About this file
This is a Scope of Work document issued by the State of Hawaii for general repairs and reroofing services at the Wailua River State Park comfort station located in Kapaa, Kauai. The project encompasses comprehensive renovation work including structural repairs, roof replacement, interior and exterior painting, plumbing updates, electrical system improvements, and restroom fixture replacement. The scope details specific work areas such as roof decking repair, installation of new roofing materials, interior wall and ceiling restoration, exterior surface treatment, and full bathroom modernization including new toilets, sinks, and associated plumbing systems. The document establishes detailed specifications and performance standards for all materials and workmanship, requiring compliance with Hawaii state building codes and standards applicable to public facilities.
The project requires the contractor to provide detailed cost proposals itemizing labor, materials, and equipment for each scope element, with pricing subject to Hawaii prevailing wage requirements. The work must be completed within a specified timeframe as outlined in the contract terms, with the contractor responsible for obtaining all necessary permits and approvals from state and county authorities. The document emphasizes quality assurance measures, site safety compliance, and restoration of the comfort station to full operational functionality. Funding is provided through state appropriations for park facility maintenance and improvements, with the successful bidder required to maintain adequate insurance coverage and bonding throughout the project duration.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 02 26 SPK 004 SOW.pdf | ||
| AG-008 103D General Conditions (1.10.23).pdf | ||
| 04 Proposal 26 SPK 004 ADDENDUM 2.pdf | ||
| 26 SPK 004 Addendum 1.pdf | ||
| 03 26 SPK 004 PHOTOS.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
i
State of Hawaii
DEPARTMENT OF LAND AND NATURAL RESOURCES
DIVISION OF STATE PARKS
Honolulu, Hawaii
BOARD OF LAND AND NATURAL RESOURCES
Ryan K.P. Kanaka ole Chairperson
SCOPE OF WORK
Job No. 26-SPK-004 Wailua River SP-Kaumualii & Old Smith's Landing Comfort Station Reroof & General Repairs
WAILUA, KAUAI, HAWAII
Approved: _________________________________________________
ERIC K. KATO
Parks Program Manager Division of State Parks
August 2026 i
INDEX
NOTICE TO BIDDERS ........................................................................................... ii
INFORMATION AND INSTRUCTIONS TO BIDDERS ....................................... I-1
PROPOSAL .............................................................................................................. P-1
SPECIAL PROVISIONS ............................................................................................ SP-1
GENERAL SPECIFICATIONS ............................................................................... S-1
SCOPE OF WORK
PHOTOS
DEPARTMENT OF LAND AND NATURAL RESOURCES INTERIM GENERAL
CONDITIONS, DATED OCTOBER 1994 (Bound Separately) ii
NOTICE TO BIDDERS
(Chapter 103D, HRS)
COMPETITIVE BIDS for Job No. 26-SPK-004 Wailua River SP-Kaumualii & Old Smith's Landing Comfort Station Reroof & General Repairs, Kauai, Hawaii shall be submitted to the Department of Land and Natural Resources, Division of State Parks on the specified date and time through the Hawaii State e- Procurement (HIePRO). HIePRO is accessible through the State Procurement Office website at www.spo.hawaii.gov.
The Department of Land and Natural Resources Interim General Condition, dated October 1994, as amended, and the General Conditions –AG008, latest revision shall be made part of the specifications.
The project is located at Wailua River State Park, Kauai, Hawaii.
The work shall generally consist of repairs to the comfort stations and replacement of the existing comfort stations roofs. Scope of work shall include, but not limited to comfort stations reroof, general repairs of comfort stations and other incidental work.
Base Bid: Reroof and general repairs for Kaumualii Comfort Station
Additive Alternate #1: Reroof and general repairs for Old Smith’s Landing Comfort Station
To be eligible to submit a bid, the Bidder must possess a valid State of Hawaii Contractor’s license classification General B.
A voluntary pre-bid conference and site visit will be held at the project site, Wailua River State Park, Kaumualii side at 9:30 am at 08/11/26.
Submission of any Requests for Information shall be submitted through the Hawaii State e-Procurement (HIePRO) system by 4:00pm on 08/18/26.
Submission of bid shall be submitted through the Hawaii State e-Procurement (HiePRO) system by 4:00 pm on 08/24/26.
The estimated cost of construction is $245,000.00.
The award of the contract, if it be awarded, will be subject to the availability of funds.
Since the estimated value of the cost of construction is less than $250,000, the apprenticeship agreement preference pursuant to Hawaii Revised Statutes §103-55.6 (ACT 17, SLH 2009) shall not apply.
Should there be any questions, please refer to the HIePRO solicitation.
I-1
INFORMATION AND INSTRUCTIONS TO BIDDERS
CONTENTS
Page
A Project Location and Scope of Work ............................................................... I-2 B Proposals ........................................................................................................... I-2 C General Conditions ........................................................................................... I-2 D Proposal Form ................................................................................................... I-2 E Omissions or Erasures ....................................................................................... I-2 F Notice of Intent to Bid and Questionnaire .......................................................... I-2 G Bid Security ...................................................................................................... I-2 H Contractor’s License Required .................................................................... I-2 – I-3 I Irregular Bids .................................................................................................... I-3 J Withdrawal of Bids ........................................................................................... I-3 K Successful Bidder to File Performance and Payment Bonds ............................ I-3 L Number of Executed Original Counterparts of Contract Documents ............... I-3 M Change Orders .................................................................................................. I-3 N Wages and Hours ................................................................................................ I-3 O Permits ......................................................................................................... I-3 – I-4 P Property Damage ................................................................................................ I-4 Q Time .................................................................................................................. I-4 R Bidder's Responsibility to Provide Proper Superintendence .............................. I-4 S Liquidated Damages ......................................................................................... I-4 T Hiring of Hawaii Residents ......................................................................... I-4 – I-5 U Water and Electricity ........................................................................................ I-5 V Public Convenience and Safety ........................................................................ I-5 W Work to be Done Without Direct Payment .......................................................... I-5 X Asbestos Containing Materials ......................................................................... I-5 Y Worker Safety .............................................................................................. I-5 – I-6 Z Quantities .......................................................................................................... I-6 AA Other Health Measures ..................................................................................... I-6 BB Hawaii Business Requirement .......................................................................... I-6 CC Compliance With §3-122-112 HAR ................................................................... I-6
I-2
INFORMATION AND INSTRUCTIONS TO BIDDERS
A. PROJECT LOCATION AND SCOPE OF WORK: The project location and scope of work shall be as generally described in the Notice to Bidders.
B. PROPOSALS: Bidders shall submit their bid, including the completed proposal form, bid bond, and any other documents required by the solicitation as part of their bid through the State of Hawaii e-Procurement System (HIePRO). See Item D, PROPOSAL FORM.
C. GENERAL CONDITIONS: The Department of Land and Natural Resources Interim
General Conditions dated October 1994, as amended, shall be made a part of these contract specifications and are referred to hereafter as the General Conditions.
D. PROPOSAL FORM: The Bidders shall fill out and upload the electronic copy of the proposal form to the HIePRO website when submitting the bid. Bid Proposals shall not be mailed, faxed or delivered to the State, unless requested to do so after the designated closing date. The successful Bidder shall fill out and print a hard copy of the proposal form, sign and submit the form with the contract award package.
E. OMISSIONS OR ERASURES: Any proposal which contains any omission or erasure or alteration not properly initialed, or conditional bid, or other irregularity may be rejected by the Board of Land and Natural Resources (Board).
F. NOTICE OF INTENT TO BID AND QUESTIONNAIRE:
A Notice of Intent to Bid is not required for this project. In compliance with HRS Section
103D-310, the lowest responsive and responsible bidder may be required to complete a questionnaire. When requested by the State, the completed questionnaire shall be submitted to the Chief Engineer for evaluation. Failure to furnish the requested information within the time allowed may be grounds for a determination of non-responsibility, in accordance with HRS Section 103D-310 and HAR Section 3-122-108.
G. BID SECURITY: A bid security will be furnished by each bidder as provided in sub-section
2.7 of the General Conditions. The successful bidder's bid security will be retained until Contract execution and furnished a performance and payment bond in an amount equal to one hundred percent (100%) of the total Contract price, including an amount estimated to be required for extra work, is furnished.
The Board reserves the right to hold the bid securities of the four lowest bidders until the successful bidder has entered into a contract and has furnished the required performance bond. All bid securities will be returned in accordance with sub-section 3.5 of the General Conditions.
Should the successful bidder fail to enter into a contract and furnish a satisfactory performance bond within the time stated in the proposal, the bid security shall be forfeited as required by law.
H. CONTRACTOR'S LICENSE REQUIRED: The Board will reject all bids received from contractors who have not been licensed by the State Contractors License Board in accordance
I-3 with Chapter 444, HRS; Title 16, Chapter 77, Hawaii Administrative Rules; and statutes amendatory thereto.
I. IRREGULAR BIDS: No irregular bids or propositions for doing the work will be considered by the Board.
J. WITHDRAWAL OF BIDS: No bidder may withdraw his bid between the time of the opening thereof and the award of contract.
K. SUCCESSFUL BIDDER TO FILE PERFORMANCE AND PAYMENT BONDS: The successful bidder will be required to file performance and payment bonds each; in the amount equal to the total contract price, including amounts estimated to be required for extra work, as provided in sub-section 3.6 of the General Conditions.
L. NUMBER OF EXECUTED ORIGINAL COUNTERPARTS OF CONTRACT
DOCUMENTS: If requested by the Board, six copies of the Contract, performance and payment bonds shall be executed.
M. CHANGE ORDERS: No work of any kind in connection with the work covered by the plans and specifications shall be considered as change order work, or entitle the Contractor to extra compensation, except when the work has been ordered in writing by the Chief Engineer (Engineer) and in accordance with sub-section 4.2 of the General Conditions.
The Contractor shall clearly identify and inform the Engineer in writing of any deviations from the contract documents at the time of submission and shall obtain the Engineer's written approval to the specified deviation prior to proceeding with any work.
N. WAGES AND HOURS: In accordance with sub-sections 7.3 to 7.9 of the General
Conditions relative to hours of labor, minimum wages and overtime pay, the current minimum wage rates promulgated by the Department of Labor and Industrial Relations (DLIR) shall be paid to the various classes of laborers and mechanics engaged in the performance of this contract on the job site. The minimum wages shall be increased during the performance of the contract in an amount equal to the increase in the prevailing wages for those kinds of work as periodically determined by the DLIR.
The Department of Land and Natural Resources will not recognize any claim for additional compensation because of the payment by the Contractor of any wage rate in excess of the said minimum wage rates. The possibility of wage increase is one of the elements to be considered by the Contractor in determining his bid, and will not, under any circumstances, be considered as the basis of a claim against the Department under this Contract.
No work shall be done on Saturdays, Sundays, legal State holidays, and/or in excess of eight
(8) hours each day without the written consent of the Engineer. Should permission be granted to work at such times, the Contractor shall pay for all inspection administrative costs thereof. No work shall be done at night unless authorized by the Engineer.
O. PERMITS: The State will process permit applications whenever possible, and the Contractor shall procure the pre-processed permits and pay the required fees. If permit applications are not processed by the State, the Contractor shall process the permit applications, permits and
I-4 licenses, and pay all charges and fees. In all cases, the Contractor shall give all notices necessary and incident to the due and lawful prosecution of the work.
P. PROPERTY DAMAGE: It shall be the responsibility of the contractor to respect State property and to prevent damage to existing improvements. The Contractor will be responsible for damages resulting from construction operations. Immediately upon discovery, the Contractor shall repair such damage to the satisfaction of the Engineer.
All trees and shrubbery outside the excavation, embankment or construction limits shall be fully protected from injury. All areas damaged by construction activities including the laydown area shall be seeded and regressed upon completion of the project.
Q. TIME: The time of completion is specified in the Proposal. It is the Board's intention to insist the Contractor diligently prosecute the work to completion within the specified time.
Prospective bidders are reminded that the State has the option to proceed with or abandon a project depending on whether the project can be completed for occupancy in the specified time.
It is the bidder's responsibility to check the availability of all materials before bidding. The bidder shall select sub-contractors and suppliers who can warrant availability and delivery of all specified or qualified materials to assure project completion within the specified time.
The successful bidder must assume all risks for completing the project by the specified date.
There shall be no extension of time for any reason except for delays caused by acts of God, labor disputes involving unions, or actions of the State. If for any reason the project falls behind schedule, the Contractor shall at its own cost, take necessary remedial measures to get the project back on schedule, i.e., working overtime, air freighting all materials, etc. In addition, if the Contractor fails to fully complete the project by the completion date, Contractor will be required to make the facility usable at its own cost.
R. BIDDER'S RESPONSIBILITY TO PROVIDE PROPER SUPERINTENDENCE: The successful low bidder shall designate in writing to the Engineer the name of its authorized superintendent (Superintendent), who will be present at the job site whenever any work is in progress. The Superintendent shall be responsible for all work, receiving and implementing instructions from the Engineer in a timely manner. The cost for superintendence shall be considered incidental to the project.
If the Superintendent is not present at the site of work, the Engineer shall have the right to suspend the work as described under sub-section 5.5 c. and 7.20 - Suspension of Work of the General Conditions.
S. LIQUIDATED DAMAGES: Liquidated damages in the amount specified in the Proposal will be assessed for each and every calendar day from and after the expiration of the time period stated in the Contract for the completion of the project.
T. HIRING OF HAWAII RESIDENTS: The Contractor shall comply with Act 68, SLH 2010, in the performance and for the duration of this contract. The Contractor shall ensure that Hawaii residents compose not less than eighty percent of the workforce employed to perform
I-5 the contract work on the project. The eighty percent requirement shall be determined by dividing the total number of hours worked on the contract by Hawaii residents, by the total number of hours worked on the contract by all employees of the Contractor in the performance of the contract. The hours worked by any Subcontractor of the Contractor shall count towards the calculation for this section. The hours worked by employees with shortage trades, as determined by the Department of Labor and Industrial Relations (DLIR), shall not be included in the calculation for this section.
The requirements shall apply to any subcontract of $50,000 or more in connection with the Contractor, that is, such Subcontractors must also ensure that Hawaii residents compose not less than eighty percent of the Subcontractor’s workforce used to perform the subcontract.
U. WATER AND ELECTRICITY: The Contractor shall make all necessary arrangements and pay all expenses for water and electricity used in the construction of this project.
V. PUBLIC CONVENIENCE AND SAFETY: The Contractor shall conduct construction operations with due regard to the convenience and safety of the public at all times. No materials or equipment shall be stored where it will interfere with the safe passage of public traffic. The Contractor shall provide, install, and maintain in satisfactory condition, all necessary signs, flares and other protective facilities and shall take all necessary precautions for the protection of the work and the convenience and safety of the public. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section
7.20 - Suspension of Work of the General Conditions.
W. WORK TO BE DONE WITHOUT DIRECT PAYMENT: Whenever the contract that the
Contractor is to perform work or furnish materials of any kind for which no price is fixed in the contract, it shall be understood that the Contractor shall perform such work or furnish said materials without extra charge or allowance or direct payment of any sort. The cost of performing such work or furnishing said material is to be included by the Contractor in a unit price for the appropriate item unless it is expressly specified that such work or material is to be paid for as extra work.
X. ASBESTOS CONTAINING MATERIALS: The use of asbestos containing materials or equipment is prohibited. The Contractor shall insure that all materials and equipment incorporated in the project are asbestos-free
Y WORKER SAFETY: The Contractor shall provide, install and maintain in satisfactory condition all necessary protective facilities and shall take all necessary precautions for the protection and safety of its workers in accordance with the Occupational Safety and Health Standards for the State of Hawaii. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section 7.20 - Suspension of Work of the
Z. QUANTITIES: All bids will be compared on the basis of quantities of work to be done as shown in the Proposal; the quantities shown in the Unit Price items are estimated, being given as a basis for comparison of bids. The Board reserves the right to increase or decrease the quantities given under the items or delete items entirely as may be required during the progress of the work.
I-6
AA. OTHER HEALTH MEASURES: Forms of work site exposure or conditions which may be detrimental to the health or welfare of workers or of the general public shall be eliminated or reduced to safe levels as required by the DOH codes, standards, and regulations. Suitable first aid kits and a person qualified to render first aid, as specified in the DOH regulations, shall be provided at all times when work is scheduled.
BB. HAWAII BUSINESS OR COMPLIANT NON-HAWAII BUSINESS REQUIREMENT:
Bidders (Contractors) shall be incorporated or organized under the laws of the State or be registered to do business in the State as a separate branch or division that is capable of fully performing under the contract, as stipulated in §3-122-112 HAR.
CC. COMPLIANCE WITH §3-122-112 HAR:
As a condition for award of the contract and as proof of compliance with the requirements of 103D-310(c) HRS, the apparent low bidder shall furnish the required documents to the Department. If the valid required certificates are not submitted on a timely basis for award of a contract, a bidder otherwise responsive and responsible may not receive the award. Bidder is responsible to apply for and submit the following documents to the Department.
A. TAX CLEARANCE REQUIREMENTS (HRS Chapter 237): Bidder shall obtain a tax clearance certificate from the Hawaii State Department of Taxation (DOTAX) and the Internal Revenue Service (IRS). The certificate is valid for six months from the most recently approved stamp date on the certificate; the certificate must be valid on the date received by the Department.
B. Department of Labor (DLIR) “Certificate of Compliance”. (HRS Chapter 383 -
Unemployment Insurance, Chapter 386 - Workers’ Compensation, Chapter 392 - Temporary Disability Insurance, and 393 – Prepaid Health Care): Bidder shall obtain a certificate of compliance from the Hawaii State Department of Labor and Industrial relations (DLIR). The certificate is valid for six months from the date of issue;
certificates must be valid on the date received by the Department.
C. Department of Commerce and Consumer Affairs (DCCA), Business Registration
Division (BREG) “Certificate of Good Standing”. Bidder shall obtain a certificate of good standing issued by the Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG). The certificate of good standing is valid for six months from the date of issue; certificates must be valid on the date received by the Department.
Alternately, instead of separately applying for these certificates at the various state agencies, bidder may choose to use the Hawaii Compliance Express (HCE), which allows businesses to register online through a simple wizard interface at http://vendors.ehawaii.gov to acquire a “Certificate of Vendor Compliance” indicating the bidder’s status is compliant with the requirements of §103D-310(c), HRS, and shall be accepted for contracting and final payment purposes. Bidders that elect to use the new HCE services will be required to pay an annual fee of $15.00 to the Hawaii Information Consortium, LLC (HIC). Bidders choosing not to participate in the HCE program will be required to provide the paper certificates as instructed in the previous paragraphs.
NOTICE TO BIDDERS
(Chapter 103D, HRS)
COMPETITIVE BIDS for Job No. 26-SPK-004 Wailua River SP-Kaumualii & Old Smith's Landing Comfort Station Reroof & General Repairs, Kauai, Hawaii shall be submitted to the Department of Land and Natural Resources, Division of State Parks on the specified date and time through the Hawaii State e- Procurement (HIePRO). HIePRO is accessible through the State Procurement Office website at www.spo.hawaii.gov.
The Department of Land and Natural Resources Interim General Condition, dated October 1994, as amended, and the General Conditions –AG008, latest revision shall be made part of the specifications.
The project is located at Wailua River State Park, Kauai, Hawaii.
The work shall generally consist of repairs to the comfort stations and replacement of the existing comfort stations roofs. Scope of work shall include, but not limited to comfort stations reroof, general repairs of comfort stations and other incidental work.
Base Bid: Reroof and general repairs for Kaumualii Comfort Station
Additive Alternate #1: Reroof and general repairs for Old Smith’s Landing Comfort Station
To be eligible to submit a bid, the Bidder must possess a valid State of Hawaii Contractor’s license classification General B.
A voluntary pre-bid conference and site visit will be held at the project site, Wailua River State Park, Kaumualii side at 9:30 am at 08/11/26.
Submission of any Requests for Information shall be submitted through the Hawaii State e-Procurement (HIePRO) system by 4:00pm on 08/18/26.
Submission of bid shall be submitted through the Hawaii State e-Procurement (HiePRO) system by 4:00 pm on 08/24/26.
The estimated cost of construction is $245,000.00.
The award of the contract, if it be awarded, will be subject to the availability of funds.
Since the estimated value of the cost of construction is less than $250,000, the apprenticeship agreement preference pursuant to Hawaii Revised Statutes §103-55.6 (ACT 17, SLH 2009) shall not apply.
Should there be any questions, please refer to the HIePRO solicitation.
SP-1
DLNR Special Provisions to DLNR IGC v22.01
SPECIAL PROVISIONS
Amend INTERIM GENERAL CONDITIONS, dated October 1994, as follows:
Section 2 – Proposal Requirements and Conditions
1. AMEND Section 2.1 Qualification of Bidder with the following:
Written Notice of Intent to Bid or Offer: A written Notice of Intent to Bid is not required for the Solicitation.
Standard Qualification Questionnaire: Bidders may be required to complete a standard qualifications questionnaire. When requested, the information shall be furnished within two working days or longer at the discretion of the Engineer. Failure to furnish the requested information within the time allowed may be grounds for a determination of non-responsibility, in accordance with HRS Section 103D-310 and HAR Section 3-122-108.
Hawaii Business or Compliant Non-Hawaii Business Requirement: Bidders shall be incorporated or organized under the laws of the State or be registered to do business in the State as a separate branch or division that is capable of fully performing under the contract, as stipulated in §3-122-112 HAR. A certified letter is not required prior to bid opening.
Compliance with §3-122-112 HAR: As a condition for award of the contract and as proof of compliance with the requirements of 103D-310(c) HRS, the apparent low bidder shall furnish the required documents to the Department. If the valid required certificates are not submitted on a timely basis for award of a contract, a bidder otherwise responsive and responsible may not receive the award. Bidder is responsible to apply for and submit the following documents to the Department.
A. Tax Clearance (HRS Chapter 237): Bidder shall obtain a tax clearance certificate from the Hawaii
State Department of Taxation (DOTAX) and the Internal Revenue Service (IRS). The certificate is valid for six months from the most recently approved stamp date on the certificate; the certificate must be valid on the date received by the Department.
B. Department of Labor (DLIR) “Certificate of Compliance”. (HRS Chapter 383 - Unemployment
Insurance, Chapter 386 - Workers’ Compensation, Chapter 392 - Temporary Disability Insurance, and 393 – Prepaid Health Care): Bidder shall obtain a certificate of compliance from the Hawaii State Department of Labor and Industrial relations (DLIR). The certificate is valid for six months from the date of issue; certificates must be valid on the date received by the Department.
C. Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG)
“Certificate of Good Standing”. Bidder shall obtain a certificate of good standing issued by the Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG). The certificate of good standing is valid for six months from the date of issue; certificates must be valid on the date received by the Department.
Hawaii Compliance Express. Alternately, instead of separately applying for these certificates at the various state agencies, bidder may choose to use the Hawaii Compliance Express (HCE), which allows businesses to register online through a simple wizard interface at http://vendors.ehawaii.gov to acquire a “Certificate of Vendor compliance” indicating that bidder’s status is compliant with requirements of §103D-310(c), HRS, shall be accepted for contracting and final payment purposes.
Bidders that elect to use the new HCE services will be required to pay an annual fee of $15.00 to the Hawaii
SP-2
Information Consortium, LLC (HIC). Bidders choosing not to participate in the HCE program will be required to provide the paper certificates as instructed in the previous paragraphs.
2. ADD Section 2.4a, Pre-Bid Conferences
Required Pre-bid Conferences: For construction and design-build projects with an estimated value of $500,000 or more and solicited under the competitive sealed bid method (103D-302 HRS); and for construction and design-build projects with an estimated value of $100,000 or more and solicited under the competitive sealed proposal method (103D-303 HRS); a pre-bid conference is required.
Other Pre-Bid Conferences: The Department may require a pre-bid conference for construction or design-build projects that are below the dollar threshold listed in above or when projects have special or unusual requirements.
Other Conditions: The Department may require the prospective Bidders to make a physical inspection of the project site and make attendance at the pre-bid conference a condition for submitting an offer.
Nothing stated at the pre-bid conference shall change the solicitation unless a change is made by written addendum.
3. DELETE Section 2.5, Addenda and Interpretations, in its entirety and replace with the following:
“Discrepancies, omissions, or doubts as to the meaning of drawings and specifications should be communicated using the question and answer section on the HIePRO solicitation for interpretation and must be received in the time frame set in the HIePRO solicitation. Any interpretation, if made and any supplemental instructions will be in the form of written addenda to the plans and specifications and made available prior to the offer due date. It shall be the prospective bidder’s sole responsibility to verify and obtain any said addenda. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the contract documents.”
Section 3 – Award and Execution of Contract
1. AMEND Section 3.3, Award of Contract, by deleting “sixty (60)” and replacing with “one hundred eighty (180)” in the first paragraph.
2. AMEND Section 3.3, Award of Contract, by adding the following after the first paragraph:
“If the contract is not awarded within the one hundred eighty (180) days, the Department may request the successful Bidder to extend the time for the acceptance of its bid. The Bidder may reject such a request without penalty; and in such case, the Department may at its sole discretion make a similar offer to the next lowest responsive and responsible bidder and so on until a bid is duly accepted or until the Department elects to stop making such requests.”
3. AMEND Section 3.9, Notice to Proceed, by replacing the last paragraph with the following:
In the event the Notice to Proceed is not issued within three hundred and sixty-five (365) calendar days after the date of bid opening, the Contractor may submit a claim for increased labor and materials costs (but not overhead costs). The claim shall be for labor and material
SP-3
costs incurred after 365 days and the full duration of the contract time allowed for the performance of the work (as specified on Page P-1 of the [Bid] PROPOSAL) have elapsed.
Such claims shall be accompanied with the necessary documentation to justify the claim. No payments will be made for escalation costs that are not fully justified as determined by the State.
4. ADD Section 3.10, Protests:
“3.10 PROTESTS—Pursuant to Section 103D-701, Hawaii Revised Statutes, an actual or prospective offeror who is aggrieved in connection with the solicitation or award may submit a protest. Any protest shall be submitting in writing to the Chairperson, Department of Land and Natural Resources, 1151 Punchbowl Street, Honolulu, Hawaii 96813, or designee as specified in the solicitation.
A protest shall be submitted in writing within five (5) working days after the aggrieved person knows or should have known the facts giving rise thereto; provided that a protest based upon the content of the solicitation shall be submitted in writing prior to the date set for receipt of offers. Further provided that a protest of an award or proposed award shall be submitted within five (5) working days after the posting of the award of the contract.
The notice of award, if any, resulting from this solicitation shall be posted on the HIePRO website.
Section 5 – Control of Work
AMEND Section 5.8 Value Engineering Incentive by deleting “$100,000” and replacing with “$250,000” in the first paragraph.
Section 6 – Substitution of Materials and Equipment
ADD the following to Section 6.3 Sub-paragraph b:
4. If the substitution meets all the requirements of the specifications and plans.
Section 7 – Prosecution and Progress
1. DELETE Section 7.2d in its entirety and replace with the following:
“d. Proof of Insurance Coverage
A Certificate of Insurance or other documentary evidence, to the satisfaction of the Engineer, that the Contractor has in place all insurance coverage required by the contract. The Certificate of Insurance shall contain wording which identifies the Project number and Project title for which the certificate of insurance is issued. Refer to the following for insurance requirements:
1. Insurance Requirements
(a) Obligation of Contractor - Contractor shall not commence any work until it obtains, at its own expense, all required herein insurance. Such insurance must have the approval of the Department as to limit, form and amount and must be maintained with a company authorized by laws of the State to issue such insurance in the State of Hawaii. Coverage by a “Non- Admitted” carrier is permissible provided the carrier has a AM Best’s Rating of “A-VII” or better.
SP-4
(b) All insurance described herein will be maintained by the Contractor for the full period of the contract and in no event will be terminated or otherwise allowed to lapse prior to written certification of final acceptance of the work by the Department.
(c) Certificate(s) of Insurance acceptable to the Department shall be filed with the Engineer prior to commencement of the work. Certificates shall identify if the insurance company is a “captive” insurance company or a “Non-Admitted” carrier to the State of Hawaii. The Best’s Rating must be stated for the “Non-Admitted” carrier. Certificates shall contain a provision that coverages afforded under the policies will not be canceled or changed until at least thirty
(30) days written notice has been given to the Engineer by registered mail. The insurance policies shall name the State of Hawaii, its officers and employees as an additional insured and such coverage shall be noted on the certificate. Should any policy be canceled before final acceptance of the work by the Department, and the Contractor fails to immediately procure replacement insurance as specified, the Department, in addition to all other remedies it may have for such breach, reserves the right to procure such insurance and deduct the cost thereof from any money due to the Contractor.
(d) Nothing contained in these insurance requirements is to be construed as limiting the extent of
Contractor’s responsibility for payment of damages resulting from its operations under this contract, including the Contractor’s obligation to pay liquidated damages, nor shall it affect the Contractor’s separate and independent duty to defend, indemnify and hold the Department harmless pursuant to other provisions of this contract. In no instance will the Department’s exercise of an option to occupy and use completed portions of the work relieve the Contractor of its obligation to maintain the required insurance until the date of final acceptance of the work.
(e) All insurance described herein shall be primary and cover the insured for all work to be performed under the contract, all work performed incidental thereto or directly or indirectly connected therewith, including traffic detour work or other work performed outside the work area, and all change order work.
(f) The Contractor shall, from time to time, furnish the Engineer, when requested, satisfactory proof of coverage of each type of insurance required or a copy of the actual policies covering the work. Failure to comply with the Engineer’s request may result in suspension of the work, and shall be sufficient grounds to withhold future payments due the Contractor and to terminate the contract for Contractor’s default.
(g) If the Contractor is self-insured, it shall furnish, upon the request and the satisfaction of the
Engineer, any documentation to demonstrate the ability to self-insure itself. The Engineer, from time to time, can conduct an audit to determine the ability of the Contractor to be self-insured. Failure to comply with the Engineer’s request will be considered a material breach of the contract, and at the discretion of the Engineer, may be sufficient grounds to terminate the contract, suspend any work or withhold future payments.
(h) It is the responsibility of the Contractor to notify the Department of any changes to its insurance policies or if the Contractor receives a notice of cancellation of any of its insurance policies. The Contractor will immediately provide written notice to the Department should the insurance policies evidenced on its Certificate of Insurance form be cancelled, limited in scope, or not renewed upon expiration.
SP-5
2. Types of Insurance - The Contractor shall purchase and maintain insurance described below which shall provide coverage against claims arising out of the Contractor’s operations under the contract, whether such operations be by the Contractor itself or by the subcontractor or by anyone directly or indirectly employed by any of them or by anyone for whose acts any of them may be liable.
(a) Worker’s Compensation. The Contractor and all subcontractors shall obtain worker’s compensation insurance for all persons whom they employ or may employ in carrying out the work under this contact. This insurance shall be in strict conformity with the requirements of the most current and applicable State of Hawaii Worker’s Compensation Insurance laws in effect on the date of the execution of this contract and as modified during the duration of the contract.
(b) Commercial General Liability. The Contractor shall obtain General Liability insurance with a limit of not less than $1,000,000 per occurrence and $2,000,000 aggregate. The insurance policy shall contain the following clauses: 1) "The State of Hawaii is added as an additional insured as respects to operations performed for the State of Hawaii."; and 2) "It is agreed that any insurance maintained by the State of Hawaii will apply in excess of, and not contributed with, insurance provided by this policy." The required limit of insurance may be provided by a single policy or with a combination of primary and excess polices.”
(c) Comprehensive Automobile Liability. The Contractor shall obtain Auto Liability insurance covering all owned, non-owned and hired autos with a combined single Limit of not less than $1,000,000 per accident for bodily injury and property damage. The insurance policy shall contain the following clauses: 1) "The State of Hawaii is added as an additional insured as respects to operations performed for the State of Hawaii."; and 2) "It is agreed that any insurance maintained by the State of Hawaii will apply in excess of, and not contributed with, insurance provided by this policy." The required limit of insurance may be provided by a single policy or with a combination of primary and excess polices.
Furthermore, the Contractor’s commercial general liability insurance and automobile liability insurance shall include coverage for bodily injury, sickness, disease or death of any person, arising directly or indirectly out of, or in connection with, the performance of work under this contract.
The Contractor’s property damage liability insurance shall provide for all damages arising out of injury to or destruction of property of others including the Department’s, arising directly or indirectly out of or in connection with the performance of the work under this contract including explosion or collapse.
The Contractor shall either:
i. Require each of its subcontractors to procure and to maintain during the life of its subcontract, subcontractors’ comprehensive general liability, automobile liability and property damage liability insurance of the type and in the same amounts specified herein; or
ii. Insure the activities of its subcontractors in its own policy.
The Contractor will be permitted, in cooperation with insurers, to maintain a self-insured
SP-6
retention for up to 25% of the per occurrence combined single limits of the commercial general liability and the automobile liability policies. The existence of the self-insured retention must be noted on the certificate of insurance coverage submitted to the Department or else it will be understood that the insurer is providing first dollar coverage for all claims. For all claims within the self-insured retention amount, the rights, duties and obligations between the Contractor and the Department shall be identical to that between a liability insurer and the Department, as an additional insured, as if there was no self-insured retention.
(d) Builder’s Risk Insurance. Unless included in the Specifications of this project, the
Contractor shall not be required to provide builder’s risk insurance. If required as noted in the Specifications, builder’s risk insurance shall be provided during the progress of work and until final acceptance by the Department upon completion of the contract. It shall be “All Risk” (including but not limited to earthquake, windstorm and flood damage) completed value insurance coverage on all completed work and work in progress to the full replacement value thereof. Such insurance shall include the Department as additional name insured. The insurance policy shall contain the following clauses: 1) "The State of Hawaii is added as an additional insured as respects to operations performed for the State of Hawaii."; and 2) "It is agreed that any insurance maintained by the State of Hawaii will apply in excess of, and not contributed with, insurance provided by this policy." The required limit of insurance may be provided by a single policy or with a combination of primary and excess polices.
The Contractor shall submit to the Engineer for its approval all items deemed to be uninsurable. The policy may provide for a deductible in an amount of up to 25% of the amount insured by the policy. With respect to all losses up to any deductible amount, the relationship between the Contractor and the Department shall be that of insurer and additional insured as if no deductible existed”.
2. DELETE Section 7.16 in its entirety and replace with the following:
“RESPONSIBILITY FOR DAMAGE CLAIMS; INDEMNITY – The Contractor shall indemnify the State and the Department against all loss of or damage to the State’s or the Department’s existing property and facilities arising out of any act or omission committed in the performance of the work by the Contractor, any subcontractor or their employees and agents. Contractor shall defend, hold harmless and indemnify the Department and the State, their employees, officers and agents against all losses, claims, suits, liability and expense, including but not limited to attorneys’ fees, arising out of injury to or death of persons (including employees of the State and the Department, the Contractor or any subcontractor) or damage to property resulting from or in connection with performance of the work and not caused solely by the negligence of the State or the Department, their agents, officers and employees. The State or the Department may participate in the defense of any claim or suit without relieving the Contractor of any obligation hereunder. The purchase of liability insurance shall not relieve the Contractor of the obligations described herein.
The Contractor agrees that it will not attempt to hold the State and its Departments and Agencies and their officers, representatives, employees or agents, liable or responsible for any losses or damages to third parties from the action of the elements, the nature of the work to be done under these specifications or from any unforeseen obstructions, acts of God, vandalism, fires or encumbrances which may be encountered in the prosecution of the work.
SP-7
The Contractor shall pay all just claims for materials, supplies, tools, labor and other just claims against the Contractor or any subcontractor in connection with this contract and the surety bond will not be released by final acceptance and payment by the Department unless all such claims are paid or released. The Department may, but is not obligated to, withhold or retain as much of the monies due or to become due the Contractor under this contract considered necessary by the Engineer to cover such just claims until satisfactory proof of payment or the establishment of a payment plan is presented.
The Contractor shall defend, indemnify and hold harmless the State and its Departments and Agencies and their officers, representatives, employees or agents from all suits, actions or claims of any character brought on account of any claims or amounts arising or recovered under the Worker’s Compensation Laws or any other law, by-law, ordinance, order or decree.
Section 8 – Measurement and Payment
1. DELETE Section 8.7a in its entirety and replace with the following:
a. Tax Clearances from the State of Hawaii Department of Taxation and Internal Revenue Service, subject to section 103D-328, HRS, current within two months of issuance date indicating that all delinquent taxes levied or accrued under State Statutes against the contractor have been paid.
2. ADD Section 8.7d, Certificate of Compliance:
d. A Certification from the Contractor affirming that the Contractor has, as applicable, remained in compliance with all laws as required by Section 103D-310, HRS, and Section 3-122-112, HAR. A contractor making a false affirmation shall be suspended and may be debarred pursuant to section
103D-702, HRS.
1. Certification of Compliance for Final Payment, State Procurement Office
Form-22. Must be Signed Original.
3. ADD Section 8.7e, Hawaii Compliance Express:
e. In lieu of submitting the tax clearances from Taxation and IRS, and SPO Form -22, the
Contractor may choose to use the Hawaii Compliance Express as described on page SP-1 of this Special Provisions.
SP-8
******** DO NOT PRINT THIS PAGE, JUST A NOTE! ********
2/28/22: Amended Section 3.9 to clarify the escalation claim provision when NTP is delayed. The revision was reviewed by ENG and DOBOR with input from Dep AG Cindy Young.
4/26/19: Revisions to the Proof of Insurance Coverage have been reviewed by Tracy Kitaoka/Risk Management Office. Per his comments, added paragraph (g) regarding self-insurance. For this specific clarification of minimum insurance requirements, we decided that the change provided clarification and did not add or delete any provisions and therefore, AG review was not required.
NOTE: 2/27/2007; SUBMITTAL TO ATTORNEY GENERAL’S OFFICE TO REVIEW REVISED
SPECIAL PROVISIONS HAVE NOT YET BEEN RETURNED TO ENGINEERING. THE
REVISIONS REFLECTED HERE, SPECIFICALLY, HAWAII COMPLIANCE EXPRESS AND
FINAL PAYMENT PROVISIONS, AND CHANGING THE NTP TIME SPAN FROM 180 DAYS TO
ONE YEAR, ARE THE ONLY CHANGES INCORPORATED INTO THIS SPECIAL PROVISIONS.
Ooops . . . . also, added provision for Builder’s Risk Insurance.
General Specifications S-1 01019-1 Job No. J00AO99A
DIVISION 1 – GENERAL REQUIREMENTS
SECTION 01019
GENERAL SPECIFICATIONS
PART 1 - GENERAL
1.1 GENERAL REQUIREMENTS
Work shall consist of furnishing all labor, tools, materials and equipment necessary and required to construct in place complete all work as indicated on the drawings and as specified herein.
1.2 GENERAL
A. Examination of Premises: The Contractor shall contact the Engineer and obtain permission before visiting the site.
B. All lines and grades shall be established by a licensed surveyor, or licensed Civil Engineer, registered in the State of Hawaii. The Contractor shall submit evidence of current and valid registration.
C. Notices: The Contractor shall notify the Engineer and give at least three (3) working days notice before starting any work.
D. Disruption of Utility Services: All work related to the temporary disconnection of electrical system shall be pre-arranged with the Engineer so that any disruption of such services will be kept to a minimum. In the event temporary power hook-up is required, the Contractor shall provide the necessary services.
E. Contractor's Operations
1. The Contractor must employ, insofar as possible, such methods and means of carrying out the work so as not to cause any interruption or interference to the facility's operations. Where the Contractor's operations would result in interruptions which would hamper the operations of the facilities, the Contractor shall rearrange the schedule of work accordingly.
2. The Contractor shall maintain safe passageway to and from the facility for the user agency personnel and the public at all times.
F. Lead Paint
1. When the project includes paint to be disturbed that was applied prior to 1980, it shall be assumed to contain lead. The Contractor shall inform its employees, subcontractors, and all other persons engaged in the project that lead containing
S-1 01019-2 Job No. J00AO99A paints are present in the existing buildings at the job site and to follow the requirements of the Department of Labor and Industrial Relations, Division of Occupational Safety and Health, Title 12, Subtitle 8,Chapter 148, Lead Exposure in Construction, Hawaii Administrative Rules (Chapter 12-148, HAR).
G. Parking Policy for Contractor
1. The Contractor and its employees will not be allowed to park in zones assigned to facility personnel.
2. Areas to be used by the Contractor shall be as designated by the Engineer. Any lawn damaged by the Contractor shall be restored as instructed by the Engineer at no cost to the State.
H. Toilet Accommodations: The Contractor may use the existing toilet facilities if so designated by the Engineer; however, it is the Contractor's responsibility…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .