This is an attachment document containing CM/GC (Construction Manager/General Contractor) contract articles for the I-5 Rose Quarter Improvements project, specifically Attachment K to RFP/Bid Solicitation 73000-00015373 for Construction Cost Verification and Audit Services. The document references Contract Change Order 400AI and includes Articles 6, 8, 9, 10, 11, 12, 16, and 17 from the original CM/GC contract. The file appears to be a component of a larger 493-page solicitation document related to infrastructure improvements on Interstate 5 in the Rose Quarter area.

The document primarily consists of standard contract provisions and terms extracted from the base CM/GC contract. Without access to the substantive content of the specific articles referenced, the file appears to serve as a contractual framework document establishing the terms and conditions governing the relationship between the Construction Manager/General Contractor and the owner, with particular focus on cost verification and audit service requirements. The document structure suggests it is part of a comprehensive RFP package establishing contractual obligations, performance standards, and administrative procedures for the construction project.

View the file

Other files

File Type Posted
00015373_Att G_ResponsibilityInquiry.docx DOCX document
00015373_RFP.docx DOCX document
00015373_Att E_Price Proposal.xlsx XLSX spreadsheet
00015373_Att H_Key Person Resume.docx DOCX document
00015373_Att D_Completed Projects and References.docx DOCX document
00015373_Att C_Proposer Info-Cert.docx DOCX document
00015373_Att A_SampleContract.docx DOCX document
00015373_Att B_DisclosureExemptionCert.docx DOCX document
00015373_Att L_Project Cost Components.pdf PDF
00015373_Att I_AcronymsTermsDefinitions.docx DOCX document
00015373_Att J_Construction Phases.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

C15255, I-5 Rose Quarter Contract Change Order 400AI

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services;

Attachment K - CMGC Contract Articles 6, 8, 9, 10, 11, 12, 16, and 17

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

Attachment AIA

RFP/Bid Solicitation 73000-00015373;

File details come from the government source that posted it. Updated .