02 - Govt Drawings Template - EOD Proficiency Range - Attachment F.pdf

PDF 832 KB Posted

Attached to
EOD Proficiency Range
Solicitation number
S-24800-00015594
Issued by
Oregon

About this file

This is a government drawings template document prepared for the EOD Proficiency Range project at Portland Air National Guard Base in Oregon, with project number TQKD26-2006 dated April 2026. The project encompasses three contract line items (CLINs): CLIN 1 for the Proficiency Range construction, CLIN 2 for a Viewing Pad, and CLIN 3 for an additional Viewing Pad cover. The primary scope of work involves constructing a 10' x 10' concrete viewing pad with a 6-inch slab-on-grade in a restricted military area. The concrete must meet 4000 PSI strength at 28 days and comply with ACI 301 Section 5 specifications, with reinforcing steel per ASTM A615 Grade 60 or ASTM A706 Grade 60 for weldable applications. Concrete mixes and rebar designs require government approval prior to installation. The contractor must complete all work within a restricted access area requiring government escort throughout the project duration, with the project schedule requiring approval 10 business days before work commences to arrange military escorts.

Key project requirements include contractor responsibility for underground utility locates, daily photo documentation with progress reports, weekly progress meetings as requested by the government, and waste removal off-base with weight-reported waste tickets submitted to the PANG Environmental Department. The contractor must provide sanitary facilities, bring potable water on-site, and ensure all water used is contained and removed off-site due to restrictive DEQ stormwater permit requirements. Equipment and tool washing is prohibited on-base, and any spills must be immediately remediated with government notification. All disturbed areas must be reseeded per specifications, concrete edges must be trowel-finished, and hot work permits must be obtained from the PANG Fire Department. Material laydown and parking are designated in a specified blue box area, with access coordinated through the Civil Engineer point of contact prior to contractor arrival at the gate.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Name: EOD PRO RANGE Project No: TQKD26-2006 Date: April 2026 Drawing No:

Drawing Title:

EOD Pro Range Portland Air National Guard Base, Oregon

COVER

G-01

SHEET INDEX

G-01 TITLE

G-02 GENERAL NOTES

G-03 SITE ACCESS

D-01 GENERAL MAP

D-02 CLIN 1 DRAWINGS

D-03 CLIN 2 DRAWINGS

BID OPTION SUMMARY

1. CLIN 1 – PROFICIENCY RANGE

2. CLIN 2 – VIEWING PAD

3. CLIN 3 – VIEWING PAD COVER

Drawing Title:

General Notes

G-02

GENERAL PROJECT NOTES:

1. ITB AND DRAWINGS TO BE READ IN CONJUNCTION WITH

SPECIFICATIONS AND ALL ATTACHMENTS IN ITB.

2. ALL DEBRIS TO BE DISPOSED OFF BASE. WASTE TICKETS TO BE

SUBMITTED TO PANG ENVIRONMENTAL DEPARTMENT.

3. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND ADJUST

WORK PLAN ACCORDINGLY, PRIOR TO BEGINNING CONSTRUCTION.

4. WORK TO BE COMPLETED IN RESTRICTED AREA. GOVERNEMTN

ESCORT REQUIRED FOR THE DURATION OF THE PROJECT.

5. PROJECT SCHEDULE (DAYS AND TIMES) MUST BE APPROVED 10

BUSINESS DAYS PRIOR TO START OF WORK, TO SCHEDULE

GOVERNMENT ESCORT.

6. THE CONTRACTOR SHALL BE RESPONSIBLE FOR COORDINATING WITH

142 SFS/RESOURCE PROTECTION OFFICE FOR ACCESS TO PANG BASE

(SEE ITB/CONTRACT FOR DETAILS).

7. CONTRACTOR TO PROVIDE SANITARY STATION.

8. CONTRACTOR TO PROVIDE WATER FOR PROJECT. NO TRUCK OR

EQUIPMENT WASHING IS APPROVED ON BASE.

9. CONTRACTOR RESPONSIBLE FOR UNDERGROUND UTILITY LOCATES.

10. EQUIPMENT AND TOOL WASHING IS PROHIBETED ON SITE.

11. CONTRACTOR TO BRING WATER ON SITE AND SHALL CONTAIN ALL

WATER TO DISPOSE OF OFF SITE. DEQ STORMWATER PERMIT FOR

PANG IS RESTRICTIVE AND PREVENTS ONSITE WASHING.

12. CONTRACTOR TO KEEP WORK AREA CLEAN AND FREE OF EXCESS

DEBRIS.

13. CONTRACTOR RESPONSIBLE FOR LOCKING UP JOB SITE, TOOLS AND

EQUIPMENT AT END OF DAY.

14. DAILY PHOTOS ARE REQUIRED BY CONTRACTOR WITH DAILY

PROGRESS REPORTS.

15. CONTRACTOR TO PARTICIPATE IN ANY WEEKLY PROGRESS REPORTS

WITH GOVERNMENT AS REQUESTED OR NEEDED BY THE

GOVERNMENT.

16. ANY AND ALL EQUIPMENT OR VEHICLE SPILLS SHALL BE

IMMEDITATELY REMEDIATED. CONTRACTOR TO NOTIFY THE

GOVERNMENT IMMEDITATELY.

17. ANY AND ALL WASTE SHALL BE REPORTED BY WEIGHT TO

GOVERNMENT VIA WASTE TICKETS.

REFERENCES AND SPECS:

1. ACI 301 SECTION 5

2. CAST IN PLACE CONCRETE 03 30 00

3. UNIT MASONRY 04 20 00

4. EARTHWORK 31 00 00

5. DEFENSE EXPLOSIVES SAFETY REGULATIONS

6055.09: VOLUME 5

PROJECT SPECIFIC NOTES:

1. SEE SPECIFIED PSI FOR CONCRETE: 4000 PSI AT 28 DAYS

2. REINFORCING STEEL: TYPICAL: ASTM A615, GRADE 60

WELDABLE BARS: ASTM A706, GRADE 60.

3. ANY AREA THAT IS DISTURBED BY EQUIPMENT, CONTRACTORS

OR THE PROJECT SHALL BE RESEEDED. SEE SEEDING

SPECIFICATIONS.

4. CONTRACTOR TO MARK AREA FOR PROJECT, PRIOR TO

EXCAVATION. GOVERNMENT TO INSPECT AND ALL PARTIES

AGREE ON LOCATION PRIOR TO WORK START.

5. CONTRACTOR TO FOLLOW INDUSTRY STANDARD PROCEDURES

ACCORDING TO THE REFERENCES AND SPECS LISTED BELOW.

6. CONCRETE MIX DESIGN AND REBAR SHALL BE SUBMITTED TO

GOVERNMENT FOR APPROVAL.

7. HOT WORK PERMIT SHALL BE AQCUIRED BY CONTRACTOR FROM

THE PANG FIRE DEPARTMENT DURING THE PROJECT.

8. CONCRETE TO BE BROOM FINISHED IN ACCORDANCE WITH ACI

301 SECTION 5.

9. EDGES TO BE TROWEL FINISHED.

10. PROVIDE 3/8- INCH -WIDE MORTAR JOINTS WHERE NECESSARY.

Drawing Title:

SITE ACCESS

G-03

GENERAL PROJECT NOTES:

1. RED ARROWS SHOW PATH TO ACCESS THE JOB SITE.

2. CONTRACTOR MUST CALL CE POC PRIOR TO ARRIVAL FOR

ACCESS TO JOB SITE.

3. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND

ADJUST WORK PLAN ACCORDINGLY, PRIOR TO BEGINNING

CONSTRUCTION.

4. BLUE BOX SHOWS MATERIAL LAYDOWN AND CONTRACTOR

PARKING.

5. ORANGE BOX SHOWS ROUGH AREA OF NEW RANGE.

6. Vehicle access????? Gate key

Drawing Title:

Map

D-01

MAP NOTES:

1. FENCE LINE

2. SEE ATTACHMENT D - EXPOSIVES SITE PLAN FOR MORE DETAILS.

Drawing Title:

Drawings

D-02

CLIN 1

SEE PROJECT SPECIFIC NOTES FOR

REBAR AND CONCRETE DETAILS

Drawing Title:

VIEWING PAD

D-02

CLIN 2

VIEWING PAD NOTES:

1. INSTALL 10’ X 10’ CONCRETE VIEWING PAD

2. SLAB ON GRADE TO BE 6”.

3. SEE PAGE 2 GENERAL AND PROJECT NOTES.

SLAB ON GRADE TO BE 6”

Slide Number 1
Slide Number 2
Slide Number 3
Slide Number 4
Slide Number 5
Slide Number 6