00015373_Att J_Construction Phases.docx

DOCX document 1 MB Posted

Attached to
I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services
Solicitation number
S-73000-00015373
Issued by
Oregon

About this file

This document is Attachment J to RFP/Bid Solicitation 73000-00015373 for I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services, issued by the State of Oregon. The attachment outlines the construction phases and timeline for the I-5 Rose Quarter Improvements project. Phase 1A, currently funded and in construction, includes stormwater improvements near I-5 and I-405, bridge work near I-5 and I-84, extension of the southbound auxiliary lane along I-5, and signage for traveler navigation. Phase 1B, with construction start planned for Summer 2027, encompasses additional signage, widening of the I-5 structure over Rose Quarter Transit Center to increase shoulder width, reconstruction of impacted transit center infrastructure, and initiation of right-of-way acquisition for Phase 1C. Phase 1C, with design and right-of-way acquisition funded but requiring construction funding, is planned for Q1 2029 and includes completion of the southern portion of the highway cover from Broadway to south of Weidler (representing 30 percent of total cover length), local street reconstruction on Broadway, Williams, and Weidler, completion of the I-5 southbound merging lane from I-405 to I-84, and extension of the northbound merging lane and shoulders to Broadway.

The document explains that the Phase 1C scope was designed as the smallest functional area of highway cover that could be constructed due to constraints posed by existing Broadway, Williams, and Weidler overcrossings. Freeway widening and lowering within the cover limits are necessary to provide adequate vertical clearance through the cover and maintain traffic during construction. This configuration allows remaining auxiliary lanes and highway cover portions to be completed either as one comprehensive package or multiple smaller packages contingent upon available funding. Remaining project elements, which currently lack design or construction funding, include construction of the remaining highway cover north of Broadway with Hancock Street extension, completion of remaining multimodal local street improvements, I-5 flyover and ramp relocation, a pedestrian and bicycle bridge, and completion of the I-5 northbound merging lane including segments from I-84 to Weidler, the Weidler 2-lane exit, and I-84 and I-405 connections.

View the file

Other files

File Type Posted
00015373_Att K_CMGC Contract Articles.pdf PDF
00015373_Att G_ResponsibilityInquiry.docx DOCX document
00015373_RFP.docx DOCX document
00015373_Att E_Price Proposal.xlsx XLSX spreadsheet
00015373_Att H_Key Person Resume.docx DOCX document
00015373_Att D_Completed Projects and References.docx DOCX document
00015373_Att C_Proposer Info-Cert.docx DOCX document
00015373_Att A_SampleContract.docx DOCX document
00015373_Att B_DisclosureExemptionCert.docx DOCX document
00015373_Att L_Project Cost Components.pdf PDF
00015373_Att I_AcronymsTermsDefinitions.docx DOCX document
Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFP/Bid Solicitation 73000-00015373;

I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services; Attachment J RFP/Bid Solicitation 73000-00015373;

I-5 Rose Quarter Improvements CM/GC Contract Construction Cost Verification and Audit Services; Attachment J Construction Phases April 2026 Phase 1A – Funded & In Construction (CN)

Stormwater improvements near the intersection of I-5 and I-405 Bridge work near the intersection of I-5 and I-84 Extension of the southbound auxiliary lane along I-5 between the I-84 and Morrison Bridge/OMSI exits Signage to help travelers navigate the area Phase IB – Funded & CN start Summer 2027

1. Signage to help travelers navigate the area Widen I-5 structure over Rose Quarter Transit Center to increase shoulder width on I-5 and reconstruct impacted transit center infrastructure Begin right-of-way acquisition for future Phase 1C construction Phase 1C – Design & ROW Funded, Need CN Funding, Planned for Q1 2029

1. Complete southern portion of the highway cover from Broadway to south of Weidler (30% of cover length) and local street reconstruction (Broadway, Williams, Weidler)

1. Complete I-5 southbound merging lane from I-405 to I-84 Extend northbound merging lane and shoulders to Broadway Why this portion of the cover? Why not smaller? Why include the cover & freeway?

Due to the constraints of the existing Broadway/Williams/Weidler overcrossings, this is the smallest functional area of the cover that can be constructed Freeway widening and lowering are necessary within the cover limits in order to provide the necessary vertical clearance through the cover and maintain traffic through the cover during construction Makes remaining portions of the auxiliary lanes and highway cover achievable either as one complete larger package or smaller packages based on available funds

Remaining Project Elements - No Design or CN Funding

1. Construct remaining highway cover north of Broadway (including Hancock St extension) Complete remaining multimodal local street improvements

1. I-5 flyover & ramp relocation

1. Pedestrian and bicycle bridge

1. Complete I-5 northbound merging lane, including segments from I-84 to Weidler, Weidler 2-lane exit, and I-84 and I-405