00015373_RFP.docx

DOCX document 141 KB Posted

Attached to
I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services
Solicitation number
S-73000-00015373
Issued by
Oregon

About this file

This Request for Proposal (RFP) is issued by the Oregon Department of Transportation (ODOT) for Construction Cost Verification and Audit Services related to the I-5 Rose Quarter Improvements Project, a construction manager/general contractor (CM/GC) contract in Portland, Oregon. The Project addresses safety and congestion issues on a 1.8-mile segment of Interstate 5 between Interstate 405 and the Morrison Bridge, with major elements including freeway pavement rehabilitation, auxiliary lane extensions, highway cover construction, bridge modifications, and multimodal improvements to local streets. ODOT seeks one contract award for cost verification and audit services, including reviews and validations of Project records to ensure contract costs are allowable, properly allocated, and reasonable. The anticipated initial contract term is two years with potential extensions up to ten years. A virtual pre-proposal conference is scheduled for October 29, 2026, at 9:00 AM Pacific Time. The proposal submission deadline, opening date, and award timeline are specified in OregonBuys; the RFP protest period ends seven calendar days prior to the bid opening date. For Phase 1A Early Work Amendment services, ODOT anticipates one interim financial verification report and one final financial verification report, with the consultant potentially authorized for multiple construction packages simultaneously as the project progresses.

Proposers must be registered vendors in OregonBuys and must meet minimum qualifications including Oregon Board of Accountancy registration, five years in business, experience performing construction accounting cost verification on projects exceeding $50 million, and expertise in contractor internal cost verification and construction dispute claims. Key personnel must hold a Certified Public Accountant (CPA) license and Certified Construction Industry Financial Professional (CCIFP) certification. The Price Proposal evaluation awards 15 points to the lowest bidder, 10 points to the second lowest, and 5 points to the third lowest total labor cost for primary staff, with no other proposers receiving price points. Total evaluation is based on 160 possible points: Project Understanding and Approach (25 points), Key Personnel (20 points), Completed Projects and References (30 points), Proposed Statement of Work (60 points), and Sample Final Audit Report (10 points). The Project is funded through a combination of state and federal sources, with Phase 1A allocated $93,000,000 and Phase 1B allocated $146,500,000. The contract will be negotiated on scope of work, pricing, methods of compensation, and expiration date. No set-asides for small businesses, minority-owned businesses, or other protected classifications are established in this solicitation.

View the file

Other files

File Type Posted
00015373_Att K_CMGC Contract Articles.pdf PDF
00015373_Att G_ResponsibilityInquiry.docx DOCX document
00015373_Att E_Price Proposal.xlsx XLSX spreadsheet
00015373_Att H_Key Person Resume.docx DOCX document
00015373_Att D_Completed Projects and References.docx DOCX document
00015373_Att C_Proposer Info-Cert.docx DOCX document
00015373_Att A_SampleContract.docx DOCX document
00015373_Att B_DisclosureExemptionCert.docx DOCX document
00015373_Att L_Project Cost Components.pdf PDF
00015373_Att I_AcronymsTermsDefinitions.docx DOCX document
00015373_Att J_Construction Phases.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

State of Oregon

Oregon Department of Transportation Request for Proposal (“RFP”) RFP TITLE: I-5 Rose Quarter IMPROVEMENTS CM/GC Contract CONSTRUCTION Cost verification and Audit Services RFP/Bid Solicitation Number: S-73000-00015373 Project-Specific Contract for Personal Services Date of Issue: See “Available Date” for this RFP in OregonBuys Opening Date and Time: See “Bid Opening Date” and time for this RFP in OregonBuys.

Purchaser/Single Point of Contact: See “Purchaser” and “Info Contact” for this RFP in OregonBuys.

Notes:

· OregonBuys: This RFP is advertised as a “Bid Solicitation” in the OregonBuys web-based eProcurement system (https://oregonbuys.gov/bso/). See RFP section 1.3 – OregonBuys for information regarding vendor registration and terminology used in OregonBuys platform.

· Hyperlinks: This document must be viewed electronically to access files, forms, provisions or other documents provided via hyperlinks within this RFP.

· Accessibility: The Oregon Department of Transportation is committed to complying with all statutory requirements to ensure that it is providing information that is more accessible to people with disabilities, as required by Section 508 of the Rehabilitation Act of 1973, as amended (29 U.S.C. 794d), and 36 C.F.R. 1194 Appendix A. This includes information regarding the solicitation process. Please contact the Single Point of Contact (“SPC”) identified in OregonBuys (see “Purchaser” and “Info Contact”) to request reasonable accommodation for access, due to a disability, to information related to this solicitation, or the solicitation process, or both. Accommodation requests must be received by the SPC 3 business days prior to the Proposal Submission Deadline (see “Bid Opening Date” and time in OregonBuys).

· Non-Discrimination: Agency, in accordance with the Title VI of the Civil Rights Act of 1964, 78 Stat. 252. 42 U.S.C. 2000d to 2000d-4 and Title 49, Code of Federal Regulations, Department of Transportation, Subtitle A, Office of the Secretary, Part 21, Nondiscrimination in Federally-Assisted programs of the Department of Transportation issued pursuant to such Act, hereby notifies all Proposers that it will affirmatively ensure that all business enterprises will be afforded full opportunity to submit proposals in response to this solicitation and will not be discriminated against on the grounds of race, color, sex, or national origin in consideration for an award.

RFP/Bid Solicitation 73000-00015373;

I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services

DAS Version 4.5 –ODOT Form S011-G050823 Page 4 of 33 Table of Contents

SECTION 1:GENERAL INFORMATION4
1.1SERVICES SOUGHT4
1.2SCHEDULE5
1.3OREGONBUYS6
1.4RFP ATTACHMENTS7
1.5PURCHASER/SINGLE POINT OF CONTACT7
SECTION 2:AUTHORITY, OVERVIEW, AND SCOPE7
2.1AUTHORITY AND METHOD7
2.2DEFINITION OF TERMS8
2.3OVERVIEW8
2.4MENU OF SERVICES12
SECTION 3:PROCUREMENT REQUIREMENTS13
3.1MINIMUM QUALIFICATIONS13
3.2MINIMUM SUBMISSION REQUIREMENTS14
3.3[ROUND 1] PROPOSAL REQUIREMENTS16
SECTION 4:[ROUND 1] SOLICITATION PROCESS17
4.1PUBLIC NOTICE17
4.2PREPROPOSAL CONFERENCE18
4.3QUESTIONS / REQUESTS FOR CLARIFICATIONS18
4.4SOLICITATION PROTESTS18
4.5PROPOSAL SUBMITTAL VIA OREGONBUYS19
4.6PROPOSAL MODIFICATION OR WITHDRAWAL19
4.7PROPOSAL DUE19
4.8PUBLIC OPENING20
4.9PROPOSAL REJECTION20
4.10[ROUND 1] EVALUATION PROCESS20
4.11[ROUND 1] POINT AND SCORE CALCULATIONS23
4.12[ROUND 1] RANKING OF PROPOSERS24
4.13NEXT STEP DETERMINATION24
4.14ADDITIONAL ROUNDS (Optional at Agency’s discretion)24
4.15SCORING AND RANKING OF PROPOSERS FOR SUBSEQUENT ROUNDS25
SECTION 5:AWARD AND NEGOTIATION25
5.1AWARD NOTIFICATION PROCESS25
5.2INTENT TO AWARD PROTEST25
5.3APPARENT SUCCESSFUL PROPOSER SUBMISSION REQUIREMENTS26
5.4CONTRACT NEGOTIATION28
SECTION 6:ADDITIONAL INFORMATION29
6.1COMMITMENT TO DIVERSITY, EQUITY, AND INCLUSION29
6.2CERTIFIED FIRM PARTICIPATION29
6.3GOVERNING LAWS AND REGULATIONS29
6.4OWNERSHIP/PERMISSION TO USE MATERIALS29
6.5CANCELLATION OF RFP; REJECTION OF PROPOSAL; NO DAMAGES.29
6.6COST OF SUBMITTING A PROPOSAL30
6.7STATEWIDE E-WASTE/RECOVERY PROCEDURE30
6.8RECYCLABLE PRODUCTS30

GENERAL INFORMATION

SERVICES SOUGHT

The State of Oregon, acting by and through the Department of Transportation, (“Agency” or “ODOT”), is issuing this Request for Proposal for Personal Services under the provisions of ORS 279B.060 for Construction Cost Verification and Audit Services (the “Services”) for the I-5 Rose Quarter Improvements Project (the ”Project”) Construction Manager/General Contractor Contract (“CM/GC Contract”).

OAR 137-049-0690(5)(f) requires that CM/GC cost reimbursements shall be made subject to final audit adjustment, and the Contract contains an audit process “to ensure that Contract costs are allowable, properly allocated and reasonable. Services will include reviews, validations, and audits of Project records in accordance with CM/GC Contract Article 10 Accounting Records (Attachment K). Additional details on the anticipated Scope of the Services are included in the Menu of Services (RFP section 2.4).

The CM/GC Contract utilizes the “Open-Book Process” as a collaborative pricing method (see Article 6.6.7 in Attachment K). This “Open-Book Process” applies to the CM/GC (and as CM/GC is a partnership or joint venture, also to the partners or joint venture members of the CM/GC), Major Subcontractors, Subcontractors and any other party, person or entity not competitively selected in accordance with Article 9.3.8. The Process is required and repeated when the CM/GC submits its preliminary GMP and final GMP proposals. It is also required for Early Work Amendments and Amendments and Change Orders to Early Work Amendments and the GMP Amendment.

Article 10.2 of the CM/GC Contract (Periodic and Final Reviews, Validations, and Audits) provides that the Agency (with the assistance of its representatives) “will, at its discretion, perform periodic reviews and audits of the Project Records, at such times and for such purposes as the Agency deems appropriate in its discretion, including but not limited to; reviews and audits of pricing and cost breakdowns used for Early Work Amendments, the GMP Amendment and other Amendments and Change Orders, validation of assumptions and clarifications for unit prices, validation of the Actual Cost of the Work, and determination that cost reimbursements and other payments are allowable, properly allocated, and reasonable, which may result in reduction adjustments or corrections in amounts paid or to be paid.” This provision also provides for a final audit of the Project Records prior to contract closeout. The final audit is to be as provided for the periodic audits, with an “emphasis on validation of the Actual Cost of the Work and determining that cost reimbursements and other payments are allowable, properly allocated and reasonable” which may also result in “reduction adjustments or corrections in amounts paid or to be paid.”

The CM/GC Contract includes multiple Early Work Packages in advance of the Guaranteed Maximum Price (“GMP”) Amendment Package (Construction Packages). Agency anticipates the following reviews for each Construction Package:

· Construction interim financial verification report(s). Interim financial verification reports may be required by Agency semi-annually, on a percentage of complete based on costs, or on a percentage complete based on calendar progress.

· Construction final financial verification report at the conclusion of each Construction Package.

Pursuant to the CM/GC Agreement, ODOT and the CM/GC entered into the Phase IA Early Work Amendment in July of 2025.

For purposes of the Phase IA Early Work Amendment, ODOT plans to complete one construction interim financial verification report and one final financial verification report at the conclusion of construction. This is reflected in Attachment G of Phase IA Early Work Amendment, which includes a Clarification and Assumption that there will be two audits – one interim and one at completion. The resulting contract will include these two reviews.

Entities subject to Open-Book Process in Phase 1A include, but are not limited to, the following:

•Joint Venture members of CM/GC (Hamilton/Sundt Joint Venture)
•Phase 1A Major Subcontractor: Raimore Construction

Agency anticipates adding additional interim and final reviews for subsequent Early Work Amendment Packages and the GMP Construction Package. Subsequent Services will be authorized only by written Contract amendment with all required approvals and signatures. Depending on the progress of the Project, the Consultant may be authorized to perform Services for multiple Construction Packages simultaneously. Additionally, Agency may add additional reviews related to the Preconstruction phase currently in progress.

The initial term of the Contract is anticipated to be 2 years with potential extensions for added Services up to an estimated cumulative of 10 years.

Agency and apparent successful Proposer shall negotiate the detailed tasks, deliverables, schedule, and costs for Services described in the scope of Services.

Agency anticipates one Contract will be awarded from this RFP.

SCHEDULE

The table below represents a tentative schedule of events. All times are listed in Pacific Time. All dates listed are subject to change. N/A denotes that event is not applicable to this RFP.

Event
Schedule
Pre-Proposal Conference
October 29, 2026, at 9:00 AM (see RFP section 4.2)
Questions / Requests for Clarification Due
10 calendar days prior to the Bid Opening Date in OregonBuys for this RFP
Answers to Questions / Requests for Clarification Issued (approx.)
Estimated 7 calendar days prior to Bid Opening Date in OregonBuys for this RFP
RFP Protest Period Ends
7 calendar days prior to the Bid Opening Date in OregonBuys for this RFP
Opening (Proposal Due)
See Bid Opening Date and time in OregonBuys for this RFP
Opening of Proposals
See RFP section 4.8
Presentations, Demonstrations, Interviews, or follow-up questions, if conducted
Estimated 2 weeks following Bid Opening Date in OregonBuys for this RFP, if conducted
Issuance of Notice of Intent to Award
Estimated 4 weeks following Bid Opening Date in OregonBuys for this RFP
Award Protest Period Ends
7 calendar days after issuance of Notice of Intent to Award

1.1 OREGONBUYS

Registration Requirement; OregonBuys User Guides.

All vendors must be registered in OregonBuys to do business with the state. Registration is free. To create a vendor account, click the blue “Register” button in the top right corner of the OregonBuys website: https://oregonbuys.gov/bso. For registration assistance see vendor registration guidance (https://www.oregon.gov/das/ORBuys/Documents/SupplierRegistrationGuide.pdf). Vendors are responsible for ensuring that their vendor information is current and correct in OregonBuys. ODOT will accept no responsibility for incorrect vendor information.

See OregonBuys User Guides located on OPO’s Contracting with ODOT page (https://www.oregon.gov/odot/Business/Procurement/Pages/HowTo.aspx) for quick reference information regarding common questions from vendors when using OregonBuys.

Crosswalk of Terms used In OregonBuys

Terms used in OregonBuys
Definition
Amendment
“Addendum” or “Addenda”, as defined in OAR 125-246-0110; or any form of notice associated with the solicitation, such as intent to award, cancellation, etc., as set forth in the Amendment.
Bid Opening Date
“Closing” as defined in OAR 137-046-0100(5). In OregonBuys it is the deadline for submitting Quotes (Bids, Proposals or other required responses) required by a Bid Solicitation.
Bid Solicitation
Any form of solicitation: Request for Proposal, Invitation to Bid, Request for Quote, Request for Information, etc., including notices (sole source notice, intent to participate, etc.). Each Bid Solicitation has a separate page and ID number in OregonBuys.
Change Order
A formal change to an existing MBPO, Release Requisition, or project-specific Purchase Order.
Master Blanket Purchase Order (“MBPO”)
Any form of parent contract/agreement (i.e. price agreement, on-call contract, etc.) that allows for purchases/releases via an ordering instrument during the term specified in the parent contract/agreement.
Purchase Order
Any form of project-specific contract (not awarded under an existing MBPO)
Quote
Any form of offer submission by vendors; i.e., Bids, Technical Proposals, Price Proposals, or any other type of offer required by a Bid Solicitation.
Release Requisition
Any form of ordering instrument used under an MBPO; i.e. Purchase Order, Work Order Contract, etc.
Vendor
Any form of business entity registered in OregonBuys. Only registered vendors are eligible to submit a Quote and enter Purchase Orders, MBPOs, or Release Requisitions pursuant to Bid Solicitations advertised in OregonBuys.

RFP ATTACHMENTS

In addition to the provisions set forth and linked within this RFP, this RFP incorporates by this reference the information published or linked on the OregonBuys Bid Solicitation page for this RFP, including but not limited to:

· Details entered in the Header Information section;

· All RFP attachments, “Amendments” (if any), and any other files linked in the File Attachments and Form Attachments subsections; and

· Information, if any, entered in the “Questions” and “Item Information” sections.

PURCHASER/SINGLE POINT OF CONTACT

The single point of contact for this RFP is identified as the “Purchaser” along with Purchaser’s “Info Contact” in OregonBuys.

AUTHORITY, OVERVIEW, AND SCOPE

AUTHORITY AND METHOD

Agency is issuing this RFP pursuant to its authority under ORS 279A.050(3).

Agency is using the Competitive Sealed Proposal method, pursuant to ORS 279B.060 and OAR 137-047-0260. Agency may use a combination of the methods for Competitive Sealed Proposals, including optional procedures: a) Competitive Range; b) Discussions and Revised Proposals; c) Revised Rounds of Negotiations; d) Negotiations; e) Best and Final Offers; and f) Multistep Sealed Proposals.

DEFINITION OF TERMS

For the purposes of this RFP, capitalized words are defined in OAR 125-246-0110, or as defined in Acronyms, Terms and Definitions (Attachment I) and in RFP section 1.3.2 - Crosswalk of Terms used In OregonBuys.

OVERVIEW

Project History. The Project is the culmination of decades of planning and collaboration between ODOT, the City of Portland, and community partners to identify how to reconnect the local community while improving safety and congestion issues in the Project Area (defined later in Project Physical Description) and on Interstate 5 (“I-5”). It is an infrastructure Project directed to address these issues by the legislature in House Bill 2017 and in alignment with the City of Portland NE Quadrant Plan and Metro Regional Transportation Plan. Graphics and written descriptions are available on the Project website.

The original construction of I-5 in the historic Lower Albina neighborhood continues to have a negative impact on generations of Black Portlanders. The placement of I-5 caused lasting harm when members of the historic Albina community lost their homes, businesses, and community places to make way for the highway in the 1950s and 1960s. Despite the cultural damage caused by the highway, the Black community near this area remains resilient and focused on the future. The Project represents a generational opportunity to make a positive impact for the community harmed by the original construction of I-5.

Applicable Law Specific to CM/GC:

ORS 279C.337 (Procurement of construction manager/ general contractor services) OAR 137-049-0690 (Construction Manager/General Contractor Services (“CM/GC Services”) OAR 137-049-0660 (RFP Pricing Mechanisms) 23 CFR Part 635 Subpart E (Construction Manager/General Contractor (CM/GC) Contracting) Project Funding. Combination of State and Federal. Current funding for construction of the Project is as follows:

RQ Phase 1A is $93,000,000 (Key No. 23682), and RQ Phase 1B is $146,500,000 (Key No. 23672).

Project Description. The Project is located in Portland, Oregon, along the 1.8-mile segment of Interstate 5 (“I‑5”) between Interstate 405 (“I-405”) to the north (“N”) (milepost 303.2) and the Morrison Bridge exit (US 26 and 99E) to the south (“S”) (milepost 301.4). The Project also includes the interchange of I‑5 and northeast (“NE”) Broadway and NE Weidler Streets (the “Broadway/Weidler Interchange”) and the surrounding transportation network, from approximately NE Hancock Street to the N, N Benton Street to the west (“W”), NE Multnomah Street to the S, and NE Second Avenue to the east (“E”).

Agency completed the Revised Supplemental Environmental Assessment (“RSEA”) for the Project to meet the National Environmental Policy Act (“NEPA”) requirements. FHWA issued a FONSI on March 6, 2024, for the Project RSEA.

Agency expects that the Project will be constructed under traffic, with no general reduction in the number of travel lanes during construction, except during limited times. This effort will require complex construction staging and mitigation of constructability issues associated with the Project. The Major Project Elements include:

· Extending auxiliary lanes

· Freeway pavement rehabilitation

· Widening highway structures

· Constructing new highway covers

· Cutting and filling walls

· Reconstructing surface streets

· Constructing Americans with Disabilities Act (“ADA”) ramps, sidewalks, multi-use paths

· Constructing drainage and water quality improvements

· Installing traffic signals and ramp meters

· Staged construction The Project Includes the following Improvements:

I‑5 Mainline Improvements. I‑5 mainline improvements include the construction of auxiliary lanes and full shoulders between I-84 to the S and I‑405 to the N, in both the northbound (“NB”) and southbound (“SB”) directions as follows:

· Extending the existing SB auxiliary lane and add full or partial width, as determined by Agency, shoulders from N Greeley Avenue, between the Elliot School Viaduct (SB exit to NE Broadway) and the Morrison Bridge and the southeast (“SE”) Portland/Oregon Museum of Science and Industry (“OMSI”) exit ramp

· Adding new NB auxiliary lane and full shoulders from the I-84 westbound (“WB”) to I-5 NB entrance ramp to the N Greeley Avenue exit ramp

· Adding one continuous highway cover over I-5 replacing the existing N Flint Avenue, NE Weidler Street, NE Broadway, N Williams Avenue, and the N Vancouver Avenue overcrossings.

Broadway/Weidler Interchange Improvements. The Broadway/Weidler Interchange improvements address connections between I‑5, the interchange and the local street network; they include the following:

· Relocating the I-5 SB exit ramp from Broadway to new connections at N Williams Avenue and to NE Weidler Street

· Widening the I-5 NB to NE Weidler Street exit ramp

Multimodal Improvements to Local Streets

· Extending NE Hancock Street west, across the new highway cover, connecting it to N Flint Avenue.

· Connect N Flint Avenue across I-5 from NE Tillamook Street to N Hancock Street and terminate it at N Broadway.

· Remove the NE Hancock Street overcrossing of I-5 from N Williams Avenue to N Dixon Street and extend across I-5 and reconnect to NE Hancock Street west of N Flint Avenue as part of the expanded highway cover.

· Adding a new bicycle and pedestrian bridge crossing over I-5 to connect NE Clackamas Street near NE 2nd Avenue to the N Williams Avenue, N Ramsay Way/N Wheeler Avenue area

· Upgrading existing bicycle facilities on NE Broadway and NE Weidler Street within the Project area with wider, separated bicycle lanes

· Update existing bicycle facilities on N Williams Avenue, converting the on-road bike lane to a protected bike lane, with a transition to the existing on-road bike lane north of NE Broadway

All of the Bridges listed below are included in the Project.

Bridge Removal. The following Bridges are expected to be removed with the Project:

Bridge No.Bridge NameMilepost
08575NE Weidler StreetMP 302.29
08575QN Williams AvenueMP 302.33
08575RNE BroadwayMP 302.35
08574N Vancouver AvenueMP 302.43
08573N Flint StreetMP 302.53

Bridge Widening (I-5). I-5 bridges are expected to be widened or may be widened, as determined by Agency:

Bridge No.Bridge NameMilepost
S8588EHwy 1 SB over UPRRMP 301.70
N8588EHwy 1 NB over UPRRMP 301.70
08583Hwy 1 over NE Hassalo St & NE Holladay StMP 301.99 (**)
08782AElliot School Viaduct, Hwy 1 …..MP 302.65 (*)
N8958AFremont Viaduct, Hwy 1 NBMP 302.99
S8958AFremont Viaduct, Hwy 1 SBMP 302.99
08958EHwy 1 NB to Hwy 61 SB over Conn (E Fremont Intchg)MP 303.06
16358NB Hwy 1 Conn to N Greely Ave over City Street, (widen East)...…MP 303.04

(*) The widening of the Elliot School Viaduct will include the partial removal of an existing retaining wall and the construction of 2 new retaining walls (**) The widening of the Hwy 1 over NE Hassalo & NE Holladay St bridge will include a deck rehabilitation (either a deck overlay replacement or a full deck replacement) for the lanes and shoulders in both freeway directions

Bridge Widening (I-84). I-84 bridges expected to be widened or may be widened, as determined by Agency:

Bridge No.Bridge NameMilepost
08588CHwy 1 SB to Hwy 2 EB over Hwy 1 & Conn (Banfield Interchange) MP 0.23
08588AHwy 2 WB to Hwy 1 NB over UPRR (Banfield Interchange)MP 0.24

New Bridges. I-5 bridges expected to be constructed:

Bridge No.Bridge NameMilepost
TBDN Vancouver & NE Hancock over Hwy 1MP C302.40
TBDN Williams, NE Broadway & NE Weidler over Hwy 1MP C302.33
TBDSB Exit Ramp to Local Streets (Flyover Bridge) ………………..MP TBD
TBDPedestrian and Bike Bridge over Hwy 1 ……………….MP 302.20

Highway Cover The “Highway Cover” is an approximately 1,500 ft wide bridge that covers I-5 between the Moda Center and the Harriett Tubman Middle School. It consists of a continuous structure that carries Weidler Street over I-5 on its south end, and Flint Street over I-5 on its north end. Possessing between 2 to 4 spans, the highway cover will be designed to support various building types and heights, to be determined by Agency as part of a broader Local Public Agency-led process. As part of the Highway Cover, the southbound direction’s entrance and exit ramps for the Broadway / Weidler interchange will be located south of the highway cover. The southbound exit ramp will include a new flyover structure connecting I-5 southbound traffic to eastbound Weidler Street. The northbound direction’s entrance and exit for the interchange will approximately remain at its current location.

CM/GC Contract The Project is being constructed using the CM/GC delivery method, by which the Owner (with the assistance of the Project team) may select certain elements to proceed to design and construction as “early work” packages prior to the execution of the GMP Amendment. An Early Work Package (“EWP”) that has construction funding and has been included in the Statewide Transportation Improvement Program (“STIP”) is also referred to as a “Construction Package.” The final Construction Package for all remaining Project Elements not selected for early work packages will be included in the GMP Amendment to the CM/GC contract, which upon execution, will also be a construction package.

The Project initially contemplated development of design documents for 3 early work packages (EWP(s) A, B, and C), and the Main Construction Package (“MCP”). Due to available funding, Agency reassembled and revised EWP(s) A, B, and C, and the MCP. As a result, the 3 identified Construction Packages that have been developed with some, but not all elements from EWP(s) A, B & C and the MCP are as follows:

· Early Work Package Phase 1A – Stormwater work near I-405 (scope previously in EWP A) and widening on the west side of the Southbound (SB) Bridge #S8588E on the segment of I5 SB exit ramp to I-84 eastbound, seismic retrofits and bridge deck overlay replacements of #S8588E and #N8588E, and installation of traffic sign bridge “Site Inclusive” at MP 301.9 (scope previously in EWP B).

Schedule Assumptions for EWA 1 (Phase 1A) Construction Package:

It is anticipated that the Construction Contractor will receive Notice to Proceed (“NTP”) for EWA 1 (Phase 1A) no later than July 24, 2025, in accordance with the CM/GC General Provisions, Section CMGC130 and Article 3.2 of the CM/GC Contract (provided by Agency).

The anticipated duration for POR Services for EWA 1 (Phase 1A) is JULY 2025 – JULY 31, 2027 (24 months = 118 work weeks).

· Early Work Package Phase 1B - Widening of Bridge #08583 (from EWP B) and construction of multiple retaining walls (from EWP B). Construction of new sign structures, paving, drainage, and ITS. This phase also includes LRT design (from EWP B). Design for this package is part of Key Number (“KN”) 19071. Construction of this package is per KN23672.

· Schedule Assumptions:

Construction NTP in summer 2027

· Early Work Package Broadway to Weidler (“B/W”) Phase 1 (also known as Early Work Package Phase 1C or “Phase 1C”) – Construction of portions of the highway cover including Broadway and Weidler, reconstruction of Williams Avenue, Broadway, Weidler local streets, extends I-5 NB auxiliary lane and I-5 SB auxiliary and shoulders through the highway cover area (from MCP), and construction of multiple retaining walls (from MCP). Construction of new sign structures, ITS, and FLS systems to support the highway cover and new auxiliary lanes. This package also includes streetcar design (from MCP). Design and ROW for this package is part of KN19071 and the RCN grant. This work does not have a programmed Construction phase and will be assigned a KN when added to the STIP.

· Schedule Assumptions:

ROW acquisition to commence Q3 2026 Construction planned for Q1 2029

Project Elements that are not included in the Early Work Packages described above remain part of the Project and may also be included as “Unassigned Design Elements.” All Project Elements not selected for an Early Work Package will become part of the Final GMP Amendment.

Each added Early Work Package, construction package, or GMP Amendment package milestone will be authorized only in the Agency’s sole discretion as directed by the APM.

MENU OF SERVICES

Consultant shall provide the CM/GC Construction Contract Cost Verification Services for Agency in order to verify the actual costs of construction and to otherwise ensure the Contract costs are allowable, properly allocated and reasonable. These services include reviews, validations and audits of Project records in accordance with the CM/GC Contract and construction and preparation of resulting reports and findings. Generally, the Services include the following:

· Cost Verification: Review Project records (including invoices, labor documents and timesheets, and vendor/subcontractor billings) in accordance with applicable Contract documents (including Clarifications and Assumptions, Cost Breakdowns, Change Orders and Administrative Change Orders (Subsection 6.12.3) to validate actual costs paid match claimed amounts and are accounted for appropriately.

· Allowable vs. Unallowable Costs: Review contract terms to ensure charges, markups, and fees are accounted for appropriately, allowable, and not otherwise double-billed inside cost-reimbursable lines.

· Open Book Subcontractors: Audit open-book pricing for subcontractors subject to open book pricing

· GMP and Early Work Reconciliation.

Consultant will be expected to perform the following for each Report:

· Implement a strategy and schedule for management of its services and deliverables to effectively manage coordination between Agency and Consultant.

· Implement a financial verification and construction cost audit strategy for each review.

· Attend a “kick off” meeting with Agency and others as appropriate; hold and attend periodic meetings as needed throughout and at the conclusion of each review.

· Obtain all necessary Project records and perform non-site and off-site procedures to fully accomplish programmatic objectives.

· Evaluate the adequacy of the Construction Manager/General Contractor (CM/GC) internal controls and overall compliance.

· Make recommendations for process improvement or clarity.

· Update and revising reports based on information received or Agency’s request.

The following Menu of Services listed below represents an initial, non-comprehensive description of services that may be included in the resulting Contract:

· Construction interim financial verification report(s) for Early Work Packages. Interim financial verification reports may be required by Agency semi-annually, on a percentage of complete based on costs, or on a percentage complete based on calendar progress.

· Construction final financial verification report at the conclusion of each Early Work Package.

· Construction interim financial verification report(s) for the GMP Amendment Construction Package. Interim financial verification reports may be required by Agency semi-annually, on a percentage of complete based on costs, or on a percentage complete based on calendar progress.

· Construction final financial verification report at the conclusion of the GMP Amendment Construction Package.

· Preconstruction Phase Financial Audit.

· Meetings with and presentations to Owner to discuss Consultant’s reports and findings.

· Additional Services Contingency Tasks. As requested by the Agency, perform additional auditing or financial services that enhance the value of the financial verification reports, including assessments, recommendations, support and consultations.

Agency reserves the right to modify the Menu of Services as necessary to meet Agency’s needs. Agency will negotiate the final Statement of Work with the successful Proposer based on the Proposed Statement of Work submitted per Section 4.10.2.4.

RFP Attachments J, K, and L are provided for informational purposes only and may not constitute a standard, specification, or regulation in the resulting Contract. Executed copies of the CM/GC Contract, EWA, CCO and mini-CM/GC contract will be provided by Agency to the awarded Consultant, as applicable to the Services.

PROCUREMENT REQUIREMENTS

MINIMUM QUALIFICATIONS

To be considered for evaluation, Proposer must be a registered vendor in OregonBuys and Proposal must demonstrate how Proposer meets all requirements of this section. Minimum qualifications may be met by the proposing firm or its subconsultants. An authorized representative of the Proposer certifies the Proposer meets the requirements cited in this section by checking the “APPROVED” checkbox on the Proposer Information and Certification Sheet (RFP Attachment C).

Minimum Firm Requirements Proposer must meet Minimum Firm Qualifications outlined below:

Minimum Firm Qualifications:

· Registered with Oregon Board of Accountancy.

· Experience performing construction accounting cost verification of heavy-civil or transportation infrastructure construction projects over $50M.

· Experience performing verification of contractor’s internal costs, inclusive of labor, material, equipment, and subcontractors

· Experience performing cost verification of construction disputes and claims.

· Experience providing litigation support related to construction accounting.

· Minimum 5 years in business.

Desired Firm Qualifications:

Experience performing these Services of the following:

· Heavy-civil or transportation infrastructure CM/GC projects.

· Joint venture or other “multi-party” organizations.

· Federal or state funded projects.

· Total project cost in addition to auditing for specific claims related issues.

Minimum Key Personnel Requirements Proposer must meet Minimum Key Personnel Qualifications outlined below:

· Certified Public Accountant (“CPA”) license with the Oregon Board of Accountancy.

· Certified Construction Industry Financial Professional (CCIFP) issued by the Construction Financial Management Association (CFMA).

Proposer shall provide the information of the Key Person(s) in Appendix 1 of Attachment C – Proposer Information and Certification Sheet that meet these requirements and will provide services under the awarded Contract.

MINIMUM SUBMISSION REQUIREMENTS

[ROUND 1] Proposal Submissions To be considered for evaluation, Proposal must contain each of the following elements (further detailed in Proposal Requirements section below):

Proposer Information and Certification Sheet (Attachment C) Disclosure Exemption Certification (Attachment B) – submit only 1 copy if applicable - see Proposal Format and Quantity section below) Price Proposal Form (Attachment E) Technical Proposal (RFP section 3.3.5):

· Written responses and requested materials (RFP section 4.10.2)

· Key Person Resumes (Attachment H)

· Completed Projects and References (Attachment D) See RFP section 5.3 for submittal requirements of selected firm after award notice.

Proposal Page Limits Proposal is limited to 25 pages. If a Proposer submits a Proposal exceeding this limit, or any other specified page limit (i.e., organizational chart, resumes, and completed projects and reference forms), Agency will consider the pages up to that allowable number and discard all subsequent pages.

Unless otherwise specified, one page is defined as: one side of a single 8-1/2" x 11" page that meets the font size requirements stated below. Any page over this size will be counted as 2 pages. Any page, partial page, tabs, indexes or table of contents with substantive text, tables, graphics, charts, resumes, etc., will be counted as 1 page. Cover letters submitted with the Proposal will be counted in the page limit but will not be forwarded to the evaluation committee Proposals must use 12-point minimum font size for the substantive text (including text in tables) with the following exceptions which must use an 11-point minimum font size:

· Proposer Information and Certification Sheet (Attachment C);

· Conflict of Interest form(s) (if required, see Attachment C);

· Key Person Resumes (Attachment H);

· Completed Projects and References (Attachment D); and

· Organization chart (RFP section 4.10.2.2).

Proposers may use their discretion for the font size of other materials that do not include substantive text (i.e., graphics, picture or graphics captions) and the sample final audit report (RFP section 4.10.2.5).

The following items do not count toward the page limit:

Disclosure Exemption Certification (Attachment B) Proposer Information and Certification Sheet (Attachment C), including Conflict of Interest form(s) Price Proposal (Attachment E) Sample Final Audit Report (RFP section 4.10.2.5) Responsibility Inquiry form (Attachment G); not required to be submitted with Proposal (RFP section 5.3.4) Proposal Format Proposal should follow the format and reference the sections listed in the Proposal Requirements (RFP section 3.3). Responses to each section and subsection should be labeled to indicate the item being addressed.

· Price information must be submitted via OregonBuys (see RFP section 3.3.3 for detailed submittal requirements).

· Technical Proposal must be submitted via OregonBuys in Portable Document File (.pdf) format (see RFP section 3.3.5 for detailed submittal requirements).

· All other required submittal items must be submitted via OregonBuys in Portable Document File (.pdf) or Microsoft Word (.docx) format.

If Proposer believes any of its Proposal is exempt from disclosure under Oregon Public Records Law (ORS 192.311 through 192.478), Proposer shall submit a completed and signed Disclosure Exemption Certification (Attachment B) and a fully redacted version of its Proposal, clearly identified as the redacted version.

Electronic Submittal Provisions

3.2.4.1.Proposers shall make reasonable efforts to minimize the file size of attachments (for tips on reducing file size, see: How to reduce PDF file size (https://www.wikihow.com/Reduce-PDF-File-Size); How to reduce the size of Word documents that contain images (https://www.howtogeek.com/255379/how-to-reduce-the-size-of-microsoft-office-documents-that-contain-images/).
3.2.4.2.Agency reserves the right to reject any submittal that is unreadable.
3.2.4.3.Agency reserves the right to award the Contract solely on the electronically submitted Proposal; however, upon Agency’s request, the apparent successful Proposer shall promptly submit its complete original signed Proposal.
3.2.4.4.Per OAR 731-146-0150(4), in the event of a failure of an Electronic Procurement System or email system that interferes with the ability to submit electronic Proposals, to protest, or to otherwise participate in the procurement, Agency may cancel the procurement or may extend the date and time of receipt of electronic Proposals by providing notice of the extension immediately after the Electronic Procurement System becomes available.
3.2.4.5.By submitting a Proposal in response to this RFP, Proposer (and if selected for award, also as the “Contractor” or “Consultant”) agrees with Agency that Signatures, and other forms of authorized representative certification, showing on documents submitted via OregonBuys or email are “Electronic Signatures” under ORS Chapter 84 and bind the signing party and are intended to be and can be relied upon by the parties.

[ROUND 1] PROPOSAL REQUIREMENTS

Proposal must address each of the items listed in this section and all other requirements set forth in this RFP. Proposer shall describe the Services to be performed. A Proposal that merely offers to provide the Services as stated in this RFP may be considered non-Responsive to this RFP and will not be considered further.

Proposal should not include extensive artwork, unusual printing or other materials not essential to the utility and clarity of the Proposal. Do not include marketing or advertising material in the Proposal, unless requested. Proposal should be straightforward and address the requests of the RFP. Proposal containing unsolicited marketing or advertising material may receive a lower evaluation score if required information is difficult to locate.

Proposer Information and Certification Sheet Proposer shall complete and submit the Proposer Information and Certification Sheet (Attachment C), with the “APPROVED” checkbox marked to certify approval of the Proposal and compliance with Oregon Tax Laws by a duly authorized representative empowered to bind the Proposer. Failure to demonstrate compliance with Oregon Tax Laws may result in a finding of non-Responsibility.

Also, Proposer shall mark the appropriate box for item 10 regarding Conflict of Interest (“COI”) disclosures. If disclosures are required for Proposer or any subs, use COI Disclosure Form(s) linked on Attachment C to make the disclosures.

References Proposer shall submit references from current or former client firms for similar projects as specified in RFP section 4.10.2.3 Evaluation Item 3 – Completed Projects and References.

Price Proposal Proposer shall submit Attachment E – Proposed Fully-Burdened Billing Rates as a separate file uploaded via the Attachments tab for this RFP in OregonBuys. Provide the fully burdened rates (inclusive of labor cost, overhead and profit) for key staff proposed to work under the prospective Contract (including subcontractor key staff, if applicable).

· List the names, classifications, duties and fully burdened rate for each of the key staff proposed.

· Include the estimated hours of overall budget for each of the key staff to provide the Interim and Final Verification Reports based on the Proposed Statement of Work submitted per Section 4.10.2.4.

The total labor cost calculated on Attachment E will be used for “Price Proposal” scoring purposes only. Agency reserves the right to negotiate the final price and billing rates under this Contract with the apparent successful Proposer.

Key Persons and their Resumes Proposer shall submit resumes of key persons to be assigned to this Project as specified in RFP section 4.10.2.2 Evaluation Item 2 – Key Personnel.

Technical Proposal Proposer shall submit written responses and requested materials as specified in RFP section 4.10.2 - Evaluation Criteria.

[ROUND 1] SOLICITATION PROCESS

PUBLIC NOTICE

The RFP and attachments are published in the OregonBuys eProcurement system (https://oregonbuys.gov/bso). RFP documents will not be mailed to prospective Proposers.

Modifications, if any, to this RFP will be made by written Addenda published in OregonBuys. Prospective Proposer is solely responsible for checking OregonBuys to determine whether any Addenda have been issued. Addenda are incorporated into the RFP by this reference.

PREPROPOSAL CONFERENCE

A virtual pre-proposal conference will be held at the date and time listed in the Schedule, RFP section 1.2. Prospective Proposers’ participation in this conference is highly encouraged but not mandatory.

The purpose of the pre-proposal conference is to:

· Provide additional description of the Project;

· Explain the RFP process; and

· Answer any questions Proposers may have related to the Project or the process.

Statements made at the pre-proposal conference are not binding upon Agency. RFP requirements will only change by written addenda published in OregonBuys. Proposers may be asked to submit questions via email to the Purchaser identified in OregonBuys for this RFP.

Interested parties may participate in the virtual pre-proposal Conference by:

Microsoft Teams meeting Join: https://teams.microsoft.com/meet/264946558460139?p=pwAU4PciJoMJNUvC2b Meeting ID: 264 946 558 460 139 Passcode: dx6i3gf3

Need help? | System reference Dial in by phone +1 971-277-1965 (975956766#) United States, Portland Find a local number Phone conference ID: 975 956 766#

QUESTIONS / REQUESTS FOR CLARIFICATIONS

All inquiries, whether relating to the RFP process, administration, deadline or method of award, the intent or technical aspects of the RFP, contractual requirements, or any other provision must:

Be submitted in writing via email to the Purchaser identified in OregonBuys for this RFP. The email must include the RFP number and identify Proposer’s name and contact information;

Refer to the specific area of the RFP being questioned (i.e. page, section and paragraph number); and Be received by the due date and time for Questions/Requests for Clarification identified in the Schedule, RFP section 1.2.

SOLICITATION PROTESTS

Protests to RFP Prospective Proposer may submit a Written protest of anything contained in this RFP, including but not limited to, the RFP process, Specifications, Scope of Work, and the proposed Sample Contract. This is prospective Proposer’s only opportunity to protest the provisions of the RFP, except that Proposer may protest Addenda as provided below and Proposer may take exception to the terms and conditions of the Sample Contract marked as negotiable as set forth in the Negotiations Section.

Protests to Addenda Prospective Proposer may submit a Written protest of anything contained in the respective Addendum. Protests to Addenda, if issued, must be submitted by the date/time specified in the respective Addendum, or they will not be considered. Protests of matters not added or modified by the respective Addendum will not be considered.

Requirements for Protests All Protests must:

Be delivered via email to the Purchaser identified in OregonBuys for this RFP;

Reference the RFP number;

Identify prospective Proposer’s name and contact information;

Be sent by an authorized representative;

State the reason for the protest, including:

the grounds that demonstrate how the Procurement Process is contrary to law, Unnecessarily Restrictive, legally flawed, or improperly specifies a brand name; and evidence or documentation that supports the grounds on which the protest is based State the proposed changes to the RFP provisions or other relief sought;

Protests to the RFP must be received by the due date and time identified in the Schedule, RFP section 1.2;

Protests to Addenda must be received by the due date identified in the respective Addendum.

PROPOSAL SUBMITTAL VIA OREGONBUYS

Proposer is solely responsible for ensuring its Proposal and all required submittal items are submitted through OregonBuys in accordance with the RFP requirements before the Bid Opening Date. Proposals submitted by any other means will be rejected.

Agency is not responsible for any delays by transmission errors or delays, or for any mis-delivery for any reason. Additional information may be found in the OregonBuys Terms of Use.

PROPOSAL MODIFICATION OR WITHDRAWAL

If a Proposer wishes to withdraw or modify a submitted Proposal, Proposer must do so using the “Withdraw Quote” button in OregonBuys prior to the Bid Opening Date and time for this RFP in OregonBuys. Proposal withdrawals and modifications must be in conformance with requirements set forth in OAR 137-047-0440.

PROPOSAL DUE

A Proposal (including all required submittal items) must be received in OregonBuys on or before the Bid Opening Date and time for this RFP specified in OregonBuys.

A Proposal received after the Bid Opening Date and time is considered LATE and will NOT be accepted for evaluation.

PUBLIC OPENING

There will be no public Opening of Proposals. Proposals received will not be available for inspection until after the evaluation process has been completed and the Notice of Intent to Award is issued pursuant to OAR 137-047-0630. However, Agency will record and make available the identity of all Proposers after Opening.

PROPOSAL REJECTION

Agency may reject a Proposal for any of the following reasons:

Proposer fails to substantially comply with all prescribed RFP procedures and requirements.

Proposer has liquidated and delinquent debt owed to the State or any department or agency of the State.

Proposer fails to meet the responsibility requirements of ORS 279B.110.

Proposer makes any contact regarding this RFP with State representatives such as State employees or officials other than the Purchaser or persons authorized by the Purchaser, or makes inappropriate contact with the Purchaser.

Proposer attempts to influence a member of the Evaluation Committee.

Proposal is conditioned on Agency’s acceptance of any other terms and conditions or rights to negotiate any alternative terms and conditions that are not reasonably related to those expressly authorized for negotiation in the RFP or Addenda.

[ROUND 1] EVALUATION PROCESS

Responsiveness and Responsibility Determination Responsiveness Determination A Proposal received prior to the Bid Opening Date for this RFP will be reviewed to determine if it is Responsive to all RFP requirements including compliance with Minimum Qualifications section and Minimum Submission Requirements section. If the Proposal is unclear, the Purchaser may request clarification from Proposer. However, clarifications may not be used to rehabilitate a non-Responsive proposal. If the Purchaser finds the Proposal non-Responsive, the Proposal may be rejected; however, Agency may waive mistakes in accordance with OAR 137-047-0470.

Responsibility Determination Agency will determine if an apparent successful Proposer is Responsible prior to award and execution of the Contract. Selected Proposer(s) shall submit a signed Responsibility Inquiry form (Attachment G) following receipt of Intent to Award notice as required in RFP section 5.3.4.

At any time prior to award, Agency may reject a Proposer found to be not Responsible.

Evaluation Criteria Each Proposal meeting all Responsiveness requirements will be independently evaluated by members of the Evaluation Committee. Evaluation Committee members may change, and Agency may have additional or fewer evaluators for optional rounds of competition. Evaluators will assign a score for each evaluation criterion listed below in this section up to the maximum points available listed for each scored item.

Purchaser may request further clarification to assist the Evaluation Committee in gaining additional understanding of a Proposal. A response to a clarification request may only clarify or explain portions of the already submitted Proposal and may not contain new information not included in the original Proposal.

Evaluation Item 1 – Project Understanding and Approach Max Points: 25 Demonstrate Proposer’s clear and concise understanding of the scope of Services requested in this RFP, the approach to deliver these Services, and Proposer’s management and organizational structure for the requested Services in a visual layout or chart format.

Given the information in RFP section 2.4 and Attachment A – Sample Contract, Exhibit A – Statement of Work, Proposer shall provide the following:

· Describe how Proposer will approach delivering Services required in this RFP to include staffing, scheduling, and other elements which proved successful for the Proposer.

· Describe how Proposer’s approach will meet the needs of the Agency and the objectives described in this RFP.

· Provide an organization chart of Proposer’s team with names of Key Personnel who will be performing the Services on this Project, including all subconsultants. Indicate which members will participate in which area of the Services described in the Proposal. The organization chart may not exceed 1 page on one side of an 11” x 17” sheet and must use a minimum of 11-point font for text.

Evaluation Item 2 – Key Personnel Max Points: 20 Demonstrate Proposer’s experience and qualifications of the key personnel to complete the Services requested in this RFP.

Proposer shall complete and submit RFP Attachment H – Key Person Resume forms to specify key personnel to be assigned for these Services. The fields on the Key Person Resumes form may be expanded, adjusted, or fields added, but may not exceed 1 page per resume and must use a minimum of 11-point font for text. Key Person Resumes are included in the page limit identified in RFP section 3.2.2; however, a maximum of 6 Key Person Resumes may be submitted. Any resumes submitted beyond this limit will be discarded by Agency and will not be included in the evaluation.

Describe how the experience of the Key Personnel aligns with successfully completing the scope of Services described in this RFP in the Experience on…