DEMOLISH THE MINI MART AND NSA CHAPEL AT NAVAL SUPPORT ACTIVITY ANNAPOLIS, MD
Solicitation number
SR23567618
Issued by

About this file

This document is a specification for the demolition of the existing Mini Mart and NSA Chapel buildings, utilities, parking lot, and concrete pad at the Naval Support Activity - Annapolis in Annapolis, MD. The work includes demolishing the buildings and utilities back to the main lines, protecting any trees on site, and re-sodding the area to return it to a green site. The contractor must coordinate utility disconnections with the government, manage construction waste, and complete incidental related work. The specification includes requirements for project management, scheduling, quality control, safety, and project closeout. This is a federal construction solicitation from the Department of the Navy Naval Facilities Engineering Command for the demolition work.

View the file

Other files

Show all 15

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WORK ORDER NO.1802998

SPECIFICATION

At the

PREPARED BY:

USNA

181 Wainwright Drive Annapolis, MD 21402

SPECIFICATION PREPARED

BY:

Architectural:

Civil:John Jones, PE Structural:

Mechanical:

Electrical:

Fire Protection:

Environmental:

Cost Estimating:John Jones, PE

Submitted By: Signature Date:

Design Manager Signature Date:

PDC Branch Head Signature Date:

Demolition Projects for Mini Mart and NSA Chapel SR23567618

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00.00 23 08/23 SUMMARY OF WORK

01 14 00.00 23 08/23 WORK RESTRICTIONS

01 20 00.00 23 08/23 PRICE AND PAYMENT PROCEDURES

01 30 00.00 23 08/23 ADMINISTRATIVE REQUIREMENTS

01 31 23.13 20 08/23 ELECTRONIC CONSTRUCTION AND FACILITY

SUPPORT CONTRACT MANAGEMENT SYSTEM

(eCMS)

01 32 17.00 23 08/23 NETWORK ANALYSIS SCHEDULES (NAS)

01 33 00.00 23 08/23 SUBMITTAL PROCEDURES

01 35 26 11/20, CHG 4: 08/23 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 23 08/23 QUALITY CONTROL

01 50 00.00 23 08/23 TEMPORARY CONSTRUCTION FACILITIES AND

CONTROLS

01 57 19.00 23 12/22 TEMPORARY ENVIRONMENTAL CONTROLS

01 74 19.00 23 08/23 CONSTRUCTION WASTE MANAGEMENT AND

DISPOSAL

01 78 00.00 23 08/23 CLOSEOUT SUBMITTALS

01 78 30.00 23 08/23 CADD DATA FOR GIS DELIVERABLES

DI VI SI ON 02 - EXI STI NG CONDI TI ONS

02 41 00 05/10, CHG 2: 02/19 DEMOLITION

02 82 00 11/18, CHG 1: 11/19 ASBESTOS REMEDIATION

02 83 00 11/18 LEAD REMEDIATION

DI VI SI ON 03 - CONCRETE

03 30 00 02/19 CAST-IN-PLACE CONCRETE

DI VI SI ON 26 - ELECTRI CAL

26 05 00.00 40 11/20 COMMON WORK RESULTS FOR ELECTRICAL

DI VI SI ON 31 - EARTHWORK

31 00 00 08/08, CHG 2: 02/21 EARTHWORK

31 23 00.00 20 02/11 EXCAVATION AND FILL

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS

32 92 19 08/17, CHG 1: 08/21 SEEDING

32 92 23 04/06 SODDING

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION 01 11 00.00 23 23

SUMMARY OF WORK

08/23

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00.00 23 SUBMITTAL

PROCEDURES:

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

The work includes the demolition of the existing buildings, utilities, parking lot, and concrete pad, returning the site back to a green site.

Utility branches shall be demolished but not limited to electric, potable water, and sanitary from the building back to the main line and capped.

Any trees currently around the building will need to be protected in place. Once all building elements have been removed the site will be re-sod. and incidental related work.

1.2.2 Location

The work is located at the Naval Support Activity - Annapolis, Annapolis, MD, approximately as indicated. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with

SECTION 01 11 00.00 23 Page 1

Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground or paved surface where existing underground utilities are discovered. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.5.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00.00 23 Page 2

SECTION 01 14 00.00 23 23

WORK RESTRICTIONS

08/23

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00.00 23 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contact Personnel

Personnel List; G

Vehicle List; G

Statement of Acknowledgement Form SF 1413; G

1.2 CONTRACTOR ACCESS AND USE OF PREMISES

1.2.1 Activity Regulations

Ensure that Contractor personnel employed on the Activity become familiar with and obey Activity regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Ensure all Contractor equipment, include delivery vehicles, are clearly identified with their company name.

1.2.1.1 Subcontractors and Personnel Contacts

Provide a list of contact personnel of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.2.1.2 Employee List

The Contractor must provide to the Contracting officer, in writing, the names of two designated representatives authorized to request personnel and vehicle passes for employees and subcontractor's employees prior to commencement of work under this contract.

a. Cont r act or shal l mai nt ai n a Per sonnel Li st consi st i ng of a compl et e l i s t of per sonnel on t he pr oj ect s i t e, associ at ed vehi c l es, and cor r el at ed t o subcont r act or when appl i cabl e f or al l empl oyees and per sonnal on t he j ob s i t e under t he cogni zance of t he cont r act or . The l i s t shal l i ncl ude appr opr i at e appr oval and expi r at i on dat e i nf or mat i on f or each i ndi v i dual . The Vehi c l e Li st shal l be i nt egr at ed

SECTION 01 14 00.00 23 Page 1 wi t h t he per sonnel l i s t . Bot h shal l be sear chabl e and f i l t er abl e f or speci f i c i ndi v i dual s, vehi c l es and f i r ms.

b. St at ement of Acknowl edgement For m SF 1413 f or al l Subcont r act or s f or al l t i er s shal l be compl et ed, submi t t ed, and appr oved pr i or t o access r equest s f or t hat subcont r act or bei ng submi t t ed.

1.2.1.3 Installation Access

Obtain access to Navy installations through participation in the Defense Biometrics Identification System (DBIDS). Requirements for Contractor employee registration, and transition for employees currently under Navy Commercial Access Control System (NCACS), are available at https://www.cnic.navy.mil/om/dbids.html . No fees are associated with obtaining a DBIDS credential.

Cont r act or s ar e advi sed t hat badge pr ocessi ng can t ake up t o 14 cal endar days t o compl et e and ar e r equi r ed t o pl an accor di ngl y. Any del ays or i mpact s t o wor k associ at ed di r ect l y or i ndi r ect l y wi t h a f ai l ur e t o adequat el y manage and pl an f or access pr ocedur es i s ent i r el y t he r esponsi bi l i t y of t he cont r act or and wi l l not be consi der ed f or any r equest s f or t i me ext ensi ons or compensat i on.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for access under local approved security procedures. Contractors shall research and comply with these procedures as they are subject to change based on multiple variable conditions. Any delays or impacts to work associated directly or indirectly with access via these procedures is entirely the responsibility of the contractor and will not be considered for any requests for time extensions or compensation.

Participation in the DBIDS is not mandatory, and Contractor personnel may apply for One-Day Passes at the Base Visitor Control Office to access an installation.

1.2.1.3.1 Registration for DBIDS

Registration for DBIDS is available at https://www.cnic.navy.mil/om/dbids.html . Procedure includes:

a. Present a letter or official award document (i.e. DD Form 1155 or SF 1442) from the Contracting Officer, that provides the purpose for access, to the base Visitor Control Center representative.

b. Present valid identification, such as a passport or Real ID Act-compliant state driver's license.

c. Provide completed SECNAV FORM 5512/1 to the base Visitor Control Center representative to obtain a background check. This form is available for download at https://www.cnic.navy.mil/om/dbids.html .

d. Upon successful completion of the background check, the Government will complete the DBIDS enrollment process, which includes Contractor employee photo, fingerprints, base restriction and several other assessments.

e. Upon successful completion of the enrollment process, the Contractor employee will be issued a DBIDS credential, and will be allowed to proceed to worksite.

SECTION 01 14 00.00 23 Page 2

1.2.1.3.2 DBIDS Eligibility Requirements

Throughout the length of the contract, the Contractor employee must continue to meet background screen standards. Periodic background screenings are conducted to verify continued DBIDS participation and installation access privileges. DBIDS access privileges will be immediately suspended or revoked if at any time a Contractor employee becomes ineligible.

An adjudication process may be initiated when a background screen failure results in disqualification from participation in the DBIDS, and Contractor employee does not agree with the reason for disqualification.

The Government is the final authority.

1.2.1.3.3 DBIDS Notification Requirements

a. Immediately report instances of lost or stolen badges to the Contracting Officer.

b. Immediately collect DBIDS credentials and notify the Contracting Officer in writing under the following circumstances:

(1) An employee has departed the company without having properly returned or surrendered their DBIDS credentials.

(2) There is a reasonable basis to conclude that an employee, or former employee, might pose a risk, compromise, or threat to the safety or security of the Installation or anyone therein.

1.2.1.3.4 One-Day Passes

Personnel applying for One-Day passes at the Base Visitor Control Office are subject to daily mandatory vehicle inspection, and will have limited access to the installation. The Government is not responsible for any cost or lost time associated with obtaining daily passes or added vehicle inspections incurred by non-participants in the DBIDS.

1.2.1.4 No Smoking Policy

Smoking is prohibited within and outside of all buildings on installation, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

1.2.2 Working Hours

Regular working hours will consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 4 p.m., Monday through Friday , , excluding Government holidays.

1.2.3 Work Outside Regular Hours

Work outside regular working hours requires Contracting Officer approval.

Make application 15 calendar days prior to such work to allow arrangements to be made by the Government for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, SECTION 01 14 00.00 23 Page 3 contract number and project title. Based on the justification provided, the Contracting Officer may approve work outside regular hours. During periods of darkness, the different parts of the work must be lighted in a manner approved by the Contracting Officer. Make utility cutovers after normal working hours or on Saturdays, Sundays, and Government holidays unless directed otherwise.

1.2.4 Exclusionary Period

No work may be performed during the period of Commissioning Week (last full week in May) and Induction Day (last week in June) , inclusive, without prior written approval of the Contracting Officer. Additionally, the Contractor shall account for an additional 10 working days where work will not be permitted due to special events, ceremonies, etc. This period has not been considered in computing the time allowed for the performance of this contract.

1.2.5 Utility Cutovers and Interruptions

a. Make utility cutovers and interruptions after normal working hours or on Saturdays, Sundays, and Government holidays. Conform to procedures required in paragraph WORK OUTSIDE REGULAR HOURS.

b. Ensure that new utility lines are complete, except for the connection, before interrupting existing service.

c. Interruption to water, sanitary sewer, storm sewer, telephone service, and electric service are considered utility cutovers pursuant to the paragraph WORK OUTSIDE REGULAR HOURS. Such interruptions will be further limited by operational timing. The contractor shall adjust their operations to accomodate Government opertaional considerations.

d. Operation of Station Utilities: The Contractor must not operate nor disturb the setting of control devices in the station utilities system, including water, sewer, electrical, and steam services. The Government will operate the control devices as required for normal conduct of the work. The Contractor must notify the Contracting Officer giving reasonable advance notice when such operation is required.

e. Connection to Existing Sanitary Sewer Line: Provide positive verification that the existing line conveys sanitary sewer; verify line is not incorrectly connected to a storm drain.

f. Notification prior to Excavation: Notify the Contracting Officer at least 20 days prior to starting excavation work. Contact Miss Utility Company 48 hours before excavation.

1.3 UTILITY REQUIREMENTS

NAVFAC Public Works Utility Division is the Authority Having Jurisdiction per all applicable codes. Contact the them via the Contracting Officer.

1.3.1 Utility Connection Permit Application (UCPA)

A UCPA must be submitted to Utilities at start of project.

The UCPA must be updated as project is being built.

SECTION 01 14 00.00 23 Page 4

A completed UCPA must be submitted to Utilities for approval prior to system connection.

1.3.2 Domestic Water and Sewer

All connections and disconnections to/from any water system interior or exterior of a facility shall be coordinated through PW Utilities.

All water lines shall be flushed and purged after istallation of new lines or after any repairs are made to the water lines.

All buried water/sewer lines shall have a tracer wire placed in Trench for future location purposes. Tracer wire shall be connected in valve box for easy access for future use. Conduit and tracer wire shall be inspected while exposed by a member of Utilities. The tracer wire shall not be less than 18 AWG insulated. The insulation shall not be yellow in color.

(2009 National Standard Plumbing Code; 2.6.6).

Water valve boxes and sewer clean outs shall be raised to grade where new lines are installed or existing lines are tapped.

Backflow Prevention located on a domestic water main is NOT a requirement, unless the facility is considered a high hazard. In which case, a Reduced Pressure Principle Assembly will be required per the National Standard Plumbing Code 10.5.9. Utilities shall make this determination and approve submittals. Facilities that require protection on the domestic main will also be required to have parallel backflow preventers installed so as not to have an outage for maintenance and testing or failures.

Utilities shall review and approve all specs for Backflow Prevention assemblies being proposed for utilization. This shall include review and identify each cross connection device, location for hazard type and Inventory for Compliance.

All backflow preventers shall be piped with a Y strainer ahead of the device with the exception of Fire Mains.

Installation of all Backflow Preventers shall be done by a licensed plumber having a current license and certification in Backflow Prevention and Cross Connection Control from the State or Local Authority. A copy of the license shall be provided to Utilities for compliance records.

Utilities shall be notified before pressurizing Potable water mains.

All Backflow Prevention shall be tested and certified by a Government certified tester after the installer has tested the backflow. A copy of the test report and current gauge calibration shall be provided to Utilities.

Final project walk-through with FEAD and the contractor is required to ensure proper inventory is captured. This is to ensure compliance of all state and local codes.

Fire Hydrant used for filling a system such as Tanks, Tankers, or irrigation use, PW Utilities must be notified and a Utility approved back flow must be installed prior to filling. Fire Dept. notifications and waivers apply.

Systems such as boilers, chillers, and/or any closed loop systems

SECTION 01 14 00.00 23 Page 5 requiring water shall be filled through the dedicated system backflow preventer having been properly tested and certified.

Sanitize all new work according to the latest edition of the National Standard Plumbing Code.

Sewer lines shall have clean outs placed in systems where new lines are added or tie-ins occur. When a tie-in is made, Utilities must be scheduled to be on site. One week notice is required for Utility scheduling.

1.4 METERING

All new or renovated Facilities shall have electric and water meters installed.

Utilities shall provide and review all specs for water meters beign proposed for utilization.

1.4.1 Water Meter

"Y" strainer shall be installed upstream of water meter.

New potable water pipe installations shall be flowed and purged of debris before building being pressurized.

Sanitize new work according to the National Standard Plumbing Code.

Water meter must be service pipe size.

Water meter specs are listed below:

a. Water Meter Specifications Water meters shall be installed inside the mechancial room of the facility. Meters shall be industrial/commercial cold water turbine meters that meet or exceed AWWA C701 standards. Water meters shall have a by-pass consisting of three gate or ball valves as appropriate. A fourth valve is required to isolate non-integral strainers. All water meters shall have a non-resettable remote reader connected to them and the remote reader shall be mounted on the exterior wall (outside) of the facility, 5-1/2 feet to 6 feet above grade. The remote reader must be protected from direct sunlight.

b. All remote readers must be of the odometer or LCD type. Remote readers must be readable visually. Remote readers that require the use of any form of instrument/tool to read the remote reader shall not be used. Meters are to meet or exceed AWWA C701 Class II standards.

Register flow to be in U.S. gallons. Meter size is to be determined in accordance with the below table:

Maximum Flow Rate (in gallons per minute)

Meter Size

200 GPM 1-1/2 inches

400 GPM 2 inches

SECTION 01 14 00.00 23 Page 6

Maximum Flow Rate (in gallons per minute)

Meter Size

550 GPM 3 inches

1250 GPM 4 inches

2500 GPM 6 inches

4500 GPM 8 inches

7000 GPM 10 inches

8800 GPM 12 inches

Remote readers shall be addressed/programmed with a multiple/GPC (gallons per contact) of 10, 100 or 1000, whichever is appropriate with the facilities' projected manning, operations and water consumption. Remote and turbine meters must have the meter multiplier located on the meter.

Additionally a strainer shall be installed in the water line prior to the meter, unless an integral strainer is part of the meter assembly. If a non-integral strainer is used, its location must conform to the following guidelines as do placement of all valves, tees and elbows prior to and after each meter.

The number of inches of clear/straight water line prior to the meter shall be ten (10) times the water line diameter and the number of inches of clear/straight water line after the meter shall be five (5) times the diameter of the water line.

Examples:

Prior to water meter: water line size 3 inches, 3 inches x 10 = 30 inches. Must be at least 30 inches of straight and obstruction free water line prior to water reaching the meter.

After the water meter: water line size 3 inches, 3 inches x 5 = 15 inches. Must be at least 15 inches of straight and obstruction free water line after the meter.

No meter boxes or pits are allowed. All water meters shall be inside the facility mechanical room where the water service enters the building.

There are no exceptions to this requirement, all meters shall be inside the facility and readily available.

Use of "Hot Boxes". Hot boxes are not allowed on installation unless prior approval is received from the Utility Department Branch Head. This will require a package submittal to include; hot box specs, beacon light specs, backflow preventer specs, and design drawings to show how the box will communicate with the trouble desk.

1.4.2 Electric Metering

Comply with direction of Public Works Utility Division on installation metering standards. Inquire prior to award to determine local metering standards or components.

SECTION 01 14 00.00 23 Page 7

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00.00 23 Page 8

SECTION 01 20 00.00 23

PRICE AND PAYMENT PROCEDURES

08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00.00 23 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

Schedule of Prices ; G

1.3 Schedule of Prices

1.3.1 Data Required

Within 15 calendar days of Contract Award, prepare and deliver to the Contracting Officer a Schedule of Prices (construction Contract) as directed by the Contracting Officer. Schedule of Prices must have cost summarized and totals provided for each construction category. Provide a detailed breakdown of the Contract price, giving quantities for each of the various kinds of work, unit prices and extended prices. Contractor overhead and profit including salaries for field office personnel, if applicable, must be proportionately spread over all pay items and not included as individual pay items.

1.3.2 Payment Schedule Instructions

Payments will not be made until the Schedule of Prices has been submitted to and accepted by the Contracting Officer.

Additionally, the Schedule of Prices must be separated as follows:

a. Primary Facilities Cost Breakdown:

Defined as work on the primary facilities out to the 5 foot line.

Work out to the 5 foot line includes construction encompassed within a theoretical line 5 foot from the face of exterior walls and includes

SECTION 01 20 00.00 23 Page 1 attendant construction, such as pad mounted HVAC cooling equipment, cooling towers, and transformers placed beyond the 5 foot line.

b. Supporting Facilities Cost Breakdown:

Defined as site work, including incidental work, outside the 5 foot line.

1.4 CONTRACT MODIFICATIONS

In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the

EP 1110-1-8 .

1.5 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.5.1 Content of Invoice

Requests for payment will be processed in accordance with the Contract Clause FAR 52.232-27 Prompt Payment for Construction Contracts and FAR 52.232-5 Payments Under Fixed-Price Construction Contracts. Invoices not completed in accordance with contract requirements will be returned to the Contractor for correction of the deficiencies. The requests for payment shall include the documents listed below.

a. The Contractor's invoice, on NAVFAC Form 7300/30 furnished by the Government, showing in summary form, the basis for arriving at the amount of the invoice. Form 7300/30 must include certification by Quality Control (QC) Manager as required by the Contract.

b. The Estimate for Voucher/ Contract Performance Statement on NAVFAC Form 4330/54 furnished by the Government. Use NAVFAC Form 4330, unless otherwise directed by the Contracting Officer, on NAVFAC Contracts when a Monthly Estimate for Voucher is required.

c. Contractor's Monthly Estimate for Voucher and Contractors Certification (NAVFAC Form 4330) with Subcontractor and supplier payment certification. Other documents, including but not limited to, that need to be received prior to processing payment include the following submittals as required. These items are still required monthly even when a pay voucher is not submitted.

d. Monthly Work-hour report.

e. Updated Construction Progress Schedule and tabular reports required by the contract.

f. Contractor Safety Self Evaluation Checklist.

g. Updated submittal register.

h. Solid Waste Disposal Report.

i. Certified payrolls.

j. Updated testing logs.

SECTION 01 20 00.00 23 Page 2

k. Other supporting documents as requested.

1.5.2 Submission of Invoices

If DFARS Clause 252.232-7006 Wide Area WorkFlow Payment Instructions is included in the Contract, provide the documents listed in above paragraph CONTENT OF INVOICE in their entirety as attachments in Wide Area Work Flow (WAWF) for each invoice submitted. The maximum size of each WAWF attachment is two megabytes, but there are no limits on the number of attachments. If a document cannot be attached in WAWF due to system or size restriction, provide it as instructed by the Contracting Officer.

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.5.3 Final Invoice

a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.

b. For final invoices being submitted via WAWF, the original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice. Once receipt of the original Final Release Form and required certification of Transportation of Supplies by Sea has been confirmed by the Contracting Officer, the Contractor must then submit final invoice and attach a copy of the Final Release Form and required certification of Transportation of Supplies by Sea in WAWF.

c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.

1.6 PAYMENTS TO THE CONTRACTOR

Payments will be made on submission of itemized requests by the Contractor which comply with the requirements of this section, and will be subject to reduction for overpayments or increase for underpayments made on previous payments to the Contractor.

1.6.1 Obligation of Government Payments

The obligation of the Government to make payments required under the provisions of this Contract will, at the discretion of the Contracting Officer, be subject to reductions and suspensions permitted under the FAR and agency regulations including the following in accordance with FAR

32.103 Progress Payments Under Construction Contracts:

a. Reasonable deductions due to defects in material or workmanship;

SECTION 01 20 00.00 23 Page 3

b. Claims which the Government may have against the Contractor under or in connection with this Contract;

c. Unless otherwise adjusted, repayment to the Government upon demand for overpayments made to the Contractor; and

d. Failure to maintain accurate "as-built" or record drawings in accordance with FAR 52.236.21 and 01 78 00.00 23 CLOSEOUT SUBMITTALS will result in suspension of all payments until compliance is achieved.

e. Failure to submit accurate Monthly Network Analysis Updates in accordance with 01 32 17.00 23 NETWORK ANALYSIS SCHEDULES (NAS) will result in suspension of all payments until compliance is achieved.

1.6.2 Payment for Onsite and Offsite Materials

Progress payments may be made to the Contractor for materials delivered on the site, for materials stored off construction sites, or materials that are in transit to the construction sites under the following conditions:

a. FAR 52.232-5(b) Payments Under Fixed Price Construction Contracts.

b. Materials delivered on the site but not installed, including completed preparatory work, and off-site materials to be considered for progress payment must be major high cost, long lead, special order, or specialty items, not susceptible to deterioration or physical damage in storage or in transit to the construction site. Examples of materials acceptable for payment consideration include, but are not limited to, structural steel, non-magnetic steel, non-magnetic aggregate, equipment, machinery, large pipe and fittings, precast/prestressed concrete products, plastic lumber (e.g., fender piles/curbs), and high-voltage electrical cable. Materials not acceptable for payment include consumable materials such as nails, fasteners, conduits, gypsum board, glass, insulation, and wall coverings.

c. Materials to be considered for progress payment prior to installation must be specifically and separately identified in the Contractor's estimates of work submitted for the Contracting Officer's approval in accordance with Schedule of Prices requirement of this Contract.

Requests for progress payment consideration for such items must be supported by documents establishing their value and that the title requirements of the clause at FAR 52.232-5 Payments Under Fixed-Price Construction Contracts have been met.

d. Materials are adequately insured and protected from theft and exposure.

e. Provide a written consent from the surety company with each payment request for offsite materials.

f. Materials to be considered for progress payments prior to installation must be stored in a locatoin pre-approved by the Contracting Officer and readily accessible for inspection by the Government. Other locations are subject to written approval by the Contracting Officer.

g. Materials in transit to the job site or storage site are not acceptable for payment.

SECTION 01 20 00.00 23 Page 4

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 20 00.00 23 Page 5

SECTION 01 30 00.00 23

ADMINISTRATIVE REQUIREMENTS

08/23

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety -- Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00.00 23 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G

Progress and Completion Pictures; G

1.3 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

1.4 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 1600x1200x24 bit true color minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 20 digital photographs each week throughout the entire project from a minimum of ten different viewpoints selected by the Contractor unless otherwise directed by the Contracting Officer. Submit with the monthly invoice two sets of digital photographs, each set on a separate compact disc (CD) or data versatile disc (DVD), cumulative of all photos to date. Indicate photographs demonstrating environmental procedures.

Provide photographs for each month in a separate monthly directory and name each file to indicate its location on the view location sketch. Also provide the view location sketch on the CD or DVD as a digital file.

Include a date designator in file names. Photographs provided are for unrestricted use by the Government.

SECTION 01 30 00.00 23 Page 1

1.5 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 Liability, during the entire period of performance under this contract. Provide other insurance coverage as required by Maryland law.

1.6 SUPERVISION

1.6.1 Superintendent Qualifications

Provide project superintendent with a minimum of 5 years experience in construction with at least 5 of those years as a superintendent on projects similar in size and complexity. The individual must be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual must be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

The superintendent must have completed the course entitled "Construction Quality Management (CQM) for Contractors." If the Superintendent does not have a current certification, they must obtain the CQM for Contractors course certification within 90 days of award. This course is periodically offered by the Naval Facilities Engineering Command and the Army Corps of Engineers. Contact the Contracting Officer for information on the next scheduled class. Include the Superintendents qualifications and certificate as part of the QC Plan under section 01 45 00.

The Superintendent is not permitted to also serve as the Quality Control (QC) Manager or Site Safety and Health Officer (SSHO). If the Superintendent is the alternate for either of those positions, the contractor must also provide an alternate superintendent.

1.6.2 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of Contract work.In addition, if a Quality Control (QC) representative is required on the Contract, then that individual must also have fluent English communication skills.

1.6.3 Duties

The project superintendent is primarily responsible for managing subcontractors and coordinating day-to-day production and schedule adherence on the project. The superintendent is required to attend Red Zone meetings, partnering meetings, and quality control meetings. The superintendent or qualified alternative must be on-site at all times during the performance of this contract until the work is completed and accepted.

1.6.4 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to ensure timely completion.

SECTION 01 30 00.00 23 Page 2

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.7 PRECONSTRUCTION MEETING

Immediately after award , prior to commencing any work at the site, coordinate with the Contracting Officer a time and place to meet for the Preconstruction Meeting . The meeting must take place within 35 calendar days after award of the contract, but prior to commencement of any work at the site. The purpose of this meeting is to discuss and develop a mutual understanding of the administrative requirements of the Contract including but not limited to: daily reporting, invoicing, value engineering, safety, base-access, outage requests, hot work permits, schedule requirements, quality control, schedule of prices or earned value report, shop drawings, submittals, cybersecurity, prosecution of the work, government acceptance, final inspections and contract close-out. Contractor must present and discuss their basic approach to scheduling the construction work and any required phasing.

1.7.1 Attendees

Contractor attendees must include the Project Manager, Superintendent, Site Safety and Health Officer (SSHO), Quality Control Manager and major subcontractors.

1.8 FACILITY TURNOVER PLANNING MEETINGS (Red Zone Meetings)

Meet with the Government to identify strategies to ensure the project is carried to expeditious closure and turnover to the Client. Start planning the turnover process at the Pre-Construction Conference meeting with a discussion of the Red Zone process and convene at regularly scheduled NAVFAC Red Zone Meetings beginning at approximately 75 percent of project completion. Include the following in the facility Turnover effort:

1.8.1 Red Zone Checklist

a. Contracting Officer's Technical Representative (COTR) will provide the Contractor a copy of the Red Zone Checklist template.

b. Prior to 75 percent completion, modify the Red Zone Checklist template by adding or deleting critical activities applicable to the project and assign planned completion dates for each activity. Submit the modified Red Zone Checklist to the Contracting Officer. The Contracting Officer may request additional activities be added to the Red Zone Checklist at any time as necessary.

1.8.2 Meetings

a. Conduct regular Red Zone Meetings beginning at approximately 75 percent project completion, or three to six months prior to Beneficial Occupancy Date (BOD), whichever comes first.

b. The Contracting Officer will establish the frequency of the meetings, which is expected to increase as the project completion draws nearer.

At the beginning, Red Zone meetings may be every two weeks then increase to weekly towards the final month of the project.

SECTION 01 30 00.00 23 Page 3

c. Using the Red Zone Checklist as a Plan of Action and Milestones (POAM) and basis for discussion, review upcoming critical activities and strategies to ensure work is completed on time.

d. During the Red Zone Meetings discuss with the COTR any upcoming activities that require Government involvement.

e. Maintain the Red Zone Checklist by documenting the actual completion dates as work is completed and update the Red Zone Checklist with revised planned completion dates as necessary to match progress.

Distribute copies of the current Red Zone Checklist to attendees at each Red Zone Meeting.

1.9 PARTNERING

Contractor shall host the partnering session within 45 calendar days of contract award. To most effectively accomplish this Contract, the Contractor and Government must form a cohesive partnership with the common goal of drawing on the strength of each organization in an effort to achieve a successful project without safety mishaps, conforming to the Contract, within budget and on schedule. The partnering team must consist of personnel from both the Government and Contractor including project level and corporate level leadership positions. Key Personnel from the supported command, end user, NAVFAC, PWD, FEAD/ROICC, Contractor, key subcontractors and the Designer of Record are required to participate in the Partnering process.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 30 00.00 23 Page 4

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

(eCMS) 08/23

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

Utilize the Naval Facilities Engineering Systems Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or email submission, including originals or copies, of the documents are not permitted unless identified within the contract.

All government contracting specialist/officer, legal, and command communications will remain the same.

1.2 USER PRIVILEGES

The Contractor's key staff may be provided access to eCMS. Contact the COR for eCMS account access. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.

Additional project roles may be assigned for workflow. The COR makes the final decision on roles for the project. User's ability to view, edit documents may be lowered at the discretion of the COR.

Only one eCMS user account is required regardless of the number of user's projects. Notify the COR within seven calendar days if a contractor user is no longer associated with company or project so they can remove them from any open record and inactivate them from the project.

1.2.1 eCMS Subcontractor Users

If the contractor's user is a subcontractor, the subcontractor must be registered under the name of their company and email. For example it is common for contractors to contract Quality Control Managers. The QC Manager's account should be under their company's name and email reducing the number of eCMS accounts required.

1.2.2 Users with Multiple Roles

Users may have multiple roles associated with their account within eCMS.

Roles are used in workflow. When a user is added to the project, they will be assigned the default role when the user was created. Contact the COR to change or add roles to the user for the project.

1.2.3 Loss of Privilege

Users may lose privilege to access eCMS at the discretion of the COR and Contracting Officer. The eCMS is a collaborative system that allows flexibility of use and does not restrict all inappropriate user actions.

User activities are logged into eCMS in visible and background data

SECTION 01 31 23.13 20 Page 1 collection. Users found to use eCMS in an inappropriate action may have their eCMS access revoked. Examples include, but not limited to, fraudulent representations, sharing user accounts with others, and changing approved records without the consent of the COR. Depending on the severity of the infraction, the users can lose eCMS access for a period of time, permanently for the project, or lose eCMS access for any project. The contractor may appeal the suspension in writing to the contracting officer within 14 calendar days of notice. The appeal must identify the infraction, supporting information, and steps to ensure the infraction will not happen in the future.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-01 Preconstruction Submittals

List of Contractor's Personnel; G

For Division 1 government approved Pre-Construction submittals, combine into a single Pre-Construction Submittal Package.

Annotated with SD Type of SD-01. Pre-Construction submittal package approval date will be used as a KPI.

1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY

1.4.1 General

NAVFAC eCMS requires a web-browser (platform-neutral) and Internet connection. For best results, recommend using browser in InPrivate/Incognito mode; Internet speeds greater than 40mbps when uploading files, computers with high RAM and Solid State Drives, "White List" eCMS website, Zip or Split files for better uploading. Non-NAVFAC Users are not to use VPN when using eCMS per NAVFAC IT.

The use of eCMS is required by the Contractor and all associated costs and time necessary to utilize eCMS will be borne by the Contractor with no allowance for time extensions and at no additional cost to the government.

1.4.2 Contractor Personnel List

Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic submittals, RFIs, daily reports, and other files and will require access to the eCMS.

Project personnel roles which must be filled as applicable in the eCMS, include, at a minimum, the Contractor's Project Manager (KTR-PM), Superintendent (KTSUPT), Quality Control (QC) Manager (KTR-QC), Principal (KTR-PRIN), and Site Safety and Health Officer (KTR-SSHO). Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users.

Provide the following information:

SECTION 01 31 23.13 20 Page 2

Company Name

Name (First, Last)

Email Address

Project Role (CQM, SSHO, Superintendent, CM, PM, Principal)

Existing or New eCMS User

1.5 SECURITY CLASSIFICATION

In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.

In conformance with the Freedom of Information Act (FOIA), DoD INSTRUCTION 5200.48 CONTROLLED UNCLASSIFIED INFORMATION (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED INFORMATION" (CUI).NAVFAC eCMS must only be used for the transaction of unclassified information associated with construction projects. Controlled Unclassified Identification (CUI) documents may be loaded into eCMS with the appropriate markings.

1.5.1 Markings on CUI Documents

Contractor's proprietary information, or documents determined by the originator in accordance with CUI guidance, should be marked CUI.

Proprietary information not marked CUI can be released under the Freedom of Information Act (FOIA). Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on Unclassified U documents.

1.6 eCMS UTILIZATION

Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract. Utilize eCMS to transfer all submittals, RFIs, daily reports, and other files required by contract to be forwarded to the government.

Full eCMS use is required. All Submittals/Information to use eCMS Modules including, but not limited to, RFIs, Daily Reports, Meeting Minutes, Communications, Issues, Punch Lists, Checklists, and Flysheets, unless otherwise directed by the COR or Contracting Officer.

The eCMS as an Electronic File Repository is authorized for projects under $1M. Upload all files using the appropriate eCMS module or as directed by the COR. Bulk uploads of RFIs, Submittals, Daily Reports, Issues, Meeting Minutes or Communications records into eCMS modules are allowed. For RFIs, group files by specification number, RFP Part number, or sheet number. For Submittals, group files by specification number. For Daily Reports, group by date range(s), Issues by date range(s), Meeting Minutes by date range(s), and Communications by Type.

SECTION 01 31 23.13 20 Page 3

1.6.1 Restricted Information

Personally Identifiable Information (PII) transmittal such as credit card, driver's license, passport, social security, and payroll number are not permitted in eCMS.