coordinate subcontractors and material suppliers; and attend all status meetings, site visits and pre-final/final inspections.

An individual Superintendent may be assigned to more than one Order; however, the Superintendent shall not be assigned to more than 5 active Orders at Tinker AFB unless approved by the CO. Alternates may only be assigned to a single Order/job site.

The Superintendent shall visit each respective Order/job site daily. Either the Superintendent or the Alternate shall be at the job site at all times when work is being performed. The Superintendent must arrive at the job site within 30 minutes of telephone direction from the CO, Contract Specialist, or Construction Quality Assurance (QA) Inspector.

The Superintendent or Alternate(s) cannot be a member of the QC staff.

The Superintendent or Alternate(s) can be the Designated Representative (reference section SITE SAFETY AND HEALTH OFFICER elsewhere in this document).

1.3.3 Subcontractors

Subcontractor firms performing ‘delegated’ design shall be authorized to offer engineering or architectural services in a US State or Territory. An Oklahoma license will not be required for individuals responsible for signing/sealing documents.

All subcontractor firms shall be licensed in their specialty where required; Contractor will provide a copy of these licenses as part of the QC Plan.

1.4 BADGES

AFMC Form 387, Air Force Material Command Identification Cards (i.e. contractor badges) are required for Contractor personnel to access/work on Tinker AFB. The Contractor must have all personnel badged prior to commencing work.

10 Jun 25 Statement of Work - 5 of 26 WWYK050751

Contractor shall designate an employee to act as Certifying Official for all personnel requiring badges. The designated Certifying Official shall complete Appointment of Security Representative letter and submit to the COR upon award of the Order; a copy of this letter (Attachment 1) is included on the attached CD.

Upon approval, Contractor’s Certifying Official will be responsible for completing an AFMC Form 496, Application for AFMC Identification Card, for all personnel requiring a contractor badge. Badges are issued at Bldg. 6611, Pass and ID.

Badges shall be displayed on the outer clothing, on the front of the body between the neck and waist and must be visible at all times.

1.5 QUALITY CONTROL

It is the Contractor’s responsibility to provide, inspect, and document the level of quality that has been established by the minimum standards of the project drawings, specifications, and this SOW.

The QCM shall direct the execution of the Contractor’s QC Plan.

Quality control shall be executed in accordance with specification section 01 45 00.00 10. The QC program shall include, but is not limited to the following:

1.5.1 Inspection System

The Contractor shall establish an inspection system which monitors the execution of any task completed under this contract. The Contractor must specify the areas to be inspected on a scheduled or unscheduled basis, how often inspections will be accomplished, and titles of the individuals who will perform the inspections.

1.5.2 Deficiency Prevention

The Contractor shall establish a method for identifying, correcting, and preventing future recurrence of quality deficiencies.

1.5.3 Inspection Files

In accordance with specification section 01 45 00.00 10, the Contractor shall maintain records of all required inspections conducted by the QCM and the necessary corrective actions taken. This documentation shall be submitted to the Government weekly with the progress reports (reference section PROGRESS REPORTS elsewhere in this document) throughout the life of the contract.

1.6 HEALTH AND SAFETY

1.6.1 Commander’s Statement of Safety Intent

The safety of everyone on Tinker AFB is our top priority. All individuals must accept personal responsibility for safety and seek opportunities for improving the safety of our work environment.

Everyone working on Tinker AFB is challenged to find, fix (if able) and report all hazards and near-misses. It is our shared duty to take every reasonable step and precaution to prevent accidents and preserve the health/safety of each contractor and government employee.

1.6.2 Occupational Safety and Health Administration (OSHA) Voluntary Protection Program (VPP)

The Contractor is hereby notified that TAFB has achieved or is pursuing VPP Star ratings across multiple sites. Additional information regarding VPP can be found at the following link:

http://www.osha.gov/dcsp/vpp/index.html http://www.osha.gov/dcsp/vpp/index.html

10 Jun 25 Statement of Work - 6 of 26 WWYK050751

The Voluntary Protection Plan applies to all construction and service contracts that have Contractor employees working more than 1000 hours per quarter on Tinker AFB. Refer to specification section 00 71 00, General Safety Requirements for Construction on Tinker AFB for additional requirements related to VPP.

1.6.3 Emergency Evacuation Procedures

Contractor employees shall follow the direction of Government employees in regard to emergency evacuation procedures, i.e. fire, tornado, or bomb threats. It is the responsibility of the Contractor to provide guidance and establish procedures for responding to an emergency for their employees. It is the Contractor’s responsibility to account for their employees following an emergency evacuation. The Contractor personnel shall participate with the Government personnel in all fire and tornado drills at no additional cost to the Government.

1.6.4 Mishap Reporting

The Contractor shall notify the CO and the COR as soon as practical after any mishaps, including recordable accidents, incidents, and near misses, as defined in EM 385-1-1 Appendix Q; and any injuries, illness, or property damage which occur on the installation while performing work under this contract.

Refer to specification section 00 71 00 for additional requirements related to mishap reporting.

1.7 BIOENVIRONMENTAL REGULATIONS

(1) To assist in the evaluation of health hazards & to provide emergency medical treatment, Contractor must have Material Data Sheets (MDS) for hazardous materials reviewed and exchange of HAZCOM information accomplished prior to use. Process hazardous material in accordance with specification section 00 72 00, Environmental Requirements for Construction on Tinker AFB.

(2) Ventilation measurements must be in accordance with current edition of ACGIH Ventilation Manual and 29 CFR 1910.94.

(3) Welding, cutting, or brazing operations must be in accordance with 29 CFR 1910.252. The Contractor shall not operate welders near chlorinated hydrocarbons.

(4) Hazardous noise levels in the vicinity of DoD Active Duty and Civilian personnel must be in accordance with OSHA 29 CFR 1910.95 and AFI 48-127, Occupational Noise and Hearing Conservation Program.

(5) Where confined spaces may be involved, ensure confined space entry permits are acquired prior to entering a confined space. Personal Protective Equipment (PPE) must be in accordance with 29 CFR 1910.146 and AFOSH Std 91-25.

1.8 OUTAGES AND CLOSURES

Request utility outages and/or closures in accordance with TAFB Standard Operating Procedure Planned and Emergency Outages. Outages may be required to be performed outside of normal duty hours. The Contractor shall provide temporary lighting and power that may be required for continued performance of User’s mission during outages.

1.9 EXISTING WORK

In accordance with FAR 52.236-9, Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements, the Contractor shall take necessary precautions to avoid damage to

10 Jun 25 Statement of Work - 7 of 26 WWYK050751 existing items to remain in place, to be reused, or to remain the property of the Government; any damaged items shall be repaired or replaced as directed by the Government.

The Contractor shall remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

The Contractor shall repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the CO. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

2. PROJECT SPECIFIC REQUIREMENTS

2.1 GOVERNMENT OCCUPANCY OF FACILITIES

The facility will not remain occupied throughout construction.

The construction area, a reasonable buffer area, and any approved staging areas will be cleared of all Government materials and personnel prior to the start of construction.

Contractor shall consult with the Government Project Manager/Construction QA Inspector and the using agency to coordinate procedures; means of access; space for storage of materials and equipment; and use of approaches, corridors, and stairways in such a way that accommodates the continued performance of the user’s mission during construction.

2.2 WORKING HOURS

In accordance with specification section 00 70 00, General Requirements for Construction on Tinker Air Force Base, construction shall take place during normal duty hours (0700 – 1600 Monday-Friday); utility outages will be the exception.

The Contractor has the responsibility to manage and maintain the construction schedule; the Contractor may request authorization to work weekends, holidays, and additional shifts as required to accomplish the work per their baseline schedule (reference section CONSTRUCTION SCHEDULE elsewhere in this document).

Work outside normal duty hours to meet schedule will be performed at no additional cost to the Government; this is to include all testing, inspection, and acceptance actions.

2.3 PHASING

There is no Government-required construction phasing for this Order.

2.4 FOD AWARENESS AND PREVENTION TRAINING

In accordance with specification section 00 71 00 all Contractor personnel working on this Order will be required to complete Foreign Object Debris (FOD) awareness and prevention training.

The work to be performed for this Order will not require the Contractor to work in or travel through areas near operational and/or production aircraft or related components.

2.5 AIRFIELD OPERATIONS

The work to be performed under this Order is not located in an airfield operations area.

10 Jun 25 Statement of Work - 8 of 26 WWYK050751

2.6 CONTROLLED/RESTRICTED AREA(S)

Work to be performed under this Order is not located in a controlled/restricted area.

2.7 AFFIRMATIVE PROCUREMENT

The Government has determined that the following products listed in the EPA Comprehensive Procurement Guideline, USDA Biopreferred, Energy Star, or FEMP Low Standby Power programs are included in the scope of this Order:

(1) EPA-designated items - NA

(2) USDA-designated biobased items - NA

(3) Energy Star products

(a) Commercial LED lighting

(b) Light fixtures

(4) FEMP Low Standby Power products - NA

A copy of the Government’s Recovered Materials Determination Form (RMDF) has been provided as an attachment to this SOW (Attachment 3). If at any time during the Order, it is determined that an applicable, designated product cannot be used due to availability, price, or not meeting required performance specification, the Contractor shall complete Page 5 of the RMDF (for each product) to provide justification for not utilizing the designated product(s). forward the completed form to the CO and the COR for review and approval.

2.8 ENVIRONMENTAL MANAGEMENT (EM) SURVEY

An EM survey indicates there are asbestos containing materials (ACM), and lead based paint (LBP) concerns for area(s) where work is to be performed. The following have been identified:

(1) Existing Mechanical Room – Red paint on fire suppression piping.

(2) Existing Office - White pipe covering with insulation above ceiling.

If at any time the Contractor encounters suspect environmental conditions not identified above, they shall notify the CO and the COR.

3. PRECONSTRUCTION SERVICES BY CONTRACTOR

3.1 CORRESPONDENCE

All electronic correspondence related to the awarded Order shall be addressed to the CO, Contract Specialist, Government Project Manager, Construction QA Inspector, the COR, and the respective organizational workflow accounts. Hardcopy correspondence will be addressed to the CO, the Contract Specialist, and the COR.

Contact information for the above will be provided at the Post Award meeting.

All electronic correspondence from the Contractor regarding a specific Order shall follow a standardized subject line naming convention. Subject line for all electronic correspondence shall be as follows:

• WWYK###### Project Title: Subject of E-mail

10 Jun 25 Statement of Work - 9 of 26 WWYK050751

3.2 DOCUMENTATION

All documents shall be submitted in accordance with specification section 01 33 00, Submittal Requirements. The Contractor shall submit all documents electronically via optical disk, e-mail, or a file transfer service such as DoD SAFE.

All documents submitted by the Contractor requiring a signature shall be submitted to the CO and the COR with an electronic digital signature. All documents submitted by the Contractor requiring further action and signature by the Government shall be capable of being digitally signed and saved by the Government representative(s) as required.

3.2.1 Document Format

3.2.1.1 Specifications/Reports/Material Submittals

Specifications, design analyses, reports for calculations, material submittals, warranty information, and similar documents shall be letter sized (8-1/2” x 11”), submitted in Adobe Acrobat (.pdf) format. Black and white documents are preferred but color copies will be accepted if they are necessary to convey intent.

3.2.1.2 Drawings

All drawings produced by the Contractor shall be created utilizing Computer-Aided Design and Drafting (CADD) software. The drawing files shall be in AutoCAD (.dwg) format and adhere to the drawing standards contained in Tri-Services A/E/C CADD Standard Release 6.0.

Drawing size shall be ANSI D (22” x 34”). Drawing scale shall be at least 1"=30' for civil/site drawings and 1/8"=1' for all other plan drawings; text and other non-scale annotation elements shall be sized to produce clear and legible prints at half-size.

Contractor shall use English scales and dimensions.

Drawings submitted by the Contractor shall be .pdf format; in addition, final design drawings and as-built record drawings shall be submitted in .dwg format. Hard copy submittals, when required, shall be printed at half-size (11" x 17").

Reference specification sections 01 33 00; 01 33 16.00 10, Design Data (Design After Award); and 01 78 00, Closeout Submittals, for additional requirements regarding developing and submitting design, shop, and as-built drawings.

3.2.2 File Naming Conventions

All documents submitted by the Contractor shall follow a standardized file naming convention as indicated below. File naming conventions shall be strictly adhered to and may only be modified by the Contracting Officer and/or the COR. File names shall have no spaces.

The following items in the below naming conventions are defined as followed:

• WWYK###### = Project number as defined by Civil Engineering Example: WWYK201234

• YYYYMMDD = Effective date of document or report

• ZZZ = Contractor’s Company Initials

• 001 = Submittal Number or Serial Report Number

10 Jun 25 Statement of Work - 10 of 26 WWYK050751

(1) Proposals:

WWYK######_Proposal#_ZZZ_Document Description Example: WWYK201234_Proposal1_ACS_Cost Proposal

(2) RFIs:

WWYK######_RFI_001

(3) Submittals:

WWYK######_FORM#_001 (Brief Description of Submittal) Example: WWYK201234_AF3000_004 CeramicTile

(4) Daily Reports:

WWYK######_Daily Report_001_YYYYMMDD

(5) Progress Reports:

WWYK######_PR_001_YYYYMMDD

(6) Other Miscellaneous Documents/Reports:

WWYK######_Form Name, Number, Or Description_YYYYMMDD

3.3 CONSTRUCTION SCHEDULE

In accordance with FAR 52.236-15, Schedules for Construction Contracts, the Contractor shall submit a baseline construction schedule to the COR for approval within ten (10) calendar days after the NTP is issued. An approved schedule will be required prior to commencement of work.

Contractor’s schedule must demonstrate a reasonable and realistic sequence of activities which represent all work through the Order performance period. Proposed schedule shall consider the major work elements, as well as submittal reviews, mobilization, material delivery times, anticipated weather delays, and final inspection/closeout.

3.3.1 Schedule Format

The schedule shall be developed in accordance with specification section 01 32 16.00 20, Small Project Construction Progress Schedules, utilizing the Network Analysis Schedule/Critical Path Method format.

The schedule shall generally match the schedule submitted with the Contractor’s accepted proposal, with the following additional information included:

(1) Order start (NTP) and end dates

(2) Additional detail/breakdown of major work elements, as necessary

(3) Cost Loading data entered for all work items. Cost loading must total to 100 percent of the value of the Order.

Any partial progress payments for materials, as approved by the CO, shall be entered separately on the schedule.

The schedule will reserve, as a minimum, the final 10% of the Order cost for final acceptance. No progress payments will be made against this final 10% of the Order until all closeout items have been submitted, all punch list items have been resolved, and final inspection/acceptance has been completed.

10 Jun 25 Statement of Work - 11 of 26 WWYK050751

3.3.2 Schedule Updates

Contractor shall keep the schedule current, reflecting actual start and end dates for work elements, activity progress, and plan for completing the remaining work. The Contractor shall submit the updated schedule at monthly intervals, with the first progress report of the month.

Reference specification section 01 32 16.00 20 for additional information.

In addition, the Contractor shall submit updated baseline schedules when directed by the CO or the COR. Examples of when a new baseline schedule may be required include instances where the period of performance has been revised through modification to the Order; or as part of a ‘get well plan’ for construction that is significantly behind schedule.

3.3.3 Coordination with Government Activities

In developing the schedule, the Contractor shall account for the following milestones and Government review times in addition to construction activities:

DELIVERY SCHEDULE & SUBMITTALS

Item of Work & Deliverables Government Review Time (calendar days)

Remarks

Post-Award Conference/ Pre-Construction Conference/ Notice to Proceed (NTP)

1 day At Tinker AFB

Baseline Construction Schedule and Schedule of Values/Draft Progress Report 14 days Provide within 10 days of

NTP

SD-01 Preconstruction Submittals (except as noted below) 14 days

Provide all preconstruction submittals within 15 days of

NTP

Health and Safety Plan 21 days

Airfield Construction Waiver 60 days Must be provided by 1st business day of month

Notice of Proposed Construction (FAA Form 7460-1) 60 days Must be provided by 1st business day of month

Request for Contractor Staging Area 30 days Must be approved prior to mobilization

Storm Water Pollution Prevention Plan (SWPPP) 21 days

Must be approved prior to submitting Tinker Excavation Permit Request

Chemical/Hazardous Material Request/Authorization 21 days

Spray Painting Plan 21 days

10 Jun 25 Statement of Work - 12 of 26 WWYK050751

DELIVERY SCHEDULE & SUBMITTALS

Item of Work & Deliverables Government Review Time (calendar days)

Remarks

Abatement Submittals (asbestos, lead based paint) 21 days

Material Submittals (SD-03, SD-04, SD-07, SD-08) 14 days Provide within 30 days of

NTP

Outages 21 days

Closures (roadway, parking aisles, etc.) 45 days

Tinker Excavation Permit Request 14 days SWPPP must be approved prior to submittal

Construction Submittals (SD-06, SD-09) 14 days

Final/Closeout Submittals (SD-10, SD-11) 14 days Must be approved prior to final inspection.

Pre-final Inspection 7-day Minimum Notice

Contractor must have completed internal pre-final and resolved all punch list items from this inspection

Final Inspection 7-day Minimum Notice

All final/closeout submittals must be approved.

Contractor must have resolved all punch list items from pre-final inspection

Note: Information provided in this table is provided to assist the Contractor in developing the construction schedule. Review times may vary depending on the complexity of the submittal.

3.4 PROGRESS REPORTING

Progress reports are used for computing payments, and for monitoring the progress against the Contractor’s baseline schedule.

The Contractor shall develop a progress report utilizing the ‘Reports’ feature of the scheduling software. Contractor developed reports shall provide the same information as AF Form 3065, Contract Progress Report. The progress report shall utilize the same work elements and schedule of values/cost loading data developed for the construction schedule.

Contractor shall submit a draft version of the progress report to the CO and the COR for approval within ten (10) calendar days after the NTP is issued (with the Baseline Schedule).

10 Jun 25 Statement of Work - 13 of 26 WWYK050751

After approval, the Contractor shall submit progress reports weekly, or as directed by the CO, throughout the life of the Order. For each progress report, the Contractor shall include the following:

(1) Percentage of work completed for each work element during the reporting period.

(2) Cumulative percentage of work completed for each work element to date.

(3) Cumulative percentage of work completed for all work elements (percent of Order completion).

(4) Scheduled cumulative percentage of work completed for all work elements, based on the baseline Order schedule (scheduled percent of Order completion).

Progress report’s will be reviewed by the Construction QA Inspector and/or the Project Manager, who will in turn provide a recommendation to the COR to approve/disapprove the progress report; approval of the Contractor’s progress report does not constitute acceptance of the work as being 100% in compliance with the Order requirements (i.e. project specifications, drawings, and this SOW).

In the event that the Contractor’s reported progress deviates from the baseline schedule, the CO may elect to hold progress meetings.

3.5 WORKING DOCUMENTS

The Government has provided this SOW and the attached drawings for the Contractor’s use in preparing working documents for use during construction. Working documents shall provide sufficient detail to prevent construction errors or code violations and minimize general coordination errors.

The Contractor shall provide the following working documents:

(1) Fire alarm shop/detail drawings.

(a) Drawings shall be prepared in accordance with specification section [28 31 60, Interior Fire Alarm System, Non-Addressable] [28 31 70, Interior Fire Alarm System, Addressable] [28 31 76, Interior Fire Alarm and Mass Notification System, Addressable].

(b) Drawings shall be signed/sealed by a licensed fire protection engineer; an Oklahoma license will not be required.

(2) Sprinkler System shop drawings

(a) Drawings shall be prepared in accordance with specification section 21 13 13, Wet Pipe Sprinkler System, Fire Protection. Provide supporting calculations.

(b) Drawings shall be signed/sealed by a licensed fire protection engineer; an Oklahoma license will not be required.

Unless otherwise directed by the CO, the Contractor shall not begin construction activities until the required documents have been reviewed and approved by the Government.

3.6 MINIMUM GUIDANCE DOCUMENTS

Contractor generated working documents shall comply with the project documents (SOW, drawings, and specifications) and the most current editions of the publications listed below.

10 Jun 25 Statement of Work - 14 of 26 WWYK050751

The term ‘most current’ is understood to mean, “Most current as of the date the solicitation is issued.”

Codes/standards/regulations referenced by the project and guidance documents are included as a part of this SOW to the extent referenced.

In case of conflict between the project documents, the guidance documents, and the governing codes/standards, the Contractor shall submit a request for information (RFI) to the Government for resolution.

3.6.1 General

(1) UFC 1-200-01, DoD Building Code

(2) UFC 1-200-02, High Performance and Sustainable Building Requirements

(3) UFC 4-010-01, DoD Minimum Antiterrorism Standards for Buildings

(4) Tinker AFB Facility Standard

3.6.2 Architectural

(1) UFC 3-101-01, Architecture

(2) UFC 3-120-10, Interior Design

(3) Architectural Barriers Act (ABA)

(4) Uniform Federal Accessibility Standard (UFAS)

3.6.3 Mechanical

(1) UFC 3-400-02, Design: Engineering Weather Data

(2) UFC 3-401-01, Mechanical Engineering

(3) UFC 3-410-01, Heating, Ventilating, and Air Conditioning Systems

(4) UFC 3-410-02, Direct Digital Control for HVAC and Other Building Control Systems

(5) UFC 3-450-01, Noise and Vibration Control

(6) Tinker AFB Mechanical Standard

3.6.4 Electrical

(1) UFC 3-501-01, Electrical Engineering

(2) UFC 3-520-01, Interior Electrical Systems

(3) UFC 3-530-01, Interior and Exterior Lighting Systems and Controls

(4) Air Force Manual (AFMAN) 32-1065, Grounding and Electrical Systems

(5) Tinker AFB Electrical Standard

3.6.5 Fire Protection

(1) Department of Air Force Instruction (DAFI) 32-2001, Fire and Emergency Services (F&ES) Program

(2) UFC 3-600-01, Fire Protection Engineering for Facilities

(3) UFC 3-601-02, Fire Protection Systems Inspection, Testing, and Maintenance

10 Jun 25 Statement of Work - 15 of 26 WWYK050751

(4) Tinker AFB Fire Protection Standard

3.7 SUBMITTAL REGISTER

Contractor has been provided with an editable version of the Government’s submittal register as a part of the RFP.

Within ten (10) calendar days after issue of the NTP, or as otherwise directed by the CO, the Contractor shall review the submittal register, revise as necessary, and submit for approval.

Contractor is to remove items from the submittal register they do not believe are applicable to the project and add submittals for additional equipment or materials that they believe should be reviewed and approved by the Government.

For any items that the Contractor believes should be removed, provide an explanation as to why that submittal should not be included.

4. CONSTRUCTION SERVICES BY CONTRACTOR

The Contractor shall execute the work as indicated in the attached drawings and specifications.

All construction shall comply with the project documents (SOW, drawings, and specifications) and any approved Contractor generated working documents.

Contractor's work items include, but are not limited to the following:

4.1 ARCHITECTURAL DEMOLITION

(1) Demolish a portion of the interior wall and demolish existing wood door in HM frame to accommodate a new 3070 metal door and frame.

(2) Demolish ACT ceiling and grid system in the existing office.

(3) Demolish floor finish in the existing office to substrate below.

(4) Demolish existing gypsum wall board panels from the existing walls (CMU or metal building liner) within the entire existing office area.

4.2 ARCHITECTURAL CONSTRUCTION

(1) Build new wall at locations required of the restroom wall to be extended to structure or deck above, 6” studs, 25ga, 16” OC with mineral batt insulation. Paint all the walls of the new electric room with epoxy paint.

(2) Install new metal 3070 Door with hardware, closer and frame at interior entry into the new electric room. Door/Frame/Floor transition to be painted.

(3) The structure to be exposed – paint.

(4) Prep exposed concrete floor, clean base concrete and apply densifier as per manufacture’s recommendations at designated electrical room.

(5) Paint the entire electrical room walls.

10 Jun 25 Statement of Work - 16 of 26 WWYK050751

4.3 FIRE PROTECTION DEMOLITION

4.3.1 Fire Suppression

(1) Demolish existing pendent fire sprinklers in space to be used for new electrical room.

4.4 FIRE PROTECTION CONSTRUCTION

4.4.1 Fire Suppression

(1) Provide 2 (two) new upright sprinklers within new electrical room. Modify piping, as needed, for fire sprinkler to provide sprinkler coverage compliant with requirements of UFC 3-600-01.

4.4.2 Fire Alarm

(1) Initiation Devices:

(a) Modify the existing Honeywell Fire-Lite ES-200x fire alarm system in accordance with requirements of UFC 3-600-01 and Tinker AFB Fire Protection Standard to incorporate the following devices:

i. Manual Pull Station: Provide new manual pull station at new door to new electrical room.

(2) Notification Devices:

(a) Modify the existing Honeywell Fire-Lite ES-200x fire alarm system in accordance with requirements of UFC 3-600-01 and Tinker AFB Fire Protection Standard to incorporate the following:

i. Combination audible-visual notification devices: Provide device in the following locations:

• New designated electrical room.

ii. Notification Device Power Panel: Test existing fire alarm panel notification power capacity and load. Verify existing panel has sufficient power capacity and backup power to support new notification devices.

• If existing Fire Alarm System has insufficient capacity to power new devices, provide new notification appliance (NAC) power panel with required additional power. Locate adjacent to fire alarm control unit panel. New NAC power panel shall be listed for use with Honeywell Fire-Lite ES-200x control panel.

• Battery Backup: 48-hr standby, 15-min alarm capacity.

(3) Fire Alarm System Testing: Test entire fire alarm system prior to starts of modifications of the fire alarm system and at the completion of work.

(a) Test Procedures: Develop fire alarm system testing plan. Submit for Government approval at least two weeks prior to performing testing.

(b) Test Report: Document and submit detailed report of testing and test results.

10 Jun 25 Statement of Work - 17 of 26 WWYK050751

4.5 MECHANICAL DEMOLITION

4.5.1 Existing Office

(1) Contractor should perform a pre-TAB of building’s HVAC system to ensure proper function prior to alterations under this project.

(2) Demolish the existing supply diffuser in the existing office space and their associated ductwork back to the main supply ducts.

4.6 MECHANICAL CONSTRUCTION

4.6.1 Electrical Room

(1) Provide and install new wall mounted supply air diffuser to serve the electrical room.

(2) Rebalance HVAC system to accommodate the electrical room.

4.7 ELECTRICAL

4.7.1 GENERAL CONSIDERATIONS

(a) The contractor must verify all the field requirements and working space required per NEC Code 110.26.

(b) New panelboards shall be installed in a neat and workmanship manner per NEC Code and UFC specifications. The new location shall be indicated in the construction documents.

Contractor must refer to NEC 110.26(A)(2) for the installation of the equipment.

4.7.2 ELECTRICAL DEMOLITION

(a) Disconnect and remove feeders from utility transformer.

(b) The contractor shall verify and trace all existing circuits connected to the electrical panelboards and all that are fed through the main gutter.

(c) Disconnect and remove existing circuits (PNL-1, PNL-2, PNL-3). Label them for further reconnection in the new panels.

(d) Disconnect and remove existing circuit from the outdoor disconnect “DISC-7” that feeds

“6006-PNL-1”. Label them for further reconnection in the new panel.

(e) Demolish two light fixtures in the mechanical room and four 2’x4’ recessed troffers in the office.

(f) Demolish conduits, supports, breakers, panelboards, disconnects, CT junction boxes, and any other associated component as needed.

4.7.3 ELECTRICAL CONSTRUCTION

(a) Contractor will provide and install new service entrance from the utility transformer.

i. The new trench required will remove a section of the parking lot asphalt as needed and once completed, replace it with concrete to match the existing level or grade.

ii. Install 3 sets (4) THWN #350 MCM, (1) THWN #2 AWG GND, 3” Conduit. Approx. 80ft.

iii. Install (2) new 3/4" copper ground rods, the GEC with 2/0 AWG and one ground bar in the electrical room.

(b) New MDP panelboard ‘6002-PNL-1’, mounted in the new electrical room.

i. Provide new 800A MCB panelboard, 208Y/120V, 3-Phase, service entrance rated.

(a) Enclosure Nema 1, copper bars, and additional grounding bar.

ii. Provide a Source Protective Device SPD accordingly.

iii. All bolt-on breakers and additional spares will be required. 20% spare/space minimum.

10 Jun 25 Statement of Work - 18 of 26 WWYK050751

iv. Contractor must provide new high-quality labels for all new equipment. New circuit directories updated on the panelboards involved.

v. Reconnect the existing circuits for the mechanical equipment (HVAC units, boiler, air compressor).

vi. Reconnect the existing circuit that feeds the panelboard “6006-PNL-1”, located in the building 6006.

vii. New grounding and bonding system required per Code. Provine a new copper grounding bar.

(c) New branch panelboard “6002-PNL-2’, mounted in the new electrical room.

i. Provide new 225A MCB panelboard, 208Y/120V, 3-Phase.

ii. Enclosure Nema 1, copper bars, and additional grounding bar.

iii. Install 1 set of (4) THHN #4/0 AWG, (1) THHN #4 AWG GND, 2-1/2 conduit. Approx.20ft.

iv. All bolt-on breakers and additional spares will be required. 20% spare/space minimum.

v. Reconnect the existing circuits (lighting, fire alarm, receptacles).

vi. Contractor must provide new high-quality labels for all new equipment. New circuit directories updated on the panelboards involved.

vii. Connect to the grounding and bonding system required per Code.

(d) New feeder for branch panelboard “6002-PNL-8” located in the Tool Crib.

i. Provide and install one set of (4) THHN #4/0 AWG, (1) THHN #4 AWG-GND, 2-1/2” EMT

Conduit. Approx. 120ft.

(e) New wireway gutter, mounted in the existing mechanical room.

i. Provide and install new 6ft long x 10” x 10” gutter Wiegmann or equal, Nema 3R.

ii. Install new (4) GFCI receptacles 20A/1P, two in the new electrical room, and two in the mechanical room.

(f) New LED Lighting

i. Provide and install (4) new LED strip lights (two in the electrical room and two in the mechanical room).

ii. Provided with integral battery backup for emergency egress.

(g) Testing

i. The equipment installed must be tested to verify the proper functionality.

ii. New Arc-Flash labels will be required for all panelboards.

4.8 ORDER OF PRECEDENCE

In the event of a conflict or inconsistency between any of the provisions of this Order, precedence shall be applied in the following order:

(1) Any portions of the accepted proposal which both conform to and exceed the requirements of the solicitation.

(2) The provisions of the solicitation, including:

(a) The Solicitation, Offer and Award

(b) Specifications (if provided)

(c) Drawings

(d) Order SOW

10 Jun 25 Statement of Work - 19 of 26 WWYK050751

(3) All other provisions of the accepted proposal

(4) Any contractor generated working documents, including, but not limited to: plans, engineering studies and analyses, shop drawings, and equipment installation drawings.

4.9 RECORD DRAWINGS

4.9.1 Working As-Built Drawings ('Redline' Set)

Working as-built drawings shall be maintained at the job site, and clearly indicate authorized field changes, updates based on existing conditions, and corrections to the drawings. Reference specification section 01 78 00 for additional information related to markups to be included in working as-built drawings.

Within five (5) days of substantial completion (i.e. completion of Contractor’s punch-out inspection) and prior to pre-final inspection, the Contractor shall submit working as-built drawings for Government use during the inspection. At the conclusion of the pre-final inspection, the Government and Contractor will identify any additional changes or corrections required for final approval.

4.9.2 Record Drawings

Within ten (10) days after the pre-final inspection and approval of the working as-built drawings, the Contractor shall incorporate the redlines into the CAD files and submit this final set as the Record Drawings. These drawings shall be labeled 'RECORD DRAWING AS-BUILTS' and submitted for Government approval. Reference specification section 01 78 00 for additional information.

Shop drawings shall be in accordance with the 'additional record drawings' requirements of specification section 01 78 00.

4.10 OPERATIONS & MAINTENANCE (O&M) MANUALS AND TRAINING

The Contractor shall provide O&M manuals for Government approval a minimum of 30 calendar days prior to the final inspection. Reference specification sections 01 78 00 and 01 78 23, Operation and Maintenance Data, for additional information.

O&M training is not required for this Order.

4.11 DD FORM 1354 REQUIREMENT

A DD Form 1354, Transfer and Acceptance of Military Real Property is not required for this Order.

5. GOVERNMENT FURNISHED DRAWINGS, SPECIFICATIONS, & REFERENCES

5.1 DRAWINGS

Refer to Appendix A, DRAWING INDEX. Drawing files, in PDF and AutoCAD format, are included on the attached CD.

5.2 SPECIFICATIONS

Refer to Appendix B, SPECIFICATIONS for a list of specification sections developed by the Government and applicable to the work. Specification files, in PDF format, are included on the attached CD.

10 Jun 25 Statement of Work - 20 of 26 WWYK050751

5.3 BASE STANDARDS / REFERENCE DOCUMENTS / FORMS

Refer to Appendix C, TINKER AFB FACILITY STANDARDS AND REFERENCE DOCUMENTS. Tinker AFB facility standards and reference files, in PDF format, are included on the attached CD.

5.4 FACILITY AS-BUILT INFORMATION

Relevant as-built drawings for B6002 are included on the attached CD. If necessary, additional as-built drawings are available from 72 ABW/CE - Engineering Support, located in B400.

6. GOVERNMENT FURNISHED PROPERTY

There is no Government Furnished Property included in this Order.

7. STAGING/STORAGE AREA(S)

Contractor shall limit storage of materials, equipment, and incidentals to the immediate construction site while work is being performed. If the Contractor requires additional storage area(s) other than the construction site, a request shall be submitted in accordance with specification section 01 50 00, Contractor Facilities.

It is recommended that the Contractor arrange for storage of equipment between its delivery and its installation, as availability of space and security during non-working hours cannot be guaranteed.

8. 'OR EQUAL' CLAUSE

Where reference is made in the specification or on the drawings to specific manufacturers and/or model numbers of equipment or materials, the information is provided to indicate design intent and to establish the minimum quality standards, physical attributes, and performance characteristics which are required for the referenced item. The use of specific names and/or model number is not intended to limit selection of other manufacturers; equipment or materials meeting these criteria may be submitted to the COR for consideration and shall be clearly identified, in writing, as a substitution.

The burden of proving equality for proposed substitutions shall be the responsibility of the Contractor and submittals for said substitutions shall include detailed manufacturer’s specifications, dimensioned drawings, performance data and any other information necessary to clearly indicate that the proposed item meets or exceeds the quality standards, physical characteristics, and performance criteria established by the SOW, specifications, and drawings.

Submittals, which do not provide proof of equality, will be rejected.

Approval of a substitute by the COR shall not result in a change to Order price or schedule; such changes can only be approved by the CO.

9. ATTACHMENTS

The following project specific attachments referenced within this SOW are included on the attached CD.

• Attachment 1 – Appointment of Security Representative Letter

• Attachment 2 – Recovered Materials Determination Form

10 Jun 25 Statement of Work - 21 of 26 WWYK050751

• Attachment 3 – Asbestos and LBP Report

• Attachment 4 – UL-2079 – 2 Hour Fire Rated Wall Head Detail & UL-419 – 2 Hour Wall

Assembly

• Attachment 5 – Equipment List

End of SOW

10 Jun 25 Statement of Work - 22 of 26 WWYK050751

APPENDIX A

Drawing Index

General

G-101 General Notes & Vicinity Map

Architecture

AD-101…