04 Atch4 TO Procedure Flow Chart.pdf

PDF 96 KB Posted

Attached to
Simplified Acquisition of Base Engineer Requirements (SABER))
Solicitation number
FA520523R0002
Issued by

About this file

This flow chart outlines the two-step task order procedure for the Simplified Acquisition of Base Engineer Requirements (SABER) contract. Step one involves a joint site visit, submission of a price proposal for survey and work item reports, proposal evaluation, potential negotiation, and task order issuance. Step two begins with completion of a task order request for proposal, submission of a task order proposal, evaluation and potential negotiation, and concludes with task order issuance and construction execution. The flow chart provides an overview of the process that the Department of the Air Force Pacific Air Forces will follow to issue task orders under SABER contract number FA520524D0001 in response to solicitation FA520523R0002.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1-step Task Order

Step 1

Identification of Requirement Identification of Requirement

Joint Site Visit Joint Site Visit

▼ Submission of Price Proposal

▼ for Survey and Work Item Report

▼ Proposal Evaluation

▼ Negotiation (if required)

▼ TO issue

Perform Survey Perform Survey Step 2

Task Order (TO) RFP Completion of Task Order (TO) RFP

▼ Survey and Work Item Report ▼

Submission of TO Proposal Submission of TO Proposal

Proposal Evaluation Proposal Evaluation

Negotiation (if required) Negotiation (if required)

TO Issue TO Issue

Construction Execution Construction Execution

Attachment 4 to Contract No. FA520524D0001

31-Jan-23

Reference: RFP No. FA520523R0002, Other Contract Requirements para H004, Attachment 1 to RFP

2-step Task Order

TASK ORDER PROCEDURE FLOW CHART

SABER CONTRACT