This document is a project bid package for Basewide Pavement Repair at the Portland Air National Guard Base in Oregon, dated 06/04/2025. The project involves comprehensive pavement maintenance across the base, with four primary scopes: mill and overlay (5,000 sqft), crack seal (1,000 linear feet), patch and repair (2,000 sqft), and pavement markings for the East and West Aprons (11,850 and 14,650 sqft respectively). The work will be conducted in restricted areas requiring government escort, with prioritized zones identified for each repair type, and includes specific technical requirements for crack sealing, debris removal, and sealant application.
The project specifications include detailed technical guidelines such as using compressed air for cleaning, specific sealant types (ASTM D6690, Type I and II), and precise application methods. The contractor must coordinate with base security (142 SFS/Resource Protection Office), complete FOD (Foreign Object Debris) training, provide sanitary facilities and water, and follow FAA Advisory Circular AC 150/5380-6C and other referenced standards. The repair work involves removing and replacing asphalt up to 6 inches deep, milling 2 inches, and reapplying 2 inches of asphalt, with careful attention to crack sealing techniques and pavement marking restoration.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROJECT NAME: BASEWIDE PAVEMENT REPAIR
PROJECT NO: FY25C Date: 06/04/2025
Drawing No:
Drawing Title:
BASEWIDE PAVEMENT REPAIR
Portland Air National Guard Base, Oregon
COVER
G-01
SHEET INDEX
G-01 COVER
G-02 NOTES
D-03 DRAWINGS – MILL AND OVERLAY
D-04 DRAWINGS – CRACK SEAL
D-05 DRAWINGS – PATCH AND REPAIR
D-06 DRAWINGS – PAVEMENT MARKINGS
*DRAWINGS TO BE READ IN CONJUNCTION WITH SCOPE OF WORK IN THE ITB.
Drawing No:
Drawing Title:
GENERAL SITE NOTES:
1. CONTRACTOR TO THROUGHLY DRY AND CLEAN THE CRACKS AND
ANY AREA TO BE PATCHED OR REPAIR, WITH COMPRESSED AIR
(100CFM OR GREATER) TO REMOVE OXIDEZED PAVEMENT, LOOSE
AGGREGATE AND FOREIGN DEBRIS.
2. ALL DEBRIS TO BE DISPOSED OFF BASE. WASTE TICKETS TO BE
SUBMITTED TO PANG ENVIRONMENTAL DEPARTMENT.
3. SEALANTS TO CONFORM WITH ASTMD6690, TYPE II OR ASTM D6690,
TYPE I. PREFERRED BRAND: COLJOINT 6690 TYPE I AND II OR
APPROVED EQUAL.
4. BACKER ROD MATERIAL- WHEN REQUIRED, USE BACKER ROD
MATERIAL IN ALL CRACKS THAT OTHERWISE WOULD REQUIRE
EXCESSIVE SEALANT. PLACE THE BACKER ROD SO THAT THE TOP
OF THE BACKER ROD IS AT LEAST 3/4 INCH BELOW THE TOP OF THE
PAVEMENT. ENSURE THAT THE BACKER ROD MATERIAL IS PLACED
AT THE SPECIFIED DEPTH AND IS NOT STRETCHED OR TWISTED
DURING INSTALLATION.
5. RATE OF PROGRESS OF CRACK PREPARATION - LIMIT THE STAGES
OF CRACK PREPARATION, WHICH INCLUDE AIR PRESSURE
CLEANING AND PLACING OF THE BACKER ROD MATERIAL, TO ONLY
THAT LINEAR FOOTAGE THAT CAN BE SEALED DURING THE SAME
DAY.
6. PREPARATION OF SEALANT- DO NOT HEAT HOT-POURED SEALANTS
IN EXCESS OF THE SAFE HEATING TEMPERATURE RECOMMENDED
BY THE MANUFACTURER, AS SHOWN ON THE SEALANT
CONTAINERS. WITHDRAW AND WASTE SEALANT THAT HAS BEEN
OVERHEATED OR SUBJECTED TO APPLICATION TEMPERATURES
FOR OVER 4 HOURS OR THAT HAS REMAINED IN THE APPLICATOR
AT THE END OF THE DAY'S OPERATION.
7. SUBMIT MANUFACTURER'S INSTRUCTIONS 3 DAYS PRIOR TO THE
USE OF THE MATERIAL ON THE PROJECT. INSTALLATION OF THE
MATERIAL WILL NOT BE ALLOWED UNTIL THE INSTRUCTIONS ARE
RECEIVED.
8. TIME OF APPLICATION - SEAL CRACKS IMMEDIATELY FOLLOWING
FINAL CLEANING AND DRYING OF THE CRACK WALLS AND
FOLLOWING THE PLACEMENT OF THE BACKER ROD MATERIAL
(WHEN REQUIRED). PLACE SEALANT ONLY WHEN CRACKS ARE DRY.
RECLEAN CRACKS THAT CANNOT BE SEALED UNDER THE
CONDITIONS SPECIFIED, OR WHEN RAIN INTERRUPTS SEALING
OPERATIONS, AND ALLOW TO DRY OR DRY BY MECHANICAL MEANS
PRIOR TO INSTALLING THE SEALANT
9. SEALING THE CRACK - IMMEDIATELY PRECEDING, BUT NOT
MORE THAN 50 FEET AHEAD OF THE CRACK SEALING
OPERATIONS, PERFORM A FINAL CLEANING AND DRYING WITH
COMPRESSED AIR. CRACKS SHOULD BE FILLED NO HIGHER
THAN 1/8 INCH ABOVE THE PAVEMENT. REMOVE EXCESS OR
SPILLED SEALANT FROM THE PAVEMENT BY APPROVED
METHODS AND DISCARD IT. INSTALL THE SEALANT IN A
MANNER WHICH PREVENTS THE FORMATION OF VOIDS AND
ENTRAPPED AIR. SEVERAL PASSES WITH THE APPLICATOR
WAND MAY BE NECESSARY TO OBTAIN THE SPECIFIED
SEALANT DEPTH FROM THE PAVEMENT SURFACE. DO NOT
USE GRAVITY METHODS OR POURING POTS TO INSTALL THE
SEALANT MATERIAL. DO NOT PERMIT TRAFFIC OVER NEWLY
SEALED PAVEMENT UNTIL THE SEALANT HAS CURED. CHECK
CRACKS FREQUENTLY TO ENSURE THAT THE NEWLY
INSTALLED SEALANT IS CURED TO A TACK-FREE CONDITION
WITHIN 3 HOURS.
10. CRACK SEALANT INSTALLATION - TEST SECTION PRIOR TO THE
CLEANING AND SEALING OF THE CRACKS FOR THE ENTIRE
PROJECT, CONSTRUCT A TEST SECTION AT LEAST 200 FEET
LONG USING THE SPECIFIED MATERIALS AND APPROVED
EQUIPMENT TO DEMONSTRATE THE PROPOSED SEALING OF
ALL CRACKS OF THE PROJECT. FOLLOWING THE COMPLETION
OF THE TEST SECTION AND BEFORE ANY OTHER CRACK IS
SEALED, INSPECT THE TEST SECTION TO DETERMINE THAT
THE MATERIALS AND INSTALLATION MEET THE
REQUIREMENTS SPECIFIED. IF MATERIALS OR INSTALLATION
DO NOT MEET REQUIREMENTS, REMOVE THE MATERIALS AND
RE-CLEAN AND RESEAL THE CRACKS AT NO COST TO THE
GOVERNMENT.
11. CLEANUP - DAILY, REMOVE UNUSED MATERIALS FROM THE
SITE AND LEAVE THE PAVEMENT IN A CLEAN CONDITION.
GENERAL PROJECT NOTES:
1. CONTRACTOR SHALL VERIFY EXISTING CONDITIONS AND
ADJUST WORK PLAN ACCORDINGLY, PRIOR TO
BEGINNING CONSTRUCTION.
2. WORK TO BE COMPLETED IN RESTRICTED AREA.
GOVERNEMTN ESCORT REQUIRED FOR THE DURATION
OF THE PROJECT.
3. PROJECT SCHEDULE (DAYS AND TIMES) MUST BE
APPROVED 72 HOURS PRIOR TO START OF WORK, TO
SCHEDULE GOVERNMENT ESCORT.
4. THE CONTRACTOR SHALL BE RESPONSIBLE FOR
COORDINATING WITH 142 SFS/RESOURCE PROTECTION
OFFICE FOR ACCESS TO PANG BASE (SEE ITB/CONTRACT
FOR DETAILS).
5. FOD TRAINING IS REQUIRED FOR ALL CONTRACTORS
WORKING PAST THE FLIGHTLINE. PANG WILL PROVIDE
FOD TRAINING.
6. CONTRACTOR TO PROVIDE SANITARY STATION.
7. CONTRACTOR TO PROVIDE WATER FOR PROJECT. NO
TRUCK OR EQUIPMENT WASHING IS APPROVED ON
BASE.
REFERENCES:
PAVEMENT REAPAIR
1. FFA ADVISORY CIRCLE DATED 10/10/2014 AC
NO:150/5380-6C
2. ASTMD6690
3. UFC 3-250-01
AIRFIELD MARKINGS
PLEASE REFER TO THE SPECIFICATIONS AND
REQUIREMENTS ON PREPARATION AND
INSTALLATION OF AIRFIELD MARKINGS AND SIGNS:
1. UFGS 32 01 11.51 (PAINT REMOVAL FROM
AIRFIELD PAVING)
2. UFGS 32 17 23 (PAVEMENT MARKINGS)
G-02
Notes
UPDATED PROJECT SPECIFICATIONS:
1. FOG SEAL: FOLLOW THE FAA SPECIFICATION P-608
2. MILL AND OVERLAY: 2" MILL WITH 2" ASPHALT PLACED BACK
3. PATCH AND REPAIR: REMOVAL OF ASPHALT UP TO 6" AND
REPLACEMENT WITH ASPHALT TO MATCH THE EXISTING THICKNESS
UP TO 6"
Drawing No:
Drawing Title:
SCOPE OVERVIEW
D-03
1st Priority
MILL AND OVERLAY
PRIORITY LEVEL
2nd Priority
Airfield
FOR BIDDING PURPOSES:
SCOPE TO INCLUDE 5000 SQFT
Drawing No:
Drawing Title:
SCOPE OVERVIEW
D-04
1st Priority
CRACK SEAL
PRIORITY LEVEL
2nd Priority
Airfield
FOR BIDDING PURPOSES:
SCOPE TO INCLUDE 1000 LNFT
Drawing No:
Drawing Title:
SCOPE OVERVIEW
D-05
Highest Priority
PATCH AND REPAIR
PRIORITY LEVEL
Middle Priority
Airfield FOR BIDDING PURPOSES:
SCOPE TO INCLUDE 2000 SQFT
Drawing No:
Drawing Title:
SCOPE OVERVIEW
D-06
Airfield NOTES:
1. REMOVE AND REPAINT MARKINGS
PAVEMENT MARKINGS
EAST AND WEST APRON
FOR BIDDING PURPOSES:
SCOPE TO INCLUDE
EAST APRON : 11,850
WEST APRON : 14,650
| Slide 1 |
| Slide 2 |
| Slide 3 |
| Slide 4 |
| Slide 5 |
| Slide 6 |