01-3 Attachment 3 (Submittal Schedule).pdf

PDF 100 KB Posted

Attached to
Project No. A-18-162, Repair Quarters 872, 874 and 878 at Camp Zama
Solicitation number
FA520920B0004
Issued by

About this file

This document is a submittal schedule for a federal construction contract to repair quarters at Camp Zama in Japan. The contract requires the submission of over 150 detailed plans, procedures, samples, inspection reports and other documents on various dates, from within 30 days of notice to proceed to prior to completion of construction. Key submittals include environmental protection and waste management plans, lead remediation and asbestos abatement procedures, concrete pouring and formwork plans, mechanical, electrical and plumbing system diagrams and specifications, performance test results for various building systems, and as-built drawings and closeout documentation. The solicitation was issued by the Department of the Air Force Pacific Air Forces for project number A-18-162. The resulting contractor must be authorized to do business in Japan and obtain any necessary licenses and permits to comply with host government requirements.

View the file

Other files

File Type Posted
Amendment 0002.pdf PDF
Attachment 1a (Addendum 1).pdf PDF
Attachment 6 (Question and Answer).pdf PDF
04 OF17 (Revised).pdf PDF
Amendment 0001.pdf PDF
04 OF17.pdf PDF
01-5 Attachment 5 (GFP Attachment).pdf PDF
02 List of Participant.pdf PDF
01 FA520920B0004.pdf PDF
01-4 Attachment 4 (Other Contr Rqts).pdf PDF
01-1 Attachment 1 (Contract Specification).pdf PDF
03 USAG-J 1529 with Sample.pdf PDF
00 Business w US Government.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROJECT NUMBER PROJECT TITLE SOLICITATION/CONTRACT NO.

A-18-162

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SECTION 01 11 01

1.9.2 Safety *

SECTION 01 11 01

1.9.3 Environmental **

SECTION 01 11 01

1.12.1 Comprehensive Construction

SECTION 01 11 01

2.1 Memo for HM Usage

SECTION 01 11 01

2.3 Drawing and Specification Bind

SECTION 01 11 01

1.16.1 As Built Drawing

SECTION 01 11 01

1.16.2 Photographic Records

SECTION 01 35 43

1.4 Environmental Protection Plan

SECTION 01 74 19

1.6 Waste Managt Plan**

SECTION 01 74 19

1.7 Manifest

SECTION 02 41 01

1.10 Survey Results

SECTION 02 41 01

3.1Work Procedure for Demolition

SECTION 02 41 01

3.1 Field inspection reports

SECTION 02 83 00

1.5 work procedure for lead remedia

SECTION 02 83 00

3.4.1.1 Initial Sample Results

A

X A

E

8 X

B

C15

X

B

B

D

E

A

E

X

A

A

A

B

X

X2

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

X

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

X

X

12 X

11 X

X

14 X

13 X

X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

E. Consult w/ CI

* Safety Office Only ** Env. Div Only *** CMB Only

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 02 83 00

1.3.3 Sampling and Analysis

SECTION 02 83 00

1.5.2.3 Occupational and Environme

SECTION 02 83 00

1.5.2.3 Sampling Results

SECTION 02 83 00

3.5.1.1Clearance Certification

SECTION 02 83 00

3.5.2. 1Hazardous Waste Manifest

SECTION 03 20 00

1.3 Work Procedure

SECTION 03 20 00

3.1 Detailed Drawings

SECTION 03 20 00

3.11 Quality Control And Inspection

SECTION 03 30 01

1.5 work procedure (Concrete)

SECTION 03 30 01

1.5 work procedure(Formwork)

SECTION 03 30 01

1.5.2.1Formwork

SECTION 03 30 01

1.5 Inspection/Test Reports

SECTION 03 30 01

1.5.3.4 Safety Data Sheets

SECTION 05 50 13

2.1 Access panels

SECTION 05 50 13

2.1 Access panels B30 X

B29 X

X B28

X C27

B26 X

B25 X

B24 X

X C23

B22 X

B21 X

X E20

X E19

X C18

X C17

X C16

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 07 14 00

3.1Work Procedure For Fluid-Appli

SECTION 07 14 00

3.1 Field Inspection Reports

SECTION 07 14 00

1.5 Warranty

SECTION 07 15 00

3.1 Work Procedure Eva Resin Wate

SECTION 07 15 00

3.1Field Inspection Reports

SECTION 07 15 00

2.1Safety Data Sheets

SECTION 07 21 16

3.1Work Procedure For Insulations

SECTION 07 21 16

3.1Field Inspection Reports

SECTION 07 21 16

2.1Material Data Sheets (Msds)

SECTION 07 54 20

3.2 Survey Reports

SECTION 07 54 20

3.4 Work Procedure For Polyvinyl-C

SECTION 07 54 20

1.6 Detail Drawings

SECTION 07 54 20

3.4 Field Inspection Reports

SECTION 07 54 20

1.10 Warranty

SECTION 07 54 20

2.1.1 Information Card X D45

X D44

X C43

B42 X

B41 X

B40 X

X B39

X C38

B37 X

X B36

X C35

B34 X

X D33

X C32

B31 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 07 54 20

3.12 Instructions to Government Per

SECTION 07 92 00

3.1 Work Procedure For Sealants

SECTION 07 92 00

3.1 Field Inspection

SECTION 07 92 00

2.1 Material Safety Data Sheets (Ms

SECTION 08 11 13

3.1Survey Reports

SECTION 08 11 13

3.2 Work Procedure For Aluminum

SECTION 08 11 13

3.2 detailed drawings

SECTION 08 11 13

3.2 Field Inspection Reports

SECTION 08 71 00

2.1 Hardware Items

SECTION 08 71 00

3.1 Installation

SECTION 08 71 00

1.4 Hardware Schedule

SECTION 08 81 00

3.1 Work Procedure For Glazing

SECTION 08 81 00

3.1 Field/Factory Acceptance Inspec

SECTION 09 22 03

3.3work procedure(Ceilings)

SECTION 09 22 03

3.3work procedure(Walls) B60 X

B59 X

X C58

B57 X

X D56

B55 X

B54 X

X C53

B52 X

B51 X

B50 X

X B49

X C48

B47 X

X D46

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 09 22 03

3.1 ceiling detailed drawings

SECTION 09 22 03

3.1 wall detailed drawings

SECTION 09 22 03

3.3 Field Inspection Reports

SECTION 09 29 00

3.1 Work Procedure For Gypsum Bo

SECTION 09 29 00

3.1 Detailed Drawings

SECTION 09 29 00

3.1 Field Inspection Reports

SECTION 09 29 00

2.1 Material Data Sheets (Msds)

SECTION 09 30 01

3.1 Work Procedure For Ceramic An

SECTION 09 30 01

3.1Detailed Drawings

SECTION 09 30 01

1.7Samples

SECTION 09 30 01

3.1Field Inspection Reports

SECTION 09 30 01

2.1 Safety Data Sheets

SECTION 09 65 01

3.2 Work procedure

SECTION 09 65 01

1.7 Samples

SECTION 09 65 01

3.2 Field Inspection Reports X C75

B74 X

B73 X

X B72

X C71

B70 X

B69 X

B68 X

X B67

X C66

B65 X

B64 X

X C63

B62 X

B61 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 09 67 23

3.1 Work Procedure For Cement Mo

SECTION 09 67 23

3.1 Detailed Drawings

SECTION 09 67 23

3.1 Field Inspection Reports

SECTION 09 67 23

2.1 Material Data Sheets (Msds)

SECTION 09 90 03

3.1 Work Procedure For Paints And

SECTION 09 90 03

1.9Color and Texture

SECTION 09 90 03

3.1Field Inspection Reports

SECTION 09 90 03

1.4Manufacturer's Material Safety D

SECTION 10 28 13

2.1 Accessory Items

SECTION 10 28 13

2.1 Accessory Items

SECTION 10 28 13

2.1 Accessory Items

SECTION 12 32 00

3.1 Work Procedure For Manufactur

SECTION 12 32 00

3.2.2 Fabrication Drawings

SECTION 12 32 00

3.2.2 Installation drawings

SECTION 12 32 00

1.3Manufacturer's Standard Color C B90 X

B89 X

B88 X

B87 X

X D86

B85 X

B84 X

X B83

X C82

B81 X

B80 X

X B79

X C78

B77 X

B76 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 12 32 00

2.2.1.1 Artificial Marble Couter Top

SECTION 12 32 00

2.2.1 Door Front (Kamachi Type)

SECTION 12 32 00

2.2.1 Side Panel Of Base/Hanging C

SECTION 12 32 00

3.1 Field Inspection Reports

SECTION 22 00 00

3.6.2 Disinfection plan with disinfec

SECTION 22 00 00

2.1.1 Pipe Materials

SECTION 22 00 00

2.1.2 Pipe Joints

SECTION 22 00 00

2.1.4 Miscellaneous Piping Material

SECTION 22 00 00

2.2 Valves

SECTION 22 00 00

2.3 Fixtures and Faucets

SECTION 22 00 00

3.5 Field Tests

SECTION 22 00 00

3.6.2 Water quality testing report

SECTION 23 00 00

1.2.1 Diagrams

SECTION 23 00 00

1.4.2 Detail Drawings

SECTION 23 00 00

2.7.1.1 Exhaust Fans B105 X

B104 X

B103 X

X C102

X C101

B100 X

B99 X

B98 X

B97 X

B96 X

B95 X

X C94

B93 X

B92 X

B91 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 23 00 00

2.7.2Kitchen Exhaust Hood

SECTION 23 00 00

3.8Performance Tests

SECTION 23 00 00

3.2 Manufacturer's Installation Instru

SECTION 23 00 00

3.10 Operation and Maintenance Ma

SECTION 23 00 03

1.4.4 Detail Drawings

SECTION 23 00 03

2.11.1.4 Heat Recovery Ventilators

SECTION 23 00 03

3.11 Performance Tests

SECTION 23 00 03

3.2Manufacturer's Installation Instru

SECTION 23 00 03

3.13.1 Operation and Maintenance M

SECTION 23 07 00

2.2 Pipe Insulation

SECTION 23 31 13

1.3 connection diagrams

SECTION 23 31 13

2.1.1Galvanized Steel Ductwork Ma

SECTION 23 31 13

3.4.1 Ductwork Leakage Tests

SECTION 23 31 13

3.4.1 Operational Tests

SECTION 23 31 13

3.6 Operation and Maintenance Man X D120

X C119

X C118

B117 X

B116 X

B115 X

X D114

B113 X

X C112

B111 X

B110 X

X D109

B108 X

X C107

B106 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 23 64 26

1.3.1System Drawing

SECTION 23 64 26

2.2Pipe and Specialties

SECTION 23 64 26

2.3 Valves

SECTION 23 64 26

2.4 Piping Accessories

SECTION 23 64 26

3.3 Tests, Flushing and Disinfection

SECTION 23 64 26

1.4 Manufacturer's Material Safety D

SECTION 23 82 19

3.1 Installation Drawings

SECTION 23 82 19

2.2 Fan Coil Units

SECTION 23 82 19

3.3 Operation and Maintenance Man

SECTION 26 20 00

3.1 Work Procedure For Electrical W

SECTION 26 20 00

1.4Detailed Drawings

SECTION 26 20 00

3.1Field Inspection Report

SECTION 26 51 00

2.1 LED Lighting Fixtures

SECTION 26 51 00

3.2 Operating Test

SECTION 31 23 00

3.1 work procedure for excavation a B135 X

X C134

B133 X

X C132

B131 X

B130 X

X D129

B128 X

B127 X

X B126

X C125

B

B

124 X

123 X

B122 X

B121 X

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.

CONTRAC-

ITEM OR DESCRIPTION REQUIRED DATE DATE TO RETURN FOLLOW-UP TOR RE- FINAL REMARKS

OF ITEM, CONTRACT SUBMISSION RECEIVED CIVIL SUSPENSE SUBMIT- APPROVAL

REFERENCE, TYPE OF DATE IN CONT- ENGINEER- DATE TAL

SUBMITTAL RACTING ING DIS-

APPROVED APPROVED

SCHEDULE OF MATERIAL SUBMITTALS

TO BE COMPLETED BY CONTRACT ADMINISTRATOR

LI

C

EN

SE

S

Repair Quarters 872, 874 and 878

C A

LC

U

LA

TO

N S

H

EE

TS

TE

ST

R

EP

O R

TS

O

TH

ER

S

IFB FA520920B0004

TO BE COMPLETED BY PROJECT ENGINNER

DATE

CONTRACTOR

NOTIFIED

C A

TA

LO

G D

A

TA

C O

LO

R

S

EL

EC

TI

O N

S

O

PE

R A

T.

M A

IN

T.

W O

R K

P R

O C

ED

U

R E

PL

A

N S

SH

O

P D

R A

W

IN

G S

SA

M

PL

ES

IN

ST

A

LL

A

TI

O N

IN

ST

R U

C

TI

O N

S

IN

ST

R U

C

TI

O N

S

C

ER

TI

FI

C A

TI

O

N S

SECTION 31 23 00

3.1 field inspection report

X C136

A. W/in 30 days after NTP B. 30 days prior to commencement of applic. work C. W/in 5days after commencement of applic. work D. Prior to compl. of Const. Pd.