This is a Notice of Intent to Award issued by the Oregon Department of Transportation (ODOT) Procurement Office for Construction Administration and Construction Engineering & Inspection (CA/CEI) services on the US101 Culverts project (S-73000-00013723) spanning mileposts 73.46 to 136.29 in Tillamook and Lincoln County. David Evans and Associates, Inc. has been selected as the top-ranked firm for negotiations of a Work Order Contract (WOC) to provide Architecture and Engineering (A&E) and related services. The project involves the rehabilitation or replacement of culverts identified as being in poor or critical condition, along with construction of a water quality biofiltration swale near milepost 76.76. The anticipated project timeline runs from February 1, 2026, to February 28, 2027. No work is authorized until execution of the WOC and issuance of a written Notice to Proceed from the ODOT Project Manager, Anita Eaton.

The negotiation process follows a structured timeline with defined activities and responsible parties, beginning within 5–10 business days of the Notice of Intent to Award and anticipated completion within the specified schedule. The Consultant must submit a Breakdown of Costs (BOC) demonstrating subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal established in the Mini-Solicitation. Required award submittal items include billing rate information, cost disclosure questionnaire, breakdown of costs, certificates of insurance, and a list of subconsultants. The contract will be funded by Federal Highway Administration (FHWA) and State funds, with payment made for completed tasks or acceptable monthly progress. If negotiations cannot reach agreement on costs, tasks, or other WOC requirements within the specified timeframe, ODOT reserves the right to terminate negotiations and proceed with the next highest-ranked firm.

View the file

Other files

File Type Posted
00013723_Mini RFP.pdf PDF
00013723 Addendum 1 _Final.pdf PDF
00013723_Exhibit A.1.pdf PDF
00013723_Att A Cover Sheet_final.doc DOC document
Attachment B_Resumes_keystaff-Final~1.docx DOCX document
Sprinkler Valves.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Department of Transportation

Procurement Office

355 Capitol St NE, MS#3-3

Salem, OR, 97301

Phone: (503) 986-2710

Fax: (503) 986-5790

OREGON DEPARTMENT OF TRANSPORTATION

Notice of Intent to Award

DATE: August 25, 2025

TO: David Evans and Associates, Inc

SUBJECT: S-73000-00013723 US101: Culverts (MP 73.46 – 136.29)

David Evans and Associates, Inc is the top-ranked firm selected for negotiations of a Work Order

Contract (WOC) to provide A&E and Related Services as specified in the above-mentioned Mini-

Solicitation. The scores and rankings of all Proposers are shown in the score matrix accompanying this notice. The award submittal requirements stated in the Mini-Solicitation are summarized on Attachment 1 of this notice.

Anita Eaton will be the ODOT Project Manager (PM) for this Project. ODOT’s PM will initiate contact with Consultant and will be the primary contact for negotiation of the statement of work

(SOW), schedule of performance and costs under the WOC. Following discussion and agreement on the SOW, a Breakdown of Costs (BOC) must be completed (using the BOC, BOC-CPFF or BOC-

NBR as applicable) and submitted to ODOT’s PM. A BOC must demonstrate subcontractor utilization to meet the Disadvantaged Business Enterprise (DBE) goal set forth in the Mini-

Solicitation. To set expectations for the contracting phase, listed below is a schedule for completing the SOW, preparing a BOC, completing negotiations, and securing approvals for both the Consultant and ODOT to follow:

Activity Responsible Party Business Days

N eg o ti a ti o n s

Establish work session to discuss the

SOW with Consultant

ODOT PM Within 5-10 days of this notice (days depend on size and complexity of the project)

Respond to work session with comments/edits to SOW

Consultant Within 5 days of work session

Respond to SOW comments/edits ODOT PM Within 3 days of receipt of Consultant comments/edits

Submission of BOC Consultant Within 5-10 days of final

ODOT scope (days depend on size and complexity of the project)

Activity Responsible Party Business Days

Respond to BOC negotiate, and

Submit for legal sufficiency

ODOT PM

OPO

Within 5-10 days of

Consultant submission of the BOC (days depend on the size and complexity of the project)

Legal Sufficiency OPO, ODOT PM, and DOJ

Within 15 (Mini-

Solicitation) & 20

(Formal) days of submission by ODOT PM

Signature routing and execution OPO, Consultant, and ODOT

Expenditure

Authority (if required)

Within 6-8 days from initial routing

Issue Notice to Proceed (NTP) ODOT PM 1 day after execution

Negotiations are anticipated to be completed (ready to submit to for legal sufficiency) within the schedule set forth in this notice.

If the schedule for negotiations cannot be met and the Consultant and ODOT are negotiating in good faith, additional time may be mutually agreed upon.

If agreement on costs, tasks, or other WOC requirements cannot be reached within this time frame, ODOT may terminate the negotiations and begin negotiations with the next highest ranked firm as provided in the solicitation and governing Oregon Administrative Rules (OARs).

Note that no work is authorized until the WOC is executed and Consultant has received a written NTP from the ODOT PM.

ODOT would like to thank each Proposer for your time and efforts in preparing a response to this solicitation.

Sincerely, Melissa Lovejoy

Procurement Contract Specialist

Melissa.e.lovejoy@odot.oregon.gov

Attachment 1 – Award Submittal Requirements

Please email to me, the Contract Coordinator, the following items if marked as

“REQUIRED” in the Mini-Solicitation

• Billing Rate Information

• Cost Disclosure Questionnaire

• Breakdown of Costs

• Certificates of Insurance

• List of Subconsultants