This is a Scope of Work and competitive bid solicitation document issued by the State of Hawaii Department of Land and Natural Resources, Division of State Parks, for a solar lighting installation project at Wailua River State Park in Kapaa, Kauai. The project involves removing 28 existing light poles and associated fixtures from concrete foundations at the Wailua Marina and Smith's Luau area, and furnishing and installing 44 new Green Frog Systems Aspire-225 solar lighting systems (or approved equivalent), consisting of 30 units with T5 optics, 12 units with T2 optics, and 2 units with T3 optics. A voluntary pre-bid conference and site visit are scheduled for August 11, 2026, at 8:00 a.m. at the project site. Requests for Information must be submitted through the Hawaii State e-Procurement (HIePRO) system by August 18, 2026, and bids are due by 4:00 p.m. on August 24, 2026. The contract completion period is 180 consecutive calendar days from the date of written notice to proceed. Bidders must possess a valid State of Hawaii Contractor's License classification General B to be eligible.

The estimated construction cost is $245,000, which is below the $250,000 threshold, thereby exempting the project from apprenticeship agreement preferences under Hawaii Revised Statutes 103-55.6. Liquidated damages are set at $150 per calendar day for delays beyond the completion date. Bidders must submit bid security and, if awarded, provide performance and payment bonds equal to 100 percent of the total contract price. Hawaii residents must comprise at least 80 percent of the workforce in accordance with Act 68, SLH 2010. Award is contingent upon fund availability, and the Board reserves the right to reject any or all bids. Apparent low bidders must provide tax clearance certificates from the Hawaii Department of Taxation and the Internal Revenue Service, a Certificate of Compliance from the Department of Labor and Industrial Relations, and a Certificate of Good Standing from the Department of Commerce and Consumer Affairs, or alternatively obtain a Certificate of Vendor Compliance through the Hawaii Compliance Express program for a $15 annual fee.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

i

State of Hawaii

DEPARTMENT OF LAND AND NATURAL RESOURCES

DIVISION OF STATE PARKS

Honolulu, Hawaii

BOARD OF LAND AND NATURAL RESOURCES

Ryan K.P. Kanaka ole Chairperson

SCOPE OF WORK

Job No. 26-SPK-003 Wailua River SP Smith's Luau Replace Lights with Solar

WAILUA, KAUAI, HAWAII

Approved: _________________________________________________

ERIC K. KATO

Parks Program Manager Division of State Parks

August 2026 i

INDEX

NOTICE TO BIDDERS ........................................................................................... ii

INFORMATION AND INSTRUCTIONS TO BIDDERS ....................................... I-1

PROPOSAL .............................................................................................................. P-1

SPECIAL PROVISIONS ............................................................................................ SP-1

GENERAL SPECIFICATIONS ............................................................................... S-1

SCOPE OF WORK

PHOTOS

DEPARTMENT OF LAND AND NATURAL RESOURCES INTERIM GENERAL

CONDITIONS, DATED OCTOBER 1994 (Bound Separately) ii

NOTICE TO BIDDERS

(Chapter 103D, HRS)

COMPETITIVE BIDS for Job No. 26-SPK-003 Wailua River SP – Smith's Luau Replace Lights with Solar, Wailua, Kauai, Hawaii shall be submitted to the Department of Land and Natural Resources, Division of State Parks on the specified date and time through the Hawaii State e-Procurement (HIePRO). HIePRO is accessible through the State Procurement Office website at www.spo.hawaii.gov.

The Department of Land and Natural Resources Interim General Condition, dated October 1994, as amended, and the General Conditions –AG008, latest revision shall be made part of the specifications.

The project is located at Wailua River State Park, Kauai, Hawaii.

The work shall generally consist of replacing the existing light poles and pole-mounted site lighting with new Green Frog Systems (or approved equal) solar lights/poles, and other incidental work.

Base Bid: Remove and dispose of 28 existing light poles and associated fixtures from their existing concrete foundations at the Wailua Marina and Smith's Luau. Furnish and install a total of 44 new Green Frog Systems Aspire-225 solar lighting systems (or approved equal).

To be eligible to submit a bid, the Bidder must possess a valid State of Hawaii Contractor’s license classification General B.

A voluntary pre-bid conference and site visit will be held at the project site, Wailua River State Park Smith’s side on 08/11/2026, at 8:00 am.

Submission of any Requests for Information shall be submitted through the Hawaii State e-Procurement (HIePRO) system by 08/18/2026.

Submission of bid shall be submitted through the Hawaii State e-Procurement (HiePRO) system by 4:00 pm on 08/24/2026.

The estimated cost of construction is $245,000.00.

The award of the contract, if it be awarded, will be subject to the availability of funds.

Since the estimated value of the cost of construction is less than $250,000, the apprenticeship agreement preference pursuant to Hawaii Revised Statutes §103-55.6 (ACT 17, SLH 2009) shall not apply.

Should there be any questions, please refer to the HIePRO solicitation.

ii

I-1

INFORMATION AND INSTRUCTIONS TO BIDDERS

CONTENTS

Page

A Project Location and Scope of Work ............................................................... I-2 B Proposals ........................................................................................................... I-2 C General Conditions ........................................................................................... I-2 D Proposal Form ................................................................................................... I-2 E Omissions or Erasures ....................................................................................... I-2 F Notice of Intent to Bid and Questionnaire .......................................................... I-2 G Bid Security ...................................................................................................... I-2 H Contractor’s License Required .................................................................... I-2 – I-3 I Irregular Bids .................................................................................................... I-3 J Withdrawal of Bids ........................................................................................... I-3 K Successful Bidder to File Performance and Payment Bonds ............................ I-3 L Number of Executed Original Counterparts of Contract Documents ............... I-3 M Change Orders .................................................................................................. I-3 N Wages and Hours ................................................................................................ I-3 O Permits ......................................................................................................... I-3 – I-4 P Property Damage ................................................................................................ I-4 Q Time .................................................................................................................. I-4 R Bidder's Responsibility to Provide Proper Superintendence .............................. I-4 S Liquidated Damages ......................................................................................... I-4 T Hiring of Hawaii Residents ......................................................................... I-4 – I-5 U Water and Electricity ........................................................................................ I-5 V Public Convenience and Safety ........................................................................ I-5 W Work to be Done Without Direct Payment .......................................................... I-5 X Asbestos Containing Materials ......................................................................... I-5 Y Worker Safety .............................................................................................. I-5 – I-6 Z Quantities .......................................................................................................... I-6 AA Other Health Measures ..................................................................................... I-6 BB Hawaii Business Requirement .......................................................................... I-6 CC Compliance With §3-122-112 HAR ................................................................... I-6

I-2

INFORMATION AND INSTRUCTIONS TO BIDDERS

A. PROJECT LOCATION AND SCOPE OF WORK: The project location and scope of work shall be as generally described in the Notice to Bidders.

B. PROPOSALS: Bidders shall submit their bid, including the completed proposal form, bid bond, and any other documents required by the solicitation as part of their bid through the State of Hawaii e-Procurement System (HIePRO). See Item D, PROPOSAL FORM.

C. GENERAL CONDITIONS: The Department of Land and Natural Resources Interim

General Conditions dated October 1994, as amended, shall be made a part of these contract specifications and are referred to hereafter as the General Conditions.

D. PROPOSAL FORM: The Bidders shall fill out and upload the electronic copy of the proposal form to the HIePRO website when submitting the bid. Bid Proposals shall not be mailed, faxed or delivered to the State, unless requested to do so after the designated closing date. The successful Bidder shall fill out and print a hard copy of the proposal form, sign and submit the form with the contract award package.

E. OMISSIONS OR ERASURES: Any proposal which contains any omission or erasure or alteration not properly initialed, or conditional bid, or other irregularity may be rejected by the Board of Land and Natural Resources (Board).

F. NOTICE OF INTENT TO BID AND QUESTIONNAIRE:

A Notice of Intent to Bid is not required for this project. In compliance with HRS Section

103D-310, the lowest responsive and responsible bidder may be required to complete a questionnaire. When requested by the State, the completed questionnaire shall be submitted to the Chief Engineer for evaluation. Failure to furnish the requested information within the time allowed may be grounds for a determination of non-responsibility, in accordance with HRS Section 103D-310 and HAR Section 3-122-108.

G. BID SECURITY: A bid security will be furnished by each bidder as provided in sub-section

2.7 of the General Conditions. The successful bidder's bid security will be retained until Contract execution and furnished a performance and payment bond in an amount equal to one hundred percent (100%) of the total Contract price, including an amount estimated to be required for extra work, is furnished.

The Board reserves the right to hold the bid securities of the four lowest bidders until the successful bidder has entered into a contract and has furnished the required performance bond. All bid securities will be returned in accordance with sub-section 3.5 of the General Conditions.

Should the successful bidder fail to enter into a contract and furnish a satisfactory performance bond within the time stated in the proposal, the bid security shall be forfeited as required by law.

H. CONTRACTOR'S LICENSE REQUIRED: The Board will reject all bids received from contractors who have not been licensed by the State Contractors License Board in accordance

I-3 with Chapter 444, HRS; Title 16, Chapter 77, Hawaii Administrative Rules; and statutes amendatory thereto.

I. IRREGULAR BIDS: No irregular bids or propositions for doing the work will be considered by the Board.

J. WITHDRAWAL OF BIDS: No bidder may withdraw his bid between the time of the opening thereof and the award of contract.

K. SUCCESSFUL BIDDER TO FILE PERFORMANCE AND PAYMENT BONDS: The successful bidder will be required to file performance and payment bonds each; in the amount equal to the total contract price, including amounts estimated to be required for extra work, as provided in sub-section 3.6 of the General Conditions.

L. NUMBER OF EXECUTED ORIGINAL COUNTERPARTS OF CONTRACT

DOCUMENTS: If requested by the Board, six copies of the Contract, performance and payment bonds shall be executed.

M. CHANGE ORDERS: No work of any kind in connection with the work covered by the plans and specifications shall be considered as change order work, or entitle the Contractor to extra compensation, except when the work has been ordered in writing by the Chief Engineer (Engineer) and in accordance with sub-section 4.2 of the General Conditions.

The Contractor shall clearly identify and inform the Engineer in writing of any deviations from the contract documents at the time of submission and shall obtain the Engineer's written approval to the specified deviation prior to proceeding with any work.

N. WAGES AND HOURS: In accordance with sub-sections 7.3 to 7.9 of the General

Conditions relative to hours of labor, minimum wages and overtime pay, the current minimum wage rates promulgated by the Department of Labor and Industrial Relations (DLIR) shall be paid to the various classes of laborers and mechanics engaged in the performance of this contract on the job site. The minimum wages shall be increased during the performance of the contract in an amount equal to the increase in the prevailing wages for those kinds of work as periodically determined by the DLIR.

The Department of Land and Natural Resources will not recognize any claim for additional compensation because of the payment by the Contractor of any wage rate in excess of the said minimum wage rates. The possibility of wage increase is one of the elements to be considered by the Contractor in determining his bid, and will not, under any circumstances, be considered as the basis of a claim against the Department under this Contract.

No work shall be done on Saturdays, Sundays, legal State holidays, and/or in excess of eight

(8) hours each day without the written consent of the Engineer. Should permission be granted to work at such times, the Contractor shall pay for all inspection administrative costs thereof. No work shall be done at night unless authorized by the Engineer.

O. PERMITS: The State will process permit applications whenever possible, and the Contractor shall procure the pre-processed permits and pay the required fees. If permit applications are not processed by the State, the Contractor shall process the permit applications, permits and

I-4 licenses, and pay all charges and fees. In all cases, the Contractor shall give all notices necessary and incident to the due and lawful prosecution of the work.

P. PROPERTY DAMAGE: It shall be the responsibility of the contractor to respect State property and to prevent damage to existing improvements. The Contractor will be responsible for damages resulting from construction operations. Immediately upon discovery, the Contractor shall repair such damage to the satisfaction of the Engineer.

All trees and shrubbery outside the excavation, embankment or construction limits shall be fully protected from injury. All areas damaged by construction activities including the laydown area shall be seeded and regressed upon completion of the project.

Q. TIME: The time of completion is specified in the Proposal. It is the Board's intention to insist the Contractor diligently prosecute the work to completion within the specified time.

Prospective bidders are reminded that the State has the option to proceed with or abandon a project depending on whether the project can be completed for occupancy in the specified time.

It is the bidder's responsibility to check the availability of all materials before bidding. The bidder shall select sub-contractors and suppliers who can warrant availability and delivery of all specified or qualified materials to assure project completion within the specified time.

The successful bidder must assume all risks for completing the project by the specified date.

There shall be no extension of time for any reason except for delays caused by acts of God, labor disputes involving unions, or actions of the State. If for any reason the project falls behind schedule, the Contractor shall at its own cost, take necessary remedial measures to get the project back on schedule, i.e., working overtime, air freighting all materials, etc. In addition, if the Contractor fails to fully complete the project by the completion date, Contractor will be required to make the facility usable at its own cost.

R. BIDDER'S RESPONSIBILITY TO PROVIDE PROPER SUPERINTENDENCE: The successful low bidder shall designate in writing to the Engineer the name of its authorized superintendent (Superintendent), who will be present at the job site whenever any work is in progress. The Superintendent shall be responsible for all work, receiving and implementing instructions from the Engineer in a timely manner. The cost for superintendence shall be considered incidental to the project.

If the Superintendent is not present at the site of work, the Engineer shall have the right to suspend the work as described under sub-section 5.5 c. and 7.20 - Suspension of Work of the General Conditions.

S. LIQUIDATED DAMAGES: Liquidated damages in the amount specified in the Proposal will be assessed for each and every calendar day from and after the expiration of the time period stated in the Contract for the completion of the project.

T. HIRING OF HAWAII RESIDENTS: The Contractor shall comply with Act 68, SLH 2010, in the performance and for the duration of this contract. The Contractor shall ensure that Hawaii residents compose not less than eighty percent of the workforce employed to perform

I-5 the contract work on the project. The eighty percent requirement shall be determined by dividing the total number of hours worked on the contract by Hawaii residents, by the total number of hours worked on the contract by all employees of the Contractor in the performance of the contract. The hours worked by any Subcontractor of the Contractor shall count towards the calculation for this section. The hours worked by employees with shortage trades, as determined by the Department of Labor and Industrial Relations (DLIR), shall not be included in the calculation for this section.

The requirements shall apply to any subcontract of $50,000 or more in connection with the Contractor, that is, such Subcontractors must also ensure that Hawaii residents compose not less than eighty percent of the Subcontractor’s workforce used to perform the subcontract.

U. WATER AND ELECTRICITY: The Contractor shall make all necessary arrangements and pay all expenses for water and electricity used in the construction of this project.

V. PUBLIC CONVENIENCE AND SAFETY: The Contractor shall conduct construction operations with due regard to the convenience and safety of the public at all times. No materials or equipment shall be stored where it will interfere with the safe passage of public traffic. The Contractor shall provide, install, and maintain in satisfactory condition, all necessary signs, flares and other protective facilities and shall take all necessary precautions for the protection of the work and the convenience and safety of the public. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section

7.20 - Suspension of Work of the General Conditions.

W. WORK TO BE DONE WITHOUT DIRECT PAYMENT: Whenever the contract that the

Contractor is to perform work or furnish materials of any kind for which no price is fixed in the contract, it shall be understood that the Contractor shall perform such work or furnish said materials without extra charge or allowance or direct payment of any sort. The cost of performing such work or furnishing said material is to be included by the Contractor in a unit price for the appropriate item unless it is expressly specified that such work or material is to be paid for as extra work.

X. ASBESTOS CONTAINING MATERIALS: The use of asbestos containing materials or equipment is prohibited. The Contractor shall insure that all materials and equipment incorporated in the project are asbestos-free

Y WORKER SAFETY: The Contractor shall provide, install and maintain in satisfactory condition all necessary protective facilities and shall take all necessary precautions for the protection and safety of its workers in accordance with the Occupational Safety and Health Standards for the State of Hawaii. The Engineer shall have the right to suspend the performance of the work in accordance with sub-section 7.20 - Suspension of Work of the

Z. QUANTITIES: All bids will be compared on the basis of quantities of work to be done as shown in the Proposal; the quantities shown in the Unit Price items are estimated, being given as a basis for comparison of bids. The Board reserves the right to increase or decrease the quantities given under the items or delete items entirely as may be required during the progress of the work.

I-6

AA. OTHER HEALTH MEASURES: Forms of work site exposure or conditions which may be detrimental to the health or welfare of workers or of the general public shall be eliminated or reduced to safe levels as required by the DOH codes, standards, and regulations. Suitable first aid kits and a person qualified to render first aid, as specified in the DOH regulations, shall be provided at all times when work is scheduled.

BB. HAWAII BUSINESS OR COMPLIANT NON-HAWAII BUSINESS REQUIREMENT:

Bidders (Contractors) shall be incorporated or organized under the laws of the State or be registered to do business in the State as a separate branch or division that is capable of fully performing under the contract, as stipulated in §3-122-112 HAR.

CC. COMPLIANCE WITH §3-122-112 HAR:

As a condition for award of the contract and as proof of compliance with the requirements of 103D-310(c) HRS, the apparent low bidder shall furnish the required documents to the Department. If the valid required certificates are not submitted on a timely basis for award of a contract, a bidder otherwise responsive and responsible may not receive the award. Bidder is responsible to apply for and submit the following documents to the Department.

A. TAX CLEARANCE REQUIREMENTS (HRS Chapter 237): Bidder shall obtain a tax clearance certificate from the Hawaii State Department of Taxation (DOTAX) and the Internal Revenue Service (IRS). The certificate is valid for six months from the most recently approved stamp date on the certificate; the certificate must be valid on the date received by the Department.

B. Department of Labor (DLIR) “Certificate of Compliance”. (HRS Chapter 383 -

Unemployment Insurance, Chapter 386 - Workers’ Compensation, Chapter 392 - Temporary Disability Insurance, and 393 – Prepaid Health Care): Bidder shall obtain a certificate of compliance from the Hawaii State Department of Labor and Industrial relations (DLIR). The certificate is valid for six months from the date of issue;

certificates must be valid on the date received by the Department.

C. Department of Commerce and Consumer Affairs (DCCA), Business Registration

Division (BREG) “Certificate of Good Standing”. Bidder shall obtain a certificate of good standing issued by the Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG). The certificate of good standing is valid for six months from the date of issue; certificates must be valid on the date received by the Department.

Alternately, instead of separately applying for these certificates at the various state agencies, bidder may choose to use the Hawaii Compliance Express (HCE), which allows businesses to register online through a simple wizard interface at http://vendors.ehawaii.gov to acquire a “Certificate of Vendor Compliance” indicating the bidder’s status is compliant with the requirements of §103D-310(c), HRS, and shall be accepted for contracting and final payment purposes. Bidders that elect to use the new HCE services will be required to pay an annual fee of $15.00 to the Hawaii Information Consortium, LLC (HIC). Bidders choosing not to participate in the HCE program will be required to provide the paper certificates as instructed in the previous paragraphs.

P-1

P R O P O S A L

FOR

DEPARTMENT OF LAND AND NATURAL RESOURCES

DIVISION OF STATE PARKS

State of Hawaii

Wailua River SP – Smith's Luau Replace Lights with Solar

__________, 2026

Administrator Division of State Parks Department of Land and Natural Resources State of Hawaii Honolulu, Hawaii

Dear Sir:

The undersigned, having carefully examined the local conditions and all available records and information covering conditions which may affect the cost of the work to be performed, and having carefully examined the Scope of Work, and other contract documents, hereby proposes to furnish and pay for all materials, tools, equipment, labor and other incidental work necessary to demolish and remove existing light poles/fixtures and install new Green Frog Systems (or approved equal) light poles/fixtures in Wailua, Kauai, Hawaii. Scope of work shall include, but not limited to demolish and remove existing light poles/fixtures and install new Green Frog Systems (or approved equal) light poles/fixtures, and other incidental work as required or called for in this Proposal, all according to the true intent and meaning of the Notice to Bidders, Information and Instructions to Bidders, Proposal, Detailed Specifications, Interim General Conditions, Scope, and any and all addenda for:

Wailua River SP – Smith's Luau Replace Lights with Solar on file in the office of the Division of State Parks for the TOTAL BID (Items 1 to 4) of:

Dollars ($_____________________) and will fully complete all work under this contract within 180 consecutive calendar days from the date of written notice to proceed, including date of said order, said total sum being itemized on the following pages.

P-2

PROPOSAL

Item No.

Quantity

Unit

Description

Unit Price

Total

BASE BID

1. 28 EA

Remove and dispose of 28 existing light poles from their concrete bases, see SOW for extra details and other associated work that must be included in price. $ $

2. 30 EA

Install 30 new Green Frog Systems Aspire-225(or approved equal) with T5 optic onto existing concrete bases, see SOW for extra details and other associated work that must be included in price. $ $

3. 12 EA

Install 12 new Green Frog Systems Aspire-225(or approved equal) with T2 optic onto existing concrete bases, see SOW for extra details and other associated work that must be included in price. $ $

4. 2 EA

Install 2 new Green Frog Systems Aspire- 225(or approved equal) with T3 optic onto existing concrete bases, see SOW for extra details and other associated work that must be included in price. $ $

Base Bid (Items 4) $

P-3

RECYCLED PRODUCTS PREFERENCE

This project allows a 10% price preference for recycled products in accordance with HRS 103D-1005.

Please indicate your selection of recycled or non-recycled product by indicating its cost FOB jobsite unloaded in the schedule below, including applicable General Excise & Use Taxes.

RECYCLED NONRECYCLED

DESCRIPTION PRODUCT COST PRODUCT COST

The bidder requesting a recycled product preference shall also complete and submit the form “CERTIFICATION OF RECYCLED CONTENT” as shown in the Interim General Conditions and provide all supporting information with this proposal. Additional information may be requested to qualify a product.

The following definitions are applicable to the CERTIFICATION OF RECYCLED CONTENT form:

"Post-consumer recovered material" means any product used by a consumer, including a business that purchases the material, that has served its intended end use, and that has been separated or diverted from the solid waste stream for the purpose of use, reuse, or recycling.

"Product" includes materials, manufactures, supplies, merchandise, goods, wares, and foodstuffs.

"Recovered material” means waste material and by-products that have been separated, diverted, or removed from the solid waste stream after a manufacturing process for the purpose of use, reuse, or recycling. Recovered material does not include those materials and by-products that are generated and normally reused on-site or within original manufacturing processes (such as mill broke, in the case of paper products).

"Recycled content” means the percentage of a product composed of recovered material, or post-consumer recovered material, or both.

"Recycled product” means a product containing recovered material, or post-consumer recovered material, or both.

The bidder agrees that preference for recycled products shall be taken into consideration to determine the low bidder in accordance with said Section and the rules promulgated, however, the award of contract will be in the amount of the bid offered exclusive any preference.

CONTRIBUTIONS BY STATE AND COUNTY CONTRACTORS PROHIBITED

Contractors are hereby notified of the applicability of Section 11-355, HRS, which states that campaign contributions are prohibited from specified State or county government contractors during the term of the contract if the contractors are paid with funds appropriated by a legislative body.

P-4

CONDITION OF AWARD

It is understood that the award of the contract will be made on the basis of the lowest responsible Total Bid (Items 1 to 4) selected by the Board of Land and Natural Resources. Write the total of bid items 1 to 4 on page P-1.

It is understood and agreed that the Board of Land and Natural Resources reserves the right to reject any and/or all bids and waive any defects when, in the Board's opinion, such rejection or waiver will be for the best interest of the State of Hawaii.

In the event all bids exceed available funds certified by the appropriate fiscal officer, the head of the purchasing agency responsible for the procurement in question is authorized in situations where time or economic considerations preclude resolicitation of work of a reduced scope to negotiate an adjustment of the bid price, including changes in the bid requirements, with the low responsible and responsive bidder, in order to bring the bid within the amount of available funds. It is understood and agreed upon that the head of the purchasing agency may delete a portion or all of any item(s) in the proposal at the stated unit or lump sum price as necessary to stay within the available funding. The bidder is responsible to make an earnest effort to represent the actual cost of each item, including all materials, labor, equipment, overhead and profit in their bid proposal to preclude claims of anticipated profit or loss of profit because of an unbalanced bid proposal.

It is also understood that if a mutually agreeable cost for the reduced scope of work necessitated by a lack of available funds cannot be agreed upon between the bidder and the head of the purchasing agency within 14 calendar days after the bid opening, then the bid may be rejected in the best interest of the purchasing agency, and the head of the purchasing agency may negotiate in progressive order (lowest to highest) with the next lowest responsible and responsive bidder.

It is also understood and agreed that the award of the contract shall be conditioned upon funds being made available for this project and further upon the right of the Board of Land and Natural Resources to hold all bids received for a period of one hundred eighty (180) days from the date of the opening thereof, unless otherwise required by law, during which time no bid may be withdrawn.

It is also understood that Notice to Proceed may be delayed up to one (1) year after the bid opening date, and that no additional compensation will be provided for any claim for escalation or delay for issuance of Notice to Proceed on or before that date.

It is also understood and agreed that the quantities given herewith are approximate only and are subject to increase or decrease, and that the undersigned will perform all quantities of work as either increased or decreased, in accordance with the provisions of the Contract Specifications.

It is also understood and agreed that the estimated quantities shown for the items for which a UNIT PRICE is asked in this Proposal are only for the purpose of comparing on a uniform basis, bids offered for the work under this contract, and the undersigned agrees that he is satisfied with and will at no time, dispute said estimated quantities as a means of claims for anticipated profit or loss of profit, because of a difference between the quantities of the various classes of work done or the materials and equipment installed, and the said estimated quantities. On UNIT PRICE bids, payment will be made only for the actual number of units incorporated into the finished project at the contract UNIT PRICE.

After the HIePRO bid due date and time, the figures will be extended and/or totaled in accordance with the bid prices of the acceptable proposals and the totals will be compared. In the comparison of bids, words written in the proposal shall govern over figures and unit prices will govern over totals. Until the award of the contract, however, the right will be reserved to reject any and all proposals and to

P-5 waive any defects or technicalities as may be deemed best for the interest of the State.

It is also understood and agreed that liquidated damages in the amount of ONE HUNDRED FIFTY AND NO/100 DOLLARS ($150.00) for each and every calendar day in excess thereof prior to completion of the contract shall be withheld from payments due to the Contractor.

It is also understood and agreed that if this bid is accepted, the successful bidder must enter into and execute a contract with the Board of Land and Natural Resources and furnish a Performance and Payment Bond, as required by law. These bonds shall conform to provisions of Section 103D-324 and 325, Hawaii Revised Statutes and any law applicable hereto.

It is also understood and agreed that the successful bidder will provide all necessary labor, materials, tools, equipment, and other incidentals necessary to do all the work and furnish all the materials specified in the contract in the manner and time herein prescribed, and according to the requirements of the Engineer as therein set forth.

It is understood that by submitting this proposal, the undersigned is declaring that their firm has not been assisted or represented on this matter by an individual who has, in a State capacity, been involved in the subject matter of this contract in the past two years.

It is understood that by submitting this proposal in accordance with HAR 3-122-192, the undersigned is declaring that the price submitted is independently arrived without collusion.

It is also understood that by submitting this proposal, a Certification for Safety and Health Programs for bids in excess of $100,000 (in accordance with HRS 396-18), the undersigned certifies that his organization will have a written safety and health plan for this project that will be available and implemented by the Notice to Proceed date of this project. Details of the requirements of this plan may be obtained from the Department of Labor and Industrial Relations, Occupational, Safety and Health Division (HIOSH).

It is further understood and agreed that the successful bidder shall comply with paragraph 3.1.a "SUBCONTRACTING" of the General Provisions which requires that the contractor shall perform with his own organization and with the assistance of workmen under his immediate superintendence, work of a value not less than twenty percent (20%) of the value of all work embraced in the Contract, except that certain contract items of work, if specifically referred to in the special provisions, will be exempted from said twenty percent requirement.

Compliance with §103-310 HRS. As a condition of award all bidders shall comply with all laws governing entities doing business in the State, including Chapter 237 HRS (general excise tax);

Chapter 383 HRS (employment security – unemployment insurance); Chapter 386 HRS (workers compensation); Chapter 392 HRS (temporary disability insurance); and Chapter 393 HRS (pre-paid health care), and shall produce all documents to the State (DLNR, Engineering Division) required to demonstrate compliance with these subsections. Any bidder making a false affirmation or certification under this subsection shall be suspended and may be debarred from further offerings or awards pursuant to §103D-702 HRS.

P-6

RECEIPT OF ADDENDA

The bidder also acknowledges receipt of any and all addenda issued by the Division of State Parks, by recording the date of receipt of the respective addenda in the space provided below:

Addendum Date Received Addendum Date Received

No. 1 ___________ No. 5 ___________ No. 2 ___________ No. 6 ___________ No. 3 ___________ No. 7 ___________ No. 4 ___________ No. 8 ___________

It is understood that failure to receive any such addendum shall not relieve the Contractor from any obligation under this Proposal as submitted.

It is also understood and agreed that if this Proposal is accepted and the undersigned should fail or neglect to contract as aforesaid, the Board may determine that the bidder has abandoned the Contract, and thereupon, forfeiture of the security accompanying his proposal shall operate and the same shall become the property of the Board.

P-7

JOINT CONTRACTORS OR SUBCONTRACTORS

TO BE ENGAGED ON THIS PROJECT

The Bidder agrees that the following is a complete listing of all joint contractors or subcontractors covered under Chapter 444, Hawaii Revised Statutes (HRS), who will be engaged by the Bidder on this project to perform the required work indicated pursuant to Section 103D-302, HRS. It is the sole responsibility of the contractor to review the requirements of this Project and determine the appropriate licenses that are required to complete the Project. The Bidder certifies that the completed listing of joint contractors or subcontractors fulfills the requirements for the project and the Bidder, together with the listed subcontractors or joint contractors have all the specialty contractor’s licenses to complete the work, except as provided for in HRS §103D-302(b). Failure of the Bidder to comply with this requirement may be just cause for rejection of the bid.

“A” General Engineering Contractors and “B” General Building Contractors are reminded that due to the Hawaii Supreme Court’s January 28, 2002 decision in Okada Trucking Co., Ltd. v. Board of Water Supply, et al., 97 Haw. 450 (2002), they are prohibited from undertaking any work, solely or as part of a larger project, which would require the general contractor to act as a specialty contractor in any area in which the general contractor has no license. Although the “A” and “B” contractor may still bid on and act as the “prime” contractor on an “A” or “B” project (See, HRS §444-7 for the definitions of an “A” and “B” project.), respectively, the “A” and “B” contractor may only perform work in the areas in which they have the appropriate contractor’s license (An “A” or “B” contractor obtains “C” specialty contractor’s licenses either on its own, or automatically under HAR § 16-77- 32). The remaining work must be performed by appropriately licensed entities.

General Engineering “A” Contractors automatically have these “C” specialty contractor’s licenses: C-3, C-9, C-10, C-17, C-24, C-31a, C-32, C-35, C-37a, C-37b, C-38, C-43, C-49, C-56, C-57a, C-57b and C- 61.

General Building “B” Contractors automatically have these “C” specialty contractor’s licenses: C-5, C-6, C-10, C-12, C-24, C-25, C-31a, C-32a, C-42a and C-42b.

In completing the Joint Contractors or Subcontractors List, describe the specialty contractor’s nature and scope of work to be performed for this project and provide the complete firm name of the joint contractor or subcontractor in the respective columns. If the Bidder is a general contractor and providing the work of the required specialty contractor, whose license is not automatically held pursuant to HAR 16-77-32, fill in the Bidder’s (general contractor’s) name and nature and scope of work to be performed on this project.

List only one joint contractor or subcontractor per required specialty contractor’s classification, unless within the same specialty, the work of each joint contractor or subcontractor can be described so that there is no overlap in work descriptions.

If a contractor’s license is required by law for the performance of the work which is called for in this bid, the bidder and all subcontractors must have the required license before the submission of the bidder’s proposal in the case of a non-federal aid project, and for federal-aid projects, the bidder must have the required license prior to the award of the project and all subcontractors prior to the start of the subcontracted work.

P-8

COMPLETE FIRM NAME OF JOINT

CONTRACTOR OR SUBCONTRACTOR

NATURE AND SCOPE OF WORK TO BE

PERFORMED

P-9

Enclosed herewith is a:

1. Surety Bond (*1) )

2. Legal Tender (*2) )

3. Cashier's Check (*3) )

4. Certificate of Deposit (*3) ) in the

5. Certified Check (*3) ) amount

6. Official Check (*3) ) of

7. Share Certificate (*3) )

8. Teller's Check (*3) )

9. Treasurer's Check (*3) )

(Cross Out Those Not Applicable)

____________________________________________________Dollars ($_______________) as required by law.

Respectfully submitted, Name of Company, Joint Venture or Partnership

Contractor's License No.

By ____________________________________

Signature (*4)

Title __________________________________ Print Name _____________________________ Date __________________________________ Address ________________________________

Telephone No. __________________________

E-Mail Address _________________________

P-10

NOTES:

1. Surety bond underwritten by a company licensed to issue bonds in this State;

2. Legal tender; or

3. A certificate of deposit; share certificate; or cashier's, treasurer's, teller's, or official check drawn by, or a certified check accepted by, and payable on demand to the State by a bank, a savings institution, or credit union insured by the Federal Deposit Insurance Corporation or the National Credit Union Administration.

A. These instruments may be utilized only to a maximum of $100,000.

B. If the required security or bond amount totals over $100,000, more than one instrument not exceeding $100,000 each and issued by different financial institutions shall be accepted.

4. Please attach to this page evidence of the authority of this officer to submit bids on behalf of the Company and also the names and residence addresses of all officers of the Company.

5. Fill in all blank spaces with information asked for or bid may be invalidated. PROPOSAL

MUST BE INTACT, MISSING PAGES MAY INVALIDATE YOUR BID.

End of Proposal

SP-1

DLNR Special Provisions to DLNR IGC v22.01

SPECIAL PROVISIONS

Amend INTERIM GENERAL CONDITIONS, dated October 1994, as follows:

Section 2 – Proposal Requirements and Conditions

1. AMEND Section 2.1 Qualification of Bidder with the following:

Written Notice of Intent to Bid or Offer: A written Notice of Intent to Bid is not required for the Solicitation.

Standard Qualification Questionnaire: Bidders may be required to complete a standard qualifications questionnaire. When requested, the information shall be furnished within two working days or longer at the discretion of the Engineer. Failure to furnish the requested information within the time allowed may be grounds for a determination of non-responsibility, in accordance with HRS Section 103D-310 and HAR Section 3-122-108.

Hawaii Business or Compliant Non-Hawaii Business Requirement: Bidders shall be incorporated or organized under the laws of the State or be registered to do business in the State as a separate branch or division that is capable of fully performing under the contract, as stipulated in §3-122-112 HAR. A certified letter is not required prior to bid opening.

Compliance with §3-122-112 HAR: As a condition for award of the contract and as proof of compliance with the requirements of 103D-310(c) HRS, the apparent low bidder shall furnish the required documents to the Department. If the valid required certificates are not submitted on a timely basis for award of a contract, a bidder otherwise responsive and responsible may not receive the award. Bidder is responsible to apply for and submit the following documents to the Department.

A. Tax Clearance (HRS Chapter 237): Bidder shall obtain a tax clearance certificate from the Hawaii

State Department of Taxation (DOTAX) and the Internal Revenue Service (IRS). The certificate is valid for six months from the most recently approved stamp date on the certificate; the certificate must be valid on the date received by the Department.

B. Department of Labor (DLIR) “Certificate of Compliance”. (HRS Chapter 383 - Unemployment

Insurance, Chapter 386 - Workers’ Compensation, Chapter 392 - Temporary Disability Insurance, and 393 – Prepaid Health Care): Bidder shall obtain a certificate of compliance from the Hawaii State Department of Labor and Industrial relations (DLIR). The certificate is valid for six months from the date of issue; certificates must be valid on the date received by the Department.

C. Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG)

“Certificate of Good Standing”. Bidder shall obtain a certificate of good standing issued by the Department of Commerce and Consumer Affairs (DCCA), Business Registration Division (BREG). The certificate of good standing is valid for six months from the date of issue; certificates must be valid on the date received by the Department.

Hawaii Compliance Express. Alternately, instead of separately applying for these certificates at the various state agencies, bidder may choose to use the Hawaii Compliance Express (HCE), which allows businesses to register online through a simple wizard interface at http://vendors.ehawaii.gov to acquire a “Certificate of Vendor compliance” indicating that bidder’s status is compliant with requirements of §103D-310(c), HRS, shall be accepted for contracting and final payment purposes.

Bidders that elect to use the new HCE services will be required to pay an annual fee of $15.00 to the Hawaii

SP-2

Information Consortium, LLC (HIC). Bidders choosing not to participate in the HCE program will be required to provide the paper certificates as instructed in the previous paragraphs.

2. ADD Section 2.4a, Pre-Bid Conferences

Required Pre-bid Conferences: For construction and design-build projects with an estimated value of $500,000 or more and solicited under the competitive sealed bid method (103D-302 HRS); and for construction and design-build projects with an estimated value of $100,000 or more and solicited under the competitive sealed proposal method (103D-303 HRS); a pre-bid conference is required.

Other Pre-Bid Conferences: The Department may require a pre-bid conference for construction or design-build projects that are below the dollar threshold listed in above or when projects have special or unusual requirements.

Other Conditions: The Department may require the prospective Bidders to make a physical inspection of the project site and make attendance at the pre-bid conference a condition for submitting an offer.

Nothing stated at the pre-bid conference shall change the solicitation unless a change is made by written addendum.

3. DELETE Section 2.5, Addenda and Interpretations, in its entirety and replace with the following:

“Discrepancies, omissions, or doubts as to the meaning of drawings and specifications should be communicated using the question and answer section on the HIePRO solicitation for interpretation and must be received in the time frame set in the HIePRO solicitation. Any interpretation, if made and any supplemental instructions will be in the form of written addenda to the plans and specifications and made available prior to the offer due date. It shall be the prospective bidder’s sole responsibility to verify and obtain any said addenda. Failure of any bidder to receive any such addendum or interpretation shall not relieve such bidder from any obligation under his bid as submitted. All addenda so issued shall become part of the contract documents.”

Section 3 – Award and Execution of Contract

1. AMEND Section 3.3, Award of Contract, by deleting “sixty (60)” and replacing with “one hundred eighty (180)” in the first paragraph.

2. AMEND Section 3.3, Award of Contract, by adding the following after the first paragraph:

“If the contract is not awarded within the one hundred eighty (180) days, the Department may request the successful Bidder to extend the time for the acceptance of its bid. The Bidder may reject such a request without penalty; and in such case, the Department may at its sole discretion make a similar offer to the next lowest responsive and responsible bidder and so on until a bid is duly accepted or until the Department elects to stop making such requests.”

3. AMEND Section 3.9, Notice to Proceed, by replacing the last paragraph with the following:

In the event the Notice to Proceed is not issued within three hundred and sixty-five (365) calendar days after the date of bid opening, the Contractor may submit a claim for increased labor and materials costs (but not overhead costs). The claim shall be for labor and material

SP-3

costs incurred after 365 days and the full duration of the contract time allowed for the performance of the work (as specified on Page P-1 of the [Bid] PROPOSAL) have elapsed.

Such claims shall be accompanied with the necessary documentation to justify the claim. No payments will be made for escalation costs that are not fully justified as determined by the State.

4. ADD Section 3.10, Protests:

“3.10 PROTESTS—Pursuant to Section 103D-701, Hawaii Revised Statutes, an actual or prospective offeror who is aggrieved in connection with the solicitation or award may submit a protest. Any protest shall be submitting in writing to the Chairperson, Department of Land and Natural Resources, 1151 Punchbowl Street, Honolulu, Hawaii 96813, or designee as specified in the solicitation.

A protest shall be submitted in writing within five (5) working days after the aggrieved person knows or should have known the facts giving rise thereto; provided that a protest based upon the content of the solicitation shall be submitted in writing prior to the date set for receipt of offers. Further provided that a protest of an award or proposed award shall be submitted within five (5) working days after the posting of the award of the contract.

The notice of award, if any, resulting from this solicitation shall be posted on the HIePRO website.

Section 5 – Control of Work

AMEND Section 5.8 Value Engineering Incentive by deleting “$100,000” and replacing with “$250,000” in the first paragraph.

Section 6 – Substitution of Materials and Equipment

ADD the following to Section 6.3 Sub-paragraph b:

4. If the substitution meets all the requirements of the specifications and plans.

Section 7 – Prosecution and Progress

1. DELETE Section 7.2d in its entirety and replace with the following:

“d. Proof of Insurance Coverage

A Certificate of Insurance or other documentary evidence, to the satisfaction of the Engineer, that the Contractor has in place all insurance coverage required by the contract. The Certificate of Insurance shall contain wording which identifies the Project number and Project title for which the certificate of insurance is issued. Refer to the following for insurance requirements:

1. Insurance Requirements

(a) Obligation of Contractor - Contractor shall not commence any work until it obtains, at its own expense, all required herein insurance. Such insurance must have the approval of the Department as to limit, form and amount and must be maintained with a company authorized by laws of the State to issue such insurance in the State of Hawaii. Coverage by a “Non- Admitted” carrier is permissible provided the carrier has a AM Best’s Rating of “A-VII” or better.

SP-4

(b) All insurance described herein will be maintained by the Contractor for the full period of the…