00015373_Att I_AcronymsTermsDefinitions.docx

DOCX document 28 KB Posted

Attached to
I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services
Solicitation number
S-73000-00015373
Issued by
Oregon

About this file

This document is an Attachment to RFP/Bid Solicitation 73000-00015373 for the I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services, issued by the Oregon Department of Transportation (ODOT). The attachment provides a comprehensive glossary of acronyms, terms, and definitions used throughout the RFP solicitation. Key terms defined include Construction Manager/General Contractor (CM/GC), Guaranteed Maximum Price (GMP), Open-Book Process, Work Packages, and various federal and state regulatory references including FHWA, NEPA, and Oregon Revised Statutes. The document establishes standardized terminology for all parties involved in the I-5 Rose Quarter Improvements Project, including the Rose Quarter Program (RQP) division responsible for project management, independent cost estimators, the Contract Administrator, and the Agency Project Manager.

The definitions encompass technical and financial concepts relevant to construction auditing and cost verification services, such as Generally Accepted Accounting Principles (GAAP) and Generally Accepted Government Auditing Standards (GAGAS). Additional defined terms address project-specific elements including Early Work Amendments (EWA) and Main Construction Package (MCP), as well as compliance and civil rights terminology such as Disadvantaged Business Enterprise (DBE), Conflict of Interest (COI), and Tribal Employment Rights Ordinance (TERO). The glossary serves as a reference tool to ensure consistent interpretation of contractual language throughout the RFP and resulting contract execution.

View the file

Other files

File Type Posted
00015373_Att K_CMGC Contract Articles.pdf PDF
00015373_Att G_ResponsibilityInquiry.docx DOCX document
00015373_RFP.docx DOCX document
00015373_Att E_Price Proposal.xlsx XLSX spreadsheet
00015373_Att H_Key Person Resume.docx DOCX document
00015373_Att D_Completed Projects and References.docx DOCX document
00015373_Att C_Proposer Info-Cert.docx DOCX document
00015373_Att A_SampleContract.docx DOCX document
00015373_Att B_DisclosureExemptionCert.docx DOCX document
00015373_Att L_Project Cost Components.pdf PDF
00015373_Att J_Construction Phases.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP/Bid Solicitation 73000-00015373;

I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services; Attachment I

ATTACHMENT I - ACRONYMS, TERMS, AND DEFINITIONS

Note: Not all acronyms, terms or definitions may be used in this RFP.

Term/AcronymDefinition
A&EArchitecture and Engineering
Agency or ODOTOregon Department of Transportation
APMAgency Project Manager
AuditeeEntity being financially audited. For this Contract, Auditees include GMGC and others subject to CM/GC contract’s “Open-Book Process.”
CAContract Administrator
CCIFPCertified Construction Industry Financial Professional
CCOContract Change Order
CFRCode of Federal Regulations
CM/GCConstruction Manager/General Contractor
COIConflict of Interest
DBEDisadvantaged Business Enterprise
DRBDispute Resolution Board
EBEastbound
EWAEarly Work Amendment. A modification to the CM/GC contract for the construction of a Work Package.
FHWAFederal Highway Administration
FONSIFinding of No Significant Impact
GAAPGenerally Accepted Accounting Principles
GAASGenerally Accepted Auditing Standards
GAGASGenerally Accepted Government Auditing Standards
GMPGuaranteed Maximum Price
GMP AmendmentThe final modification to the CM/GC contract for this Project, negotiated at the beginning of the final Construction Package.
HBHouse Bill
IEIndependent (cost) Estimator
IIAInstitute of Internal Auditors
IIA StandardsInternational Standards for the Professional Practice of Internal Auditing
MCPMain Construction Package
NBNorthbound
NEPANational Environmental Policy Act
NTENot to Exceed
NTPNotice to Proceed
OAROregon Administrative Rule
OECRAgency’s Office of Equity and Civil Rights
Open-Book ProcessA transparent approach to enable validation of costs which allows full, real-time access to the CM/GC’s detailed financial records related to the CM/GC Contract, including, but not limited to actual costs, overheads, and profit margins.
ORSOregon Revised Statute
OTCOregon Transportation Commission
PIIPersonally Identifiable Information
Progress EstimateConstruction phase monthly estimate submitted by CM/GC to Agency for the amount and value of Work completed.
ProjectI-5 Rose Quarter Improvements Project
RCNReconnecting Communities and Neighborhoods
RFPRequest for Proposal
RQRose Quarter
RQPRose Quarter Program. An ODOT division responsible for managing the successful delivery of the I-5 Rose Quarter Improvements Project.
RSEARevised Supplemental Environmental Assessment
SBSouthbound
Scope of WorkBroad description of services desired; more general than the Statement of Work.
SOWStatement of Work. Contracted tasks and subtasks to include scheduled deliverables.
SPCSingle Point of Contact
StateState of Oregon
STIPStatewide Transportation Improvement Program
TEROTribal Employment Rights Ordinance
UMSUrban Mobility Strategy
UPRRUnion Pacific Railroad
USCUnited States Code
USDOTUS Department of Transportation
WBWestbound
WPWork Package.A discreet effort produced by the A&E Consultant and constructed by the CM/GC via an Early Work Amendment or Guaranteed Maximum Price Amendment.

File details come from the government source that posted it. Updated .