02811 - Golf Course Irrigation.pdf
PDF 362 KB Posted
- Attached to
- Stone Creek Golf Course Irrigation Project
- Solicitation number
- S-C01010-00016773
- Issued by
- Oregon
About this file
This is a Scope of Work specification document for the Clackamus County Stone Creek Golf Club Irrigation Renovation Project (Section 02811), detailing comprehensive requirements for a golf course irrigation system renovation. The project encompasses the design, installation, and commissioning of a complete irrigation system including high-density polyethylene (HDPE) pipe and fittings, control valves, sprinkler heads, a computerized central control system (Rain Bird Cirrus PRO), and associated electrical infrastructure. The scope includes mainline and lateral pipe installation using fusion techniques, swing joint assemblies, remote control valves with integrated control modules, landscape rotors and spray heads, and a sophisticated central control system capable of managing three independent 18-hole golf courses plus miscellaneous areas. The specification requires all piping to be 100% fused with zero allowable leakage, fusion technicians to be AquaFusion qualified, and comprehensive documentation including manual datalogging of all fusion joints with technician identification, date, and time of completion. The contractor must provide GPS surveying assistance for sprinkler head location, with staking conducted in up to six site visits by Baer Design Group LLC, and ensure sprinkler installation within 6 inches of GPS coordinates.
The specification mandates extensive quality assurance requirements including PE4710 material certification with a 25-year HDPE system warranty, one-year fusion provider warranty, and one-year installation warranty covering all workmanship and materials. The contractor is responsible for all excavation, trenching, backfilling, electrical work installation, and utility location verification, with minimum pipe cover requirements ranging from 18 to 36 inches depending on application and wire type. The project includes delivery of extra replacement parts (quick coupler valves, rotors, remote control valves, fittings), new socket fusion equipment, system winterization and spring activation services, comprehensive record drawings, operations and maintenance manuals, and personnel instruction upon completion. The contractor must maintain the existing irrigation system's operational status during construction, coordinate with golf course management to limit simultaneous hole closures, and restore all turf disturbance with sod and seed. A one-year warranty period includes contractor-performed winterization and spring system reactivation, with emergency repairs authorized to the owner at the contractor's standard service rates.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| BID 2026-24 Stone Creek Golf Irrigation.pdf | ||
| 25014 - Bid Set.pdf | ||
| 02211 - Rough Grading.pdf | ||
| 02110 - Site Clearing.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Clackamus County Stone Creek Golf Club
Irrigation Renovation Project 02811/1 10/25
SECTION 02811
GOLF COURSE IRRIGATION
PART 1 – GENERAL
1.1 SUMMARY
A. Section Includes
1. Pipe and fittings, valves, sprinkler heads, accessories, and connections to water source.
2. Control system.
B. Related Sections: The following Sections contain requirements that relate to this Section:
1. Division 2 Section 02110 “Site Clearing” for site preparation.
2. Division 2 Section 02211 “Rough Grading” for course improvements.
1.2 SYSTEM PERFORMANCE REQUIREMENTS
A. Location of Sprinklers and Devices: Design location is intended for maximum irrigation efficiency. All
Sprinklers will be located by Irrigation Consultant
B. Minimum Water Coverage:
1. Not less than:Turf Areas: 100 percent.
C. All flow velocities, within the entire irrigation system, shall not exceed 5 feet per second.
1.3 SUBMITTALS
A. Product data including pressure rating, rated capacity, settings, and electrical data of selected models for the following:
1. Valves, including general-duty, underground, automatic control, quick-coupler types, isolation, air release and drain type and valve boxes.
2. Sprinklers.
3. Pipe and Fittings.
4. Wiring and Splice Kits.
5. Irrigation system record drawings.
6. Control system.
7. IC Modules.
B. Wiring diagrams for electrical controllers, valves, and devices.
C. Maintenance data for inclusion in "Operation and Maintenance Manual" for the following:
1. Seasonal activities of start-up, shut-down and winterization, including blow-out operation of sprinkler system with compressed air.
2. Automatic control valves.
3. Sprinklers.
4. Controllers.
5. Irrigation system record drawings.
6. Central control system.
D. HDPE pipe, valves and fittings:
1. The following information shall be submitted by pipe and fitting suppliers:
a. Name of the pipe manufacturer and a list of the piping and quantities to be provided by manufacturer. A Certificate of Origin is required for all pipe not manufactured in the United
States.
b. Name(s) of fitting manufacturer(s) and lists of fittings and quantities to be provided by manufacturer. A Certificate of Origin is required for all fittings not manufactured in the United
States.
Irrigation Renovation Project 02811/2 10/25
c. Pipe and fitting product data indicating conformance with this specification, applicable standards, and warranty provisions, including written documentation regarding any intended variance from this specification and applicable standards.
d. At the time of shipment, the supplier shall provide certified documentation of pipe and fitting conformance with this specification and applicable pipe and fitting standards specified herein.
2. The following information shall be submitted by Fusion Providers.
a. Documentation that each Fusion Technician has met requirements for joining proficiency for each type of fusion joint performed by the Fusion Technician under this specification.
b. Documentation of conformance with this specification and applicable standards, including written documentation regarding any intended variance from this specification and applicable standards.
This will include fusion joint warranty information and recommended project specific fusion parameters.
c. The following MANUAL AS-RECORDED DATA is required from the Contractor and/or Fusion
Provider:
3. Manual Datalogging for each fusion joint performed on the project, including joints that were rejected. Submittals of the Fusion Technician’s joint reports are required as requested by the Owner or Engineer. Specific requirements of the Fusion Technician’s joint manual datalogging shall include:
a. Fusion technician’s name or initials
b. Date and exact time at completion of fusion process
c. Once the technician has completed this process, they are confirming that they followed all safety and fusion procedures for the fusion machine used.
1.4 QUALITY ASSURANCE
A. Installer Qualifications: Engage an experienced company, foreman, superintendent and laborers with a minimum of five years experience and who have successfully installed irrigation systems similar in material, design, and extent to that indicated for Project that have resulted in construction with a record of successful in-service performance.
B. Listing/Approval Stamp, Label, or Other Marking: On equipment, specialties, and accessories made to specified standards.
C. Listing and Labeling: Equipment, specialties, and accessories that are listed and labeled.
1. The Terms "Listed" and "Labeled": As defined in "National Electrical Code," Article 100.
2. Listing and Labeling Agency Qualifications: A "Nationally Recognized Testing Laboratory"
(NRTL) as defined in OSHA Regulation 1910.7.
D. HDPE pipe, valves and fittings:
1. REFERENCES:
a. This section contains references to the following documents. They are a part of this section to the extent referenced in this specification. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of a conflict between the requirements of this section and those of the referenced documents, the requirements of this specification shall prevail.
b. Unless otherwise specified, references to documents shall mean the latest published edition of the referenced document in effect at the time of construction.
Reference Title
AWWA C651 Standard for Disinfecting Water Mains
ANSI/AWWA C901 Polyethylene (PE) Pressure Pipe and Tubing, ½ In. (13 mm) Through 3 In. (76 mm) for
Water Service
Irrigation Renovation Project 02811/3 10/25
Reference Title
ANSI/AWWA C906 Polyethylene (PE) Pressure Pipe and Fittings, 4 In. (100 mm) Through 63 In. (1,600 mm), for Water Distribution and Transmission
ASTM C923 Standard Specification for Resilient Connectors Between Reinforced Concrete Manhole
Structures, Pipes and Laterals
AWWA M55 Manual of Water Supply Practices, PE Pipe–Design and Installation
ASTM D1603 Standard Test Method for Carbon Black in Olefin Plastics
ASTM D2321 Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and
Other Gravity-Flow Applications
ASTM D2774 Standard Practice for Underground Installation of Thermoplastic Pressure Piping
ASTM D3035 Standard Specification for Polyethylene (PE) Plastic Pipe (DR-PR) Based on Controlled
Outside Diameter
ASTM D3261 Standard Specification for Butt Heat Fusion Polyethylene (PE) Plastic Fittings for
Polyethylene (PE) Plastic Pipe and Tubing
ASTM D3350 Standard Specification for Polyethylene Plastics Pipe and Fittings Materials
ASTM D4218 Standard Test method for Determination of Carbon Black Content in Polyethylene
Compounds by the Muffle-Furnace Technique
ASTM F585 Standard Practice for Insertion of Flexible Polyethylene Pipe Into Existing Sewers
ASTM F714 Standard Specification for Polyethylene (PE) Plastic Pipe (SDR-PR) Based on Outside
Diameter
ASTM F1055 Standard Specification for Electrofusion Type Polyethylene Fittings for Outside Diameter
Controlled Polyethylene Pipe and Tubing
ASTM F1290 Standard Practice for Electrofusion Joining Polyolefin Pipe and Fittings
ASTM F1417 Standard Test Method for Installation Acceptance of Plastic Gravity Sewer Lines Using
Low-Pressure Air
ASTM F1962 Standard Guide for Use of Maxi-Horizontal Directional Drilling for Placement of
Polyethylene Pipe or Conduit Under Obstacles, Including River Crossings
ASTM F2164 Standard Practice for Field Leak Testing of Polyethylene (PE) Pressure Piping Systems
Using Hydrostatic Pressure
ASTM F2206 Standard Specification for Fabricated Fittings of Butt-Fused Polyethylene (PE) Plastic
Pipe, Fittings, Sheet Stock, Plate Stock, or Block Stock
ASTM F2620 Standard Practice for Heat Fusion Joining of Polyethylene Pipe and Fittings
ASTM F2786 Standard Practice for Field Leak Testing of Polyethylene (PE) Pressure Piping Systems
Using Gaseous Media Under Pressure (Pneumatic Leak Testing)
NSF/ANSI 61 Drinking Water System Components–Health Effects
PPI TR-4 PPI Listing of Hydrostatic Design Basis (HDB), Strength Design Basis (SDB), Pressure
Design Basis (PDB) and Minimum Required Strength Ratings for Thermoplastic Piping
Materials for Pipe
PPI TR-46 Guidelines for Use of Mini-Horizontal Directional Drilling for Placement of High-
Density Polyethylene Pipe
E. Product Options: Irrigation system piping, specialties, and accessories are based on specific types, manufacturers, and models indicated. Components with equal performance characteristics produced by other manufacturers may be considered, provided deviations in dimensions, operation, and other characteristics do not change design concept or intended performance as judged by the Irrigation Consultant. The burden of proof of product equality is on the Contractor. Any substitutions must be approved by the Irrigation
Consultant in writing prior to installation.
1.4 HDPE MANUFACTRUER REQUIREMENTS
A. High density polyethylene (HDPE) pipe and fittings shall be manufactured in accordance with the following standards
1. ASTM D3035 – ½ in through 24-in pipe
2. ASTM F714 – 3-in through 54-in pipe
3. AWWA C901 – 1/2 In. (13mm) through 3 In. (76 mm) pipe and tubing
4. AWWA C906 – 4 In. (100 mm) through 63 In (1,600 mm) pipe and fabricated fittings
Irrigation Renovation Project 02811/4 10/25
5. ASTM D3261 – butt fusion fittings, saddles and flange adapters
6. ASTM F1055 – electrofusion couplings and saddles.
7. ASTM F2206 – fabricated fittings
1.5 HDPE FUSION TECHNICIAN REQUIREMENTS
A. Each Fusion Technician shall be separately qualified to make each type of fusion joint. Fusion joint types are butt fusion, saddle fusion, electrofusion, and socket fusion. Only AquaFUSION® qualified technicians shall make fuses during initial construction and during the contractor warranty period. Qualification to make one type of fusion joint shall not qualify a Fusion Technician to make a different type of fusion joint.
B. Each Fusion Technician making butt fusion joints shall be qualified to make butt fusion joints in accordance with ASTM F2620. Qualification shall have occurred not more than 12 months before performing fusion joining on site in accordance with this specification. Qualification shall be a documented demonstration of proficiency by making joints in accordance with ASTM F2620 that are proved to be satisfactory by destructive testing (bend-back test) in accordance with ASTM F2620. Prior to any fused HDPE pipe being installed in the trench, the contractor shall perform a bend back test (in accordance with ASTM F 2620).
These tests shall be random. The fusion technician will not know in advance which of his/her fusions will be tested. The completed test specimen shall be manually data logged (each will be marked clearly with name of technician, date, passed or failed written with a silver, metallic Sharpie marker). These completed test specimens will remain onsite for inspection of the irrigation consultant till the project is completed. Tests will be performed as follows, one test per diameter, per week, per technician.
C. Each Fusion Technician making saddle fusion joints shall be qualified to make saddle fusion joints in accordance with ASTM F2620. Qualification shall have occurred not more than 12 months before performing on-site fusion joining in accordance with this specification. Qualification shall be a documented demonstration of proficiency by making joints in accordance with ASTM F2620 that are proved to be satisfactory by destructive testing in accordance with ASTM F2620.
D. Each Fusion Technician making electrofusion fitting joints shall be qualified to make electrofusion fitting joints in accordance with ASTM F1290 and the electrofusion fitting manufacturer’s recommended procedure.
Qualification shall have occurred not more than 12 months before performing on-site fusion joining in accordance with this specification. Qualification shall be a documented demonstration of proficiency by making joints in accordance with ASTM F1290 and the electrofusion fitting manufacturer’s recommended procedure that are proved to be satisfactory by destructive testing in accordance with ASTM F1290 and the electrofusion fitting manufacturer’s recommended procedure.
E. Each Fusion Technician making socket fusion joints shall be qualified to make socket fusion joints in accordance with ASTM F2620. Qualification shall have occurred not more than 12 months before performing on-site fusion joining in accordance with this specification. Qualification shall be a documented demonstration of proficiency by making joints in accordance with ASTM F2620 that are proved to be satisfactory by destructive testing in accordance with ASTM F2620.
1.6 APPROVED HDPE SUPPLIERS
A. Pipe and fitting suppliers shall be approved by the Project Consultant.
B. The following pipe manufacturers are approved:
a. AquaFuse®
b. ISCO
c. High Country Fusion
C. The following fitting manufacturers are approved:
a. AquaFuse®
b. ISCO
c. High Country Fusion
D. The following on-site qualification training are approved:
Irrigation Renovation Project 02811/5 10/25
a. AquaFuse®
b. Ewing/ISCO
E. The following mainline and isolation valves are approved:
a. ControlFlo™
b. AquaFuse®
c. Leemco
1.6 1.7 PROJECT CONDITIONS
A. Perform site survey, research public utility records, and verify existing utility locations. Verify that irrigation system piping may be installed in compliance with original design and referenced standards.
1.7 1.8 SEQUENCING AND SCHEDULING
A. Maintain uninterrupted water service to all facilities during normal working hours. Arrange for temporary water shutoff with Owner.
with
B. Maintain Uninterrupted existing irrigation system during construction. Arrange for temporary water shutoff with Owner. Provide alternate water source for irrigation if water is to be shut off for more than (2) days.
C. Provide proposed construction schedule to Ownership prior to construction. Coordinate hole closure with
Course staff minimum one week in advance. Maximum number of holes closed simultaneously shall be limited to one hole unless approved by Ownership in advance.
1.8 1.9 TURN-OVER MATERIALS AND EQUIPMENT
A. Deliver extra materials to Owner. Furnish extra materials matching products installed as described below.
Package them with protective covering for storage and label clearly describing contents.
1. Quick Coupler Valves, Hose Swivels and Operating Keys: Furnish (3) extra parts.
2. VIH Rotors: Furnish (6) extra full heads and (6) extra part circle heads, each model.
3. Remote Control Valves: Furnish (2) extra valve assemblies, for each assembly type. To exclude lateral isolation valve.
4. Landscape Sprinklers: Furnish (6) extra full circle rotors and (6) extra adjustable heads, each model.
5. Landscape Spray/Rotary Sprinklers: Furnish (6) extra each model spray body and nozzle.
6. Lateral Isolation Valves: Furnish (2) extra each model lateral isolation valve.
7. 2-Inch Socket Fusion Fittings: Furnish (5) extra coupler, tee and 90 el, each model.
8. 2-Inch Mechanical Fittings: Furnish (2) Philmac IPS-OD-Large Bore poly x poly couplers, tees and couplers, each model.
B. Deliver 2-inch socket fusion equipment, new in box.
1. Socket & Sidewall Heater Assembly: 2-inch McElroy 252601, or approved equal.
2. Heater Adapter Set: 2-inch McElroy MCSW02669, or approved equal.
3. Heater Sling: 2-inch McElroy SW08601, or approved equal.
4. Depth Guage & Chamfer Tool: 2-inch McElroy SW08701, or approved equal.
5. Clamp: 2-inch McElroy SW02710, or approved equal.
1.10 SUBSTITUTIONS
A. Substitutions to the specified equipment will be permitted with the express written approval of the Irrigation
Consultant. Substitutions will be approved only when the substituted item is equivalent or better in quality and performance than the item originally specified. The final determination for "equivalents" rests with the
Irrigation Consultant. Their decision shall be final and binding.
Irrigation Renovation Project 02811/6 10/25
1.11 1.11 INSTALLATION WARRANTY
A. Warranty system against defects of installation and material for a period of 1 year after final completion of the irrigation system. Guarantee shall also cover repair or damage to any part of the premises resulting from leaks or other defects in material, equipment and workmanship to the satisfaction of the Irrigation Consultant.
Repairs, if required, shall be done promptly upon notification by the Owner, and, at no cost to the Owner.
B. As part of the warranty, the Contractor shall be responsible for deactivating and winterizing the system prior to the onset of the freezing season and for reactivating the system at the onset of the spring growing season;
each event must be accomplished once during the warranty period. In the event the system is completed in a season when it will not be in use, the Contractor shall winterize the system upon completion of testing (and approval by the Irrigation Consultant) and reactivate the system in the spring. The Contractor shall submit a letter to the Irrigation Consultant certifying that the system was winterized and drained and indicate the date such action was accomplished. The Contractor shall be responsible for any damage resulting from failure to comply. Contractor shall instruct and demonstrate winterization and startup techniques for Owner.
1.9 1.12 RAIN BIRD BRANDED WARRANTY
A. All Valve-In-Head rotors and swing joint shall carry a 5-year parts replacement warranty.
B. All other Rain Bird branded components shall carry a minimum 1-year parts replacement warranty.
1.13 HDPE PIPE, FITTINGS AND VALVES
A. Pipe and fitting suppliers shall provide a twenty five-year HDPE system warranty covering defects in product material and workmanship. A successful pressure test or pressure leak test prior to the expiration of the warranty period shall not relieve the supplier of warranty responsibility for the full warranty term.
B. Fusion providers shall provide a one-year warranty from the date of installation acceptance covering defects in fusion joining workmanship that shall provide for remaking defective butt fusion, saddle fusion, electrofusion, or socket fusion joints. A successful pressure test or pressure leak test prior to the expiration of the warranty period shall not relieve the installer of warranty responsibility for the full warranty term.
1.14 ALLIED MATERIAL WARRANTY
A. All components not covered under the Rain Bird or HDPE pipe, fitting and valve warranty shall carry a minimum 1-year parts replacement warranty.
PART 2 MATERIALS
2.1 SWING JOINTS:
1. Swing Joints shall have AquaFuse® thread inlet and modified stub ACME threads with elastomeric O-ring seals at each rotating joint and meets ASTM Standard F2768 (Standard Specification for Modified Stub
ACME Thread Joint with Elastomeric Seal in plastic piping components). Each rotating joint shall be sealed with an elastomeric O-ring, installed pre-compressed in a sealing groove free of parting lines to prevent leakage as produced by CMF Global.
B. Rain Bird Swing Joints:
1. Rain Bird 952-IC Series Rotors: Rain Bird SJ1215033TS
2. Rain Bird 702-IC/752-IC Series Rotors: Rain Bird SJ12125R3TS
3. 1” Landscape Rotors: AquaFuse AF1C2-418
4. ¾” Landscape Rotors: AquaFuse AF1AF-418
5. ½” Spray Heads: Hunter SJ7512
6. Quick Couple Valve: AquaSaddle 1-1/2" Female Acme 90° with Lasco G1MS-212
C. Or approved Equal
Irrigation Renovation Project 02811/7 10/25
2.2 VIH ROTORS:
A. Full-circle sprinklers shall be:
1. Rain Bird A702-IC-70-32
2. Rain Bird A752-IC-70-26
3. Rain Bird A952-IC-70-48
B. Part-circle sprinklers shall be:
1. Rain Bird A752-IC-70-36
2. Rain Bird A752-IC-70-26
3. Rain Bird A952-IC-70-48
2.3 LANDSCAPE ROTORS:
A. Rain Bird 8005-SS Series, nozzle per plan.
2.4 ROTARY SPRAY HEADS: N/A
2.5 2” REMOTE CONTROL VALVES:
A. Rain Bird 200-PESB-PRS-ICM with ICM adapter.
2.6 2” REMOTE CONTROL VALVE & FILTER:
B. Rain Bird 200-PESB-PRS-ICM with ICM adapter.
C. Netafim LVCZ150HP-NV filter kit.
2.7 CENTRAL CONTROL SYSTEM:
A. The computerized central control system shall be the Rain Bird Cirrus PRO as hereinafter specified. It shall be capable of controlling three (3) independent, 18-hole golf courses, plus one “other” area, each consisting of greens, tees, fairways, approaches, perimeters, roughs and miscellaneous areas. The central shall include the Rain Bird Cirrus PRO
Computer Assembly, a field hardware (Integrated Control) interface, an uninterruptible power supply rated at 980
Watts or higher, a power circuit surge arrestor and a grounding network grid with surge arrestors, all as hereinafter specified.
B. All Cirrus PRO central control systems shall be “Hybrid” compatible. Cirrus PRO Hybrid computer systems shall have the flexibility to control up to three (3) field interfaces in any combination of interface type. Each of the interfaces will require a separate serial port for each device. To enable the functionality of these items, a Cirrus PRO system Hybrid software module and additional interfaces (MIM, MIM-LINK or MIM-LINK900, ICI or LDI as needed) shall be supplied as specified on the drawings.
C. Cirrus PRO software shall include the following modules; Automatic Weather™, Smart Weather™, Rain Bird
Messenger™, Hybrid Software, Smart Sensors™, The Freedom System™, Map Utilities, Map Layers and Multiple
Weather Stations. An additional module purchase is required for Smart Pump™.
D. The Cirrus PRO system shall provide for the selection of three (3) different flow measurement units - U.S. gallons per minute (GPM), cubic meters per hour (M3/H) or liters per second (L/S). It shall also provide for the selection of any one of 22 different languages for display.
E. Cirrus PRO Software Capacity —The Cirrus PRO software shall operate in the Microsoft® Windows® 10 32 or 64-bit environment and shall be capable of controlling any one (1) or up to eight (8) of the four (4) types of Rain Bird field control systems: hard-wired satellite controllers; LINK or LINK900 radio-operated satellite controllers, decoder field devices, or IC System.
Irrigation Renovation Project 02811/8 10/25
F. The Cirrus PRO software, when used with an IC System, shall have the capacity to control a maximum of 24,000 single ICMs and activate up to 24,000 rotors or valves using eight (8) IC Interfaces and a Hybrid software module.
G. Continuous “real-time” communication - Between the central computer, interfaces and field satellite controllers, decoders or IC modules, the system shall provide continuous operation and response at all times. Continuous field
“feedback” status information shall be registered in the computer software and also at the satellite interface when satellite systems are used. Cirrus PRO shall be a program/schedule-based system providing maximum flexibility of programming and giving the operator absolute and full control of the entire system. The Cirrus PRO system shall be capable of unlimited programs residing in the system at one time. Each program shall be further defined by a number of smaller schedules. A maximum of 50 programs and up to 50 schedules per program may be operated simultaneously. All programming shall be maintained in the computer memory and on the hard drive, from which they shall be executed. Programming shall NOT be “downloaded” to the field satellites. It shall NOT be possible to change or reprogram from the field thus assuring the operator full control at all times.
H. A “time window” may be defined for each individual program, confining its operation to this specific time period.
Individual programs shall be capable of being designated for up to six (6) start times. Individual schedules shall be capable of being designated for up to 12 start times within the specified time window for their program. It shall be possible to designate the sequence of operation of areas and the sequence of operation of stations in these areas, within a given schedule.
I. Dynamic Flo-Manager® feature shall be included with the software and automatically distribute and limit flow within the system, to eliminate hydraulic “overload” while maintaining maximum system operating efficiency, without the requirement of entering flow zone or branch piping data. The system shall also be capable of entering complete flow management database information for up to six (6) independent pump stations; up to 250 piping network branches and up to 999 flow zones for each pump station. This shall result in the highest efficiency of pump station operation, shortest watering cycle time and conservation of energy. During operation, individual flow graphs shall be automatically generated for each of the three (3) courses, with individual station activity information being presented in colorful charts. Flow graphs shall be automatically stored in the software for future access and reference.
J. The Cirrus PRO Smart Weather™ optional software module, when specified, shall monitor and respond to climatic conditions as they occur by tracking evapotranspiration (ET) rates and other sensory inputs from up to five (5) on-site weather stations. Smart Weather shall also log weather conditions for future reference. Smart Weather shall provide automatic response from user- defined thresholds on up to five (5) WS-PRO2 Weather Stations. The Smart Weather responses shall be provided to the computer for programmed response and shall be capable of sending an email or text message to the user for alarm conditions with the optional Rain Bird MessengerTM module.
K. Pump Profiling™ - Cirrus PRO shall provide user-definable limits for irrigation system capacity to manage system flow and decrease power consumption during peak electrical periods. If so desired, the user shall define irrigation system capacity for each hour of the day to optimize system efficiency according to electrical demand. The Cirrus
PRO software shall automatically increase or decrease system capacity according to these user-defined limits.
L. Programming Flexibility - The Cirrus PRO system shall also provide for programs to be set to adhere to manual water budgeting; at the system level, at the individual program level and/or at the individual schedule level. A watersaver feature shall provide water budgeting capabilities from zero (0) to 300% in one (1) % increments.
Automatic rain shutdown shall be possible with the integration of a rain sensor.
M. An innovative, guided initialization and “start-up” programming method in Cirrus PRO shall result in a customized
QuickStart™ program that gets the system “up” and “operating” in the shortest possible time. Built-in rotor database tables shall provide for easy specification of station sprinklers for custom irrigation scheduling. Precipitation rates for each station shall be automatically calculated with the selection of sprinkler model, pattern and spacing.
N. A unique QuickIRR™ method of programming shall provide for a quick and easy method to automatically build programs to meet all irrigation challenges and allow programming by specific areas and designating sequence of operation of these areas. This feature is enhanced in Cirrus PRO by providing the ability to program multiple courses.
Select the course, hole, area, sequence and run time and Cirrus PRO will calculate the most efficient irrigation sequencing.
Irrigation Renovation Project 02811/9 10/25
O. A “Dry Run” feature shall provide for simulation of a program prior to operation, enabling the user to make the necessary adjustments before actually operating it in the field. A printout of the “dry run” results shall be possible, as well as being displayed on the monitor.
P. The Cirrus PRO Cycle + Soak™ feature works with Flo-Manager to achieve maximum efficiency and conservation. It helps control water application on slopes and in areas with poor drainage. Cycle + Soak shall maintain pump station demand while preventing over application in challenging areas of the course. The Cycle + Soak feature will ensure the maximum cycle time defined by the user is never exceeded and will not change with changes in station runtime.
Q. Graphical display of the golf course can be achieved using GPS, CAD, aerial photograph or the Scorecard function.
Each hole can be defined to indicate the areas to be irrigated such as greens, tees, fairways, approaches, perimeters, roughs and miscellaneous areas. The system shall provide for multi-station programming and operation of individual stations. A station data table shall give complete database information for each individual station.
R. The FREEDOM SystemTM - The Cirrus PRO system shall be capable of direct manual access of any station at any time. Full system remote control via handheld radio or remote telephone commands shall be possible with the integration of The FREEDOM System™ and handheld software module.
S. Logs and Troubleshooting - The Cirrus PRO system shall provide for an individual course, daily and seasonal logs for record keeping and easy compliance with regulatory requirements regarding water usage. A unique “Cost
Estimator” feature shall provide projections of water and power costs for specific irrigation cycles, which can be used in establishing budget requirements.
T. When used with an Integrated Control System, the Cirrus PRO software shall contain detailed diagnostics software that measures a series of parameters related to system operation. These parameters shall include ICI and ICM operation. The software diagnostics shall be capable of polling individual station ICM’s on each wire path and display the number of passed and failed ICMs on each wire path. The diagnostics shall also be capable of measuring the total mA draw on each wire path. Individual ICM’s can be interrogated to confirm communication with the central control software as well as measure the voltage at each ICM for troubleshooting purposes. The diagnostics shall be capable of communicating with each ICM by “fast connect” or through the “long address” setting based on the diagnostic function.
U. Hardware—Computer - Furnish and install at the central location a Rain Bird Cirrus PRO computer assembly consisting of the following minimum specifications:
1. DELLTM OptiplexTM 7040 Mini Tower
2. Intel® Core™ i5-6500 Processor
3. 8GB, DDR4 RAM
4. 1TB Solid State Drive
5. US English (QWERY) Wireless Keyboard and Mouse8X DVD+/-RW Optical Disk Drive
6. Intel® Integrated Graphics
7. 24" Widescreen HD LED-Lit Flat-Panel Monitor
8. 58” Hisense 58U6HF 4K LED Smart TV with 10’ HDMI cable and wall mount.
9. 16 GB USB Flash Drive
10. 6 Serial (RS232/COM) Ports
11. 1 Parallel Port
12. 10 External USB 2.0 Ports (6 USB 3.0, 4 USB 2.0)
V. Preinstalled software shall consist of:
1. Rain Bird Cirrus PRO software program
2. Microsoft Windows® 10 Professional 64-bit
W. Voltage Stabilizer (120VAC)—At the central location, furnish and install a combination voltage stabilizer and uninterruptible power source. Unit shall have a minimum rated output of 1440VA and 980 Watts. It shall be suitable for 50/60 Hz operation with input power of 120VAC. The unit shall operate in the AC mode from 82VAC input up to
144VAC input, regulating the output voltage within proper limits. Transfer to battery mode shall occur at any input voltage less than 75VAC or greater than 154VAC. In battery mode, output shall be a pure Sine wave form. Stepped or approximated Sine wave forms shall not be acceptable. Output voltage regulation shall be less than 5% at full load.
Frequency regulation shall be +/- 3 Hz on battery. Surge energy rating shall be a minimum of 459 Joules. Battery
Irrigation Renovation Project 02811/10 10/25 back-up shall have a minimum time of approximately 14 minutes minimum at half-load capacity. The unit shall have
Quick Status Indicators and an LCD menu-driven display screen showing power status, control settings, configuration, test and diagnostics, and logs. USB and Smart-Slot computer interface ports shall enable communication with the central control computer. The tower housing shall have a minimum of eight (8) “battery and surge” NEMA 5-15R electrical outlets. The voltage stabilizer shall be the APC Smart-UPS 1500 or higher.
2.8 ISOLATION VALVES:
A. Ductile Iron Mainline Valves, Sizes 4”-12”:
1. Ductile Iron Resilient Seated Gate Valves 250 PSI Polyethylene Ends.
2. Valves shall conform to the latest revision of AWWA Standard C509/C515 covering resilient wedge
(RS) gate valves for water supply service.
3. AWWA C509/C515 valves shall have an iron body, bonnet, and O-ring plate. The wedge shall be fully encapsulated with rubber.
4. The sealing rubber shall be permanently bonded to the wedge casting per ASTM D429.
5. Valves shall be supplied with O-ring seals at all pressure retaining joints. No flat gaskets shall be allowed.
6. The valve shall be non-rising stem (NRS), opened by turning left or right, and provided with either a 2” square operating nut or a hand wheel. The operating nut and hand wheel shall be marked with the word
“Open” and an arrow to indicate the direction to open.
7. Stems shall be cast copper alloy or stainless steel with an integral collar in full compliance with AWWA.
All stems shall operate with copper alloy stem nuts independent of the wedge.
8. All stems shall have two O-rings located above the thrust collar and one O-ring below. The upper stem
O-rings shall be replaceable with valve fully opened and subjected to full pressure. The stems on 2”-12” or 63mm-315mm sizes shall also have a low torque thrust bearing located both above and below the stem collar to reduce friction during operation.
9. Waterway shall be smooth, unobstructed, and free of all pockets, cavities, and depressions in the seat area.
10. The body, bonnet, and O-ring plate shall be coated, both on the interior and the exterior, with fusion-bonded epoxy. Epoxy shall be applied in accordance with AWWA C550 and be NSF 61 certified.
11. Each valve shall have the maker’s name, the pressure rating, and the year in which it was manufactured cast into the body. Prior to shipment from the factory, each valve shall be hydrostatically pressure tested to the requirements of AWWA C509/C515.
12. AquaFuse® ControlFlo™ Valves shall have all component parts cast and assembled in the USA and shall be manufactured by the Clow Valve Company.
B. Ductile Iron Mainline Valves, Sizes 14”-24”:
1. Ductile Iron Resilient Seated Gate Valves 250 PSI Flanged End.
2. Valves shall conform to the latest revision of AWWA Standard C509/C515 covering resilient wedge
(RS) gate valves for water supply service.
3. AWWA C509/C515 valves shall have an iron body, bonnet, and O-ring plate. The wedge shall be fully encapsulated with rubber.
4. The sealing rubber shall be permanently bonded to the wedge casting per ASTM D429.
5. Valves shall be supplied with O-ring seals at all pressure retaining joints. No flat gaskets shall be allowed.
6. The valve shall be non-rising stem (NRS), opened by turning left or right, and provided with either a 2” square operating nut or a hand wheel. The operating nut and hand wheel shall be marked with the word
“Open” and an arrow to indicate the direction to open.
7. Stems shall be cast copper alloy or stainless steel with an integral collar in full compliance with AWWA.
All stems shall operate with copper alloy stem nuts independent of the wedge.
8. All stems shall have two O-rings located above the thrust collar and one O-ring below. The upper stem
O-rings shall be replaceable with valve fully opened and subjected to full pressure. The stems on 2”-12” or 63mm-315mm sizes shall also have a low torque thrust bearing located both above and below the stem collar to reduce friction during operation.
9. Waterway shall be smooth, unobstructed, and free of all pockets, cavities, and depressions in the seat area.
Irrigation Renovation Project 02811/11 10/25
10. The body, bonnet, and O-ring plate shall be coated, both on the interior and the exterior, with fusion-bonded epoxy. Epoxy shall be applied in accordance with AWWA C550 and be NSF 61 certified.
11. Each valve shall have the maker’s name, the pressure rating, and the year in which it was manufactured cast into the body. Prior to shipment from the factory, each valve shall be hydrostatically pressure tested to the requirements of AWWA C509/C515.
12. Leemco LMV Series, or approved equal.
C. Poly Lateral Isolation Valves:
1. AquaFuse ControlFlow 360 Ball Valve AFBV0200Y-MFNO-360.
2. ISCO MTD Polyflow Full port Ball Valve TRI10901.
3. All valves shall be ball valve type constructed from High Density Polyethylene PE 4710 Full Port and manufactured in accordance with AWWA C901, AWWA C906, ASTM D2513, ASME B16.40, CFR 49
Part 192 and CSA B137.4.
4. Manufacturing facility must be ISO 9001 certified.
5. All valves must be serialized for complete material and process traceability.
6. Valve should maintain a bubble tight seal throughout the entire pressure and temperature range and provide blow-out proof stem and Seal design.
7. All valves must be PE4710 material both body and ends.
8. Operation must be 360 degree open to close.
9. Valves shall be temperature rated -20°F – 140°F Valve body must provide resistance to mechanical and thermal loads as supplied by AquaFuse® ControlFlo™.
2.9 VALVE OPERATING KEYS:
A. Rain Bird 55-K-1.
B. The contractor shall provide three keys of each type required to operate all types of manual gate valves used.
2.10 VALVE BOXES:
a. Automatic Electric Valves:
1. Rain Bird VB-JMB-H. Extensions as required.
2. Carson 1324 Spec Grade Valve Box with Green “T” Lid and Bolt. Extensions as required.
3. Or approved Equal.
B. Lateral Isolation Valves:
1. Rain Bird VB-10RND-L. Extensions as required.
2. Carson 910 Spec Grade Valve Box with Green “T” Lid. Extensions as required.
3. Or approved Equal.
C. Mainline Isolation Valves:
1. Rain Bird VB-10RND-L. Extensions as required.
2. Carson 910 Spec Grade Valve Box with Tan “T” Lid. Extensions as required.
3. Or Approved Equal.
D. Air Relief Valve:
1. Christy B24 Concrete Valve Box with B24D Lid and B24x12 extensions as required.
2. Or approved Equal.
E. Splices:
1. Rain Bird VB-10RND-BLK. 10” CL 200 PVC Riser
2. Carson 910 Spec Grade Valve Box with Black “T” Lid. 10” CL 200 PVC Riser.
3. Or approved Equal.
2.11 FLUSH VALVE AND AIR-RELIEF VALVE:
A. Crispin IC10A Air/Vac Combo Valve assembly as detailed.
Irrigation Renovation Project 02811/12 10/25
2.12 WIRE CONNECTORS:
a. All high voltage splice kits shall be Direct Bury Multi-Mold Resin 85 Series as manufactured by 3-M.
b. Wire 24-volt splice kits shall be Direct Bury Splice Kits (DBY) as manufactured by 3-M.
c. All 24 volt and 120-volt wire splices are to be placed in Carson 910 valve boxes with black lid.
2.13 WIRING:
A. 120 and 220 volt and wiring shall be type UF, direct burial copper wire sized as shown on the irrigation plan.
120 and 220 volt wiring shall be three conductor Tray cable and shall consist of one black power wire, one white common wire, and one green ground wire which is to be one wire size smaller that the power wire which the ground is servicing. Grounding shall be provided per manufacturer’s recommendation.
B. 24V Power wire shall be red 14-2 PE UF/UL direct bury as manufactured by Regency or approved equal.
2.14 WEATHER STATION:
d. Rain Bird Spectrum Watchdog 3552HU as manufactured by Campbell Scientific with solar/battery power and cellular communication. Weather station shall be equipped with Solar Radiation Sensor, Air Temperature and
Relative Humidity Probe Tipping Bucket Rain Gage, and either the Wind Set or Sonic Wind Sensor.
3.1 PIPE AND FITTINGS
F. PE4710 100% Fused System:
1. PE4710 100% Fused System Component material (compound) for all fittings (general and service), valves (mainline and lateral), and pipe shall be high density bimodal High-Performance polyethylene copolymer designed for extrusion of potable water, reclaimed water, industrial, and mining pipe.“PE4710 Fused System Component material (compound) shall have a PENT value at 2.4 MPa and 80 °C of >10,000 hours per ASTM F 1473 and It is listed by the Plastics Pipe Institute (PPI TR-4, as both PE 4710 and PE 100) and is certified to ANSI/NSF Standard 14, ANSI/NSF Standard 61, CSA
B137.1 and CSA B137.4 and have Oxidative Resistance Classification of CC3”.
2. All Fused PE4710 material (compound) shall conform to material requirements specified in pipe standard: ASTM D3035 or ASTM F714 or AWWA C901 or AWWA C906, fitting standard: AWWA
C906 or ASTM D3261 or ASTM F2206 or ASTM F1055 as applicable for the pipe or fitting. PE4710 material (compound) shall meet the requirements of ASTM D3350 and shall meet or exceed Cell
Classification 445574C and 445576C and is Certified NSF Standard 14 and/or Standard 61 for Potable
Water Pipe and Fittings and have an Oxidative Resistance Classification of CC3.
3. PE4710 material (compound) shall have a hydrostatic design basis (HDB) rating at 140°F (60°C) of not less than 1000 psi that shall be listed in PPI TR-4 in the name of the pipe manufacturer.
4. PE4710 pipe and fitting material (compound) in PE4710 pipe and fittings shall contain color and ultraviolet (UV) stabilizer meeting the requirements of Code C or E per ASTM D3350. Code C material shall contain 2 to 3 percent carbon black to provide indefinite protection against UV degradation when material from the pipe is tested in accordance with ASTM D1603 or ASTM D4218.
Code E material used for coextruded OD color stripes or a coextruded ID color layer shall contain sufficient UV stabilizer to protect the pipe against UV degradation for at least 24 months of unprotected outdoor exposure. Coextruded color PE compound material shall be PE4710 pipe material compound, varying only by color and UV stabilizer.
5. Clean rework materials derived from pipe production by the same manufacturer are acceptable as part of a blend with new material for the production of new pipe provided that the rework material is the same PE4710 material designation as the new material (compound) to which it is added. Finished products containing rework material shall meet the requirements this specification.
G. PE4710 pipe and butt fusion fittings shall have plain ends for butt fusion.
Irrigation Renovation Project 02811/13 10/25
H. PE4710 pipe:
1. Nominal straight lengths of 3 inch and larger pipe shall be 40 ft. or 50 ft.
2. Nominal coil lengths of 4-inch and smaller pipe shall be 500 ft. Longer or shorter coils such as 800 ft for 4-inch pipe, 1000 ft for 3-inch pipe, or 2000 ft for 2 inch or smaller pipe shall be acceptable. Pipe shall be black. Coextruded lavender or purple stripes or a coextruded lavender or purple layer shall be an acceptable option.
3. Pipe shall be permanently marked using heated indent printing in accordance with ASTM D3035 or
ASTM F714 as applicable for the pipe size including:
a. Nominal size and sizing system, e.g., IPS or DIOD
b. DR or SDR
c. Standard Designation, ASTM D3035 or ASTM F714 material designation, and pressure rating or pressure class for water at 73°F.
a) Marking the Standard Designation on the pipe shall serve as the manufacturer’s certification that the pipe has been manufactured, sampled and tested and has been found to comply with the requirements of the standard.
b) The ASTM D3035 or ASTM F714 pipe pressure rating for water at 73°F shall be
“PE4710 PR161” where 161 = pressure rating in psi
4. Extrusion production-record code
5. Manufacturer’s Trademark or trade name “AquaFuse”.
I. PE4710 fittings:
1. PE4710 butt fusion, saddle fusion, electrofusion and fabricated fittings shall be manufactured from
PE4710 material (compound) in accordance with this specification. All fittings molded and fabricated shall be manufactured in the U.S.A. and must be NSF-61 Approved and manufactured at a
Factory Mutual (FM) approved facility that has been inspected and approved by FMRC, and are audited frequently to ensure compliance and promote continuing improvement.
2. PE4710 fittings shall comply with ASTM D3261 for molded butt fusion and saddle fusion fittings, flange adapters and MJ adapters, or shall comply with ASTM F2206 or AWWA C906 for fabricated butt fusion fittings, or shall comply with ASTM F1055 for electrofusion fittings.
3. PE4710 fittings shall comply with the marking requirements of ASTM D3261 for molded butt and saddle fusion fittings, flange adapters and MJ adapters or shall comply with the marking requirements of ASTM F2206 or AWWA C906 for fabricated butt fusion fittings, or shall comply with the marking requirements of ASTM F1055 for electrofusion fittings.
4. PE4710 fittings shall have pressure class ratings not less than the pressure class rating of the pipe to which they are joined.
3.2 FUSION JOINTS
A. Unless otherwise specified, PE4710 pipe and fittings shall be assembled in the field with butt fusion, saddle fusion or electrofusion joints. Electrofusion couplings can only be installed if pipe is prepared with a professional rotary scraper. ASTM F2620 and the pipe manufacturer’s recommended procedure shall be observed for butt fusion and saddle fusion joints. ASTM F1290 and the electrofusion fitting manufacturer’s recommended joining procedure shall be observed for electrofusion joints.
B. Field butt fusion, saddle fusion and electrofusion joints shall be made by Fusion Technicians that are qualified in accordance with this specification to make the specific fusion joint type.
C. Field fusion joints shall be recorded and documented in accordance with this specification.
3.3 MECHANICAL CONNECTIONS AND FITTINGS FOR PRESSURE APPLICATIONS
A. Connections shall be defined in conjunction with the linking of project piping, as well as the tie-ins to other piping systems.
B. MECHANICAL AND COMPRESSION FITTINGS
1. Acceptable mechanical and compression fittings for use with PE4710 pipe and fittings shall be mechanical fittings that are qualified by the mechanical fitting manufacturer for use with HDPE pipe and fittings.
2. Mechanical and compression fittings for use with HDPE pipe shall provide restraint against longitudinal separation that is inherent to the design of the joint. Mechanical joints that do not provide restraint against pull-
Irrigation Renovation Project 02811/14 10/25 out or push-off are prohibited. An insert stiffener must be used to ensure long term restraint and water tight seal.
Compression Fittings are to be used for REPAIRS ONLY.
3. Mechanical connections to non-HDPE devices and appurtenances shall be by bolted flange adapter or MJ adapter.
Flange adapter and MJ adapter connections shall be assembled, installed and tightened in accordance with flange adapter or MJ adapter manufacturer’s instructions. Flange bolt tightening shall be in accordance with PPI TN-38.
B. GASKETED, PUSH-ON FITTINGS
1. Gasket push-on fittings shall be fitted with insert stiffener and an external mechanical restraint that span across the joint and are assembled in accordance with restraint manufacturer’s instructions.
a. Thrust blocking does not provide acceptable restraint and is prohibited.
b. Where plain-end PE4710 pipe is assembled with push-on fittings, the PE4710 pipe end shall be fitted with electrofusion restraints so that external mechanical restraint may be secured to the PE4710 pipe.
2. Where PE4710 pipe is connected to gasket mechanical joint fittings or appurtenances, the connection shall be made by butt fusing a PE4710 MJ Adapter to the PE4710 pipe and connecting the PE4710 MJ Adapter to the mechanical joint fitting or appurtenance.
C. SLEEVE-TYPE COUPLINGS
1. Sleeve-type mechanical couplings shall be manufactured for use with HDPE pipe, and shall be restrained and shall be fitted with insert stiffener as indicated on the drawings and in these specifications. Unrestrained sleeve-type couplings are prohibited.
D. EXPANSION AND FLEXIBLE COUPLINGS
1. Expansion-type mechanical couplings are prohibited.
E. CONNECTION HARDWARE AND COATING
1. Bolts shall be carbon steel grade 5 or 8 with a minimum 105,000 PSI tensile strength conforming to SAE J429.
Bolts shall be standard ANSI B1.1, Class 2A coarse threads. Nuts shall conform to ASTM A563 and be standard
ANSI B1.1, Class 2A coarse threads. All bolt heads and nuts shall be hexagonal. Identification on the head of the bolt shall be three slash marks.
2. Bolts and nuts shall be finished with the TRIPAC 2000 coating system to significantly reduce the effects of corrosion. A multi-step process shall be utilized to chemically clean, abrasive blast and prime with zinc/nickel phosphate primer prior to application of the Xylan fluoropolymer. Wear resistance (K-Factor) shall be in the range of 6 to 8 (excellent) and minimal effects should be seen after a 2000-hour Salt Spray test conforming to ASTM B-
117.
4.1 CONSTRUCTION:
4.01 DELIVERY AND OFF-LOADING
A. All piping shall be bundled or packaged for transportation by commercial carrier to the site.
B. Before off-loading, pipe shall be inspected for damage. Any pipe damaged in shipment shall be assessed and either accepted or rejected as directed by the Owner or Engineer, and the pipe supplier shall be notified of rejected pipe within 7 days of delivery at the site. Rejected pipe shall be quarantined for disposition. Each pipe shipment shall be checked for quantity and proper pipe size, color and type.
C. Pipe shall be off-loaded and handled in accordance with the pipe manufacturer’s instructions and AWWA M55.
D. The Contractor shall be responsible for correct procedures in loading, unloading, stacking, transporting, and handling all materials to be used in the system. The Contractor shall avoid rough handling which could affect the useful life of equipment. Pipe shall be handled in accordance with the manufacturer's recommendations on loading, unloading, and storage.
Irrigation Renovation Project 02811/15 10/25
4.02 HANDLING AND STORAGE
A. Pipe lengths should be placed and stored on level ground. Pipe should be stored at the job site in the unit packaging provided by the manufacturer. The interior of the pipe, as well as all end surfaces, should be kept free from dirt and foreign matter.
B. Pipe shall be handled and supported with the use of woven fiber pipe slings or approved equal. Care shall be exercised when handling the pipe to not cut, gouge, scratch or otherwise abrade the piping in any way.
This is the start of the file's text. The full file is on GovTribe.