Construction, CCADF Sprinkler Heads Replacement
Solicitation number
2026-389
Issued by
Collin County, Texas

About this file

This is a Product Substitution Request Form for a construction project managed by Collin County, Texas, related to fire sprinkler system work. The form serves as a formal mechanism for bidders to propose alternative products or manufacturers in place of those specified in the contract documents for IFB 2024-403. The document requires bidders to provide comprehensive supporting documentation including product descriptions, specifications, drawings, photographs, performance data, and test results to support their substitution requests. Bidders must also describe any changes to contract documents necessitated by the proposed substitution and warrant that the alternative product is equal or superior to the specified product, maintains equivalent warranty coverage, preserves the same maintenance service and parts availability, causes no adverse effects on other trades or schedule impacts, and does not affect dimensions or functional clearances.

The form includes a review and action section for project administrators to approve, conditionally approve, reject, or deny the substitution request based on timeliness and compliance with project manual requirements. Supporting documentation options include drawings, product data, samples, tests, reports, and other materials relevant to the substitution evaluation. Submission requirements mandate that any approved substitutions proceed with submittals in accordance with Project Manual specifications, while rejected or late requests require bidders to use the originally specified materials. The form establishes accountability by requiring the bidder's signature, firm name, address, and contact information, as well as the reviewing official's signature and date of action.

View the file

Other files

File Type Posted
Construction,_CCADF_Sprinkler_Heads_Replacement.pdf PDF
206.07.15_CCADF_Sprinkler_Head_Replacement_Specifications_Book.pdf PDF
LEGAL_NOTICE-2026-389.pdf PDF
Construction_Agreement.docx DOCX document
004547-Conflict_of_Interest.pdf PDF
Construction_Agreement_Architect_2.12.25.docx DOCX document
Maintenance_Bond.pdf PDF
Payment_Bond.pdf PDF
Bid_Bond.doc DOC document
W9.pdf PDF
Performance_Bond.pdf PDF
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 004325 - PRODUCT SUBSTITUTION REQUEST FORM

Bidder: Project No: IFB 2024-403

Project: Construction, Collin County Courthouse Fire Sprinkler Pipe Replacement

Section: Article/ Paragraph:

Proposed Substitution:

Manufacturer: Address:

Telephone: Proposed Model No.:

Attached data includes product description, specifications, drawings, photographs, and performance and test data adequate for evaluation of the request; applicable portions of the data are clearly identified.

Attached data also includes a description of changes to the Contract Documents that the proposed substitution will require for its installation.

The undersigned warrants and represents:

· Proposed substitution has been fully investigated and determined to be equal or superior in all respects to specified product.

· Same warranty will be furnished for proposed substitution as for specified product.

· Same maintenance service and source of replacement parts, as applicable, is available.

· Proposed substitution will have no adverse effect on other trades and will not affect or delay progress schedule.

· Proposed substitution does not affect dimensions and functional clearances.

· Payment will be made for changes to building design, including A/E design, detailing, and construction costs caused by substitution.

Submitted By: Signed:

Firm: Address:

Phone:

REVIEW & ACTION (Initial)

Substitution approved - Make submittals in accordance with Project Manual requirements.
Substitution approved as noted - Make submittals in accordance with Project Manual requirements.
Substitution rejected - Use specified materials.
Substitution Request received too late - Use specified materials.

Signature: Date:

Supporting Data Attached: ____Drawings ____Product Data ____Samples ____Tests ____Reports ____Other

END OF REQUEST FORM