This is a Request for Bid (RFB) document issued by the Oregon Department of Transportation (ODOT) for on-call Region 2 paving work. The project, titled "I5 Intermittent Inlay Paving MP199.31-203.55," involves 2-inch inlay paving on Interstate 5 in both northbound and southbound directions around the Coburg exit (milepoint 199) in Lane County, Oregon. The scope of work includes cold plane pavement removal (51,462 square yards), dense asphalt concrete pavement placement (5,790 tons), thermoplastic line striping (41,461 feet), and recessed white Type IAR markers (783 units), along with mobilization, temporary traffic control, and pollution control planning. Work is restricted to night hours between 8:00 PM and 6:00 AM, with a minimum 14-day mobility notice required for ramp closures. The project has a required completion date of September 30, 2026, with a bid submission deadline of June 4, 2026, at 2:00 PM. ODOT Project Manager Cody Stone (503-953-6334) oversees the project.
This RFB is limited to holders of the On-Call Region 2 Paving Price Agreement, meaning only pre-qualified contractors may bid. The project requires compliance with Oregon's domestic preference requirements under ORS 279C.303 and State Buy America Provisions. All work must be performed at prevailing wage rates as established by Oregon's Department of Business and Consumer Services (effective January 5, 2026, as amended April 5, 2026). Bidders must submit completed bid forms via OregonBuys with unit prices and total pricing for all line items. Portable changeable message signs must be placed at least seven days in advance of any ramp or lane closures. A regulated speed reduction of 55 miles per hour has been implemented for the project, with coordination ongoing for Oregon State Police presence on site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Detailed Paving Limits.docx | DOCX document | |
| Speed Zone Order 14340.pdf | ||
| 00017016_bid tab.xlsx | XLSX spreadsheet | |
| Advanced flagging sample layout.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Sheet1
| REQUEST FOR BID AND RESULTING WORK ORDER |
| On-Call Region 2 Paving |
| INSTRUCTIONS: ODOT will fill in all information below except Contractor Information, Work Order Number (to be added upon award of Work Order), and pricing. ODOT will provide a list of bid items and their estimated quantities. Contractor must complete the Contractor Information section, including a signature, and insert unit and total prices for all bid items. Contractor must submit its bid by uploading the completed Request for Bid/Work Order form to the Attachments tab for the project in OregonBuys and entering the total bid price on the Items tab. |
| This request for bid and any resulting work order are subject to the domestic preference requirements of ORS 279C.303. See Project Specific Requirements section below for additional information. | |
| Request for Bid Number: S-73000-00017016 | Work Order Number: |
Issue Date: 5/21/2026 Bid due date and time: 6/4/2026 2:00 pm
Project Name: I5 Intermittent Inlay Paving MP199.31-203.55
Project description (include milepoint locations): 2" Inlay paving on I5 in the NB and SB directions around the Coburg exit (MP199). Review attached document for more information on paving extents. Ramp closures require a minimum of 14 days mobility notice (minimum 14 days from when ODOT submits the notice to when contractor can start work). Overlay BR08171 at MP200.50NB, saw and seal joints. All project limits are painted in the field. ODOT has received a regulated speed reduction of 55 MPH for this project, and we are working on an agreement with OSP for a trooper to be on site. Traffic control to still be designed for a 65 MPH zone, and include the the additional signage for the regulated speed reduction found in the attached files.
| ODOT Project Manager Name and Phone number: Cody Stone 503-953-6334 |
| ODOT Project Manager Billing Address (may be an email): Cody.Stone@ODOT.Oregon.gov |
ODOT Site Representative (if different than ODOT Project Manager):
Required Completion Date: Sep 30, 2026
CONTRACTOR INFORMATION
Contractor (COMPANY) Legal Name:
Address:
Contact Person: Email:
Phone: CCB #:
Contractor's On-Call Region 2 Paving Price Agreement Number: PO-73000-
Contractor’s signature below indicates its firm offer to provide the Services described in this Work Order in accordance with all terms, conditions, and specifications contained in the Price Agreement referenced above, and any additional specifications contained within this Work Order and its attachments. The Work Order is not effective until it is signed by ODOT's Procurement Authority, and ODOT issues a notice to proceed.
Contractor Signature: Date:
| ODOT Signature (Procurement Authority): | Date: |
| ANTICIPATED WORK ITEMS (PAY ITEMS) | |
| This Work Order indicates an estimate of services/quantities required. Payment to Contractor will be made based on actual quantities provided/performed: |
| Item | Description | Est. Qty. | Unit | Unit Price | Total Price |
| 1 | Mobilization | 1 | LS | $ - 0 | |
| 2 | Temporary Work Zone Traffic Control, Complete | 1 | LS | $ - 0 | |
| 3 | Pollution Control Plan | 1 | LS | $ - 0 | |
| 4 | Cold Plane Pavement Removal, 2" Deep | 51,462 | SQ YD | $ - 0 | |
| 5 | Level 4, 1/2" Dense ACP Mixture (PG70-22ER) | 5,790 | TON | $ - 0 | |
| 6 | Thermoplastic, Extruded or Sprayed, Grooved, Non-Profiled | 41,461 | FOOT | $ - 0 | |
| 7 | Mono-Directional White Type IAR Markers, Recessed | 783 | EACH | $ - 0 | |
| $ - 0 | |||||
| PROJECT SPECIFIC REQUIREMENTS |
X This project requires compliance with the domestic preference requirements of ORS 279C.303. Contractor shall comply with Price Agreement Exhibit A - State Buy America Provisions.
X This project requires payment of the following prevailing wage rates, which are available online at http://www.oregon.gov/boli/WHD/PWR/Pages/pwr_state.aspx:
The “PREVAILING WAGE RATES for Public Works Contracts in Oregon” dated January 5, 2026 and as amended April 5, 2026
| County where the work will be performed: Lane | |
| X | The following attachments are incorporated into this Request for Bid and any resulting Work Order: |
Detailed Paving Limits.docx Speed Zone Order 14340.pdf Advanced flagging sample layout.pdf
X One or more traffic lanes may be closed when allowed, shown, or directed during the following periods of time:
Night work only - 8:00 PM to 6:00 AM
X Portable Changeable Message Signs (PCMS) shall be placed a minimum of 7 days in advance of any ramp or lane closure to alert the public of the closure. The location of the PCMS and the message on the PCMS shall be submitted to the Project Manager as part of the Contractor’s proposed TCP.
Traffic will be allowed on the cold planed surface up to ____ calendar days after removing the existing surface. Sweep and clean the cold planed surface before opening to traffic.
COMMENTS & SPECIAL INSTRUCTIONS: