00015373_Att I_AcronymsTermsDefinitions.docx
DOCX document 28 KB Posted
- Attached to
- I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services
- Solicitation number
- S-73000-00015373
- Issued by
- Oregon
About this file
This document is an Attachment to RFP/Bid Solicitation 73000-00015373 for the I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services, issued by the Oregon Department of Transportation (ODOT). The attachment provides a comprehensive glossary of acronyms, terms, and definitions used throughout the RFP solicitation. Key terms defined include Construction Manager/General Contractor (CM/GC), Guaranteed Maximum Price (GMP), Open-Book Process, Work Packages, and various federal and state regulatory references including FHWA, NEPA, and Oregon Revised Statutes. The document establishes standardized terminology for all parties involved in the I-5 Rose Quarter Improvements Project, including the Rose Quarter Program (RQP) division responsible for project management, independent cost estimators, the Contract Administrator, and the Agency Project Manager.
The definitions encompass technical and financial concepts relevant to construction auditing and cost verification services, such as Generally Accepted Accounting Principles (GAAP) and Generally Accepted Government Auditing Standards (GAGAS). Additional defined terms address project-specific elements including Early Work Amendments (EWA) and Main Construction Package (MCP), as well as compliance and civil rights terminology such as Disadvantaged Business Enterprise (DBE), Conflict of Interest (COI), and Tribal Employment Rights Ordinance (TERO). The glossary serves as a reference tool to ensure consistent interpretation of contractual language throughout the RFP and resulting contract execution.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 00015373_Att K_CMGC Contract Articles.pdf | ||
| 00015373_Att G_ResponsibilityInquiry.docx | DOCX document | |
| 00015373_RFP.docx | DOCX document | |
| 00015373_Att E_Price Proposal.xlsx | XLSX spreadsheet | |
| 00015373_Att H_Key Person Resume.docx | DOCX document | |
| 00015373_Att D_Completed Projects and References.docx | DOCX document | |
| 00015373_Att C_Proposer Info-Cert.docx | DOCX document | |
| 00015373_Att A_SampleContract.docx | DOCX document | |
| 00015373_Att B_DisclosureExemptionCert.docx | DOCX document | |
| 00015373_Att L_Project Cost Components.pdf | ||
| 00015373_Att J_Construction Phases.docx | DOCX document |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFP/Bid Solicitation 73000-00015373;
I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services; Attachment I
ATTACHMENT I - ACRONYMS, TERMS, AND DEFINITIONS
Note: Not all acronyms, terms or definitions may be used in this RFP.
| Term/Acronym | Definition | |
| A&E | Architecture and Engineering | |
| Agency or ODOT | Oregon Department of Transportation | |
| APM | Agency Project Manager | |
| Auditee | Entity being financially audited. For this Contract, Auditees include GMGC and others subject to CM/GC contract’s “Open-Book Process.” | |
| CA | Contract Administrator | |
| CCIFP | Certified Construction Industry Financial Professional | |
| CCO | Contract Change Order | |
| CFR | Code of Federal Regulations | |
| CM/GC | Construction Manager/General Contractor | |
| COI | Conflict of Interest | |
| DBE | Disadvantaged Business Enterprise | |
| DRB | Dispute Resolution Board | |
| EB | Eastbound | |
| EWA | Early Work Amendment. A modification to the CM/GC contract for the construction of a Work Package. | |
| FHWA | Federal Highway Administration | |
| FONSI | Finding of No Significant Impact | |
| GAAP | Generally Accepted Accounting Principles | |
| GAAS | Generally Accepted Auditing Standards | |
| GAGAS | Generally Accepted Government Auditing Standards | |
| GMP | Guaranteed Maximum Price | |
| GMP Amendment | The final modification to the CM/GC contract for this Project, negotiated at the beginning of the final Construction Package. | |
| HB | House Bill | |
| IE | Independent (cost) Estimator | |
| IIA | Institute of Internal Auditors | |
| IIA Standards | International Standards for the Professional Practice of Internal Auditing | |
| MCP | Main Construction Package | |
| NB | Northbound | |
| NEPA | National Environmental Policy Act | |
| NTE | Not to Exceed | |
| NTP | Notice to Proceed | |
| OAR | Oregon Administrative Rule | |
| OECR | Agency’s Office of Equity and Civil Rights | |
| Open-Book Process | A transparent approach to enable validation of costs which allows full, real-time access to the CM/GC’s detailed financial records related to the CM/GC Contract, including, but not limited to actual costs, overheads, and profit margins. | |
| ORS | Oregon Revised Statute | |
| OTC | Oregon Transportation Commission | |
| PII | Personally Identifiable Information | |
| Progress Estimate | Construction phase monthly estimate submitted by CM/GC to Agency for the amount and value of Work completed. | |
| Project | I-5 Rose Quarter Improvements Project | |
| RCN | Reconnecting Communities and Neighborhoods | |
| RFP | Request for Proposal | |
| RQ | Rose Quarter | |
| RQP | Rose Quarter Program. An ODOT division responsible for managing the successful delivery of the I-5 Rose Quarter Improvements Project. | |
| RSEA | Revised Supplemental Environmental Assessment | |
| SB | Southbound | |
| Scope of Work | Broad description of services desired; more general than the Statement of Work. | |
| SOW | Statement of Work. Contracted tasks and subtasks to include scheduled deliverables. | |
| SPC | Single Point of Contact | |
| State | State of Oregon | |
| STIP | Statewide Transportation Improvement Program | |
| TERO | Tribal Employment Rights Ordinance | |
| UMS | Urban Mobility Strategy | |
| UPRR | Union Pacific Railroad | |
| USC | United States Code | |
| USDOT | US Department of Transportation | |
| WB | Westbound | |
| WP | Work Package. | A discreet effort produced by the A&E Consultant and constructed by the CM/GC via an Early Work Amendment or Guaranteed Maximum Price Amendment. |
File details come from the government source that posted it. Updated .