Addendum No. 1 for the Ecorse DWSRF 7892-01 Water Main Replacement project was issued by Giffels Webster on 06/11/2025, involving the City of Ecorse and Wayne County. The addendum includes multiple modifications to the original bid documents, such as quantity adjustments for water services, excavation, granular material, pavement, and aggregate base items. Key changes include updating water service quantities (e.g., reducing short 1.5-inch services from 2 to 1, increasing long 1.5-inch services from 2 to 6), modifying pavement cross sections for Wayne County jurisdiction (changing from 1.5-inch to 2-inch HMA, 8-inch to 10-inch concrete, and 6-inch to 9-inch aggregate base), and altering the location of known lead/galvanized water service lines.
The addendum also updates technical specifications, including gate valve and hydrant product numbers and opening directions. Gate valves will now open clockwise for various sizes (6-inch to 16-inch), and hydrants will open counterclockwise. A pre-bid meeting was held on June 10, 2025, at Ecorse City Hall, with meeting minutes included in the document. The project is funded through the DWSRF (Drinking Water State Revolving Fund) and will involve replacing approximately 12,500 feet of 8-inch water main and 500 lead service lines. The engineer's estimate is approximately $13 million, with the project expected to start in late 2025 due to loan closing. The bid opening is scheduled for June 23, 2025, at 10 AM, and the project will adhere to federal funding requirements, including Davis-Bacon wages and American Iron & Steel provisions.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
#20519.00 City of Ecorse Ecorse DWSRF 7892-01 Water Main Replacement
Giffels Webster 00 91 13-1 Addendum No. 1
ADDENDUM NO. 1
ISSUE DATE: 06/11/2025
The following changes and/or clarifications shall be incorporated into said Bid Documents, and such changes shall be allowed for in the Bid by the Contractor. The Bid Form shall represent the conditions as set forth in the original Bid Documents, as modified by this Addendum.
1. Minor quantity discrepancies found after posted to bid. Updated bid form provided, but changes are as follows:
a. Water Service, Short, 1.5 Inch from 2 Ea to 1 Ea
b. Water Service, Long, 1 Inch from 115 Ea to 112 Ea
c. Water Service, Long, 1.5 Inch from 2 Ea to 6 Ea
d. Granular Material, Class II from 2643 Cy to 2662 Cy
e. Excavation, Earth from 2643 Cy to 2662 Cy
f. Brick, Rem unit changed from Ea to Sy
g. Aggregate Base, 6 Inch, Modified changed from 8,351 Sy to 8,109 Sy
h. Aggregate Base, 9 Inch, Modified changed from 0 Sy to 242 Sy (added this pay item)
i. Conc Pavt with Integral Curb, Nonreinf, 10 inch, Modified replaced existing item Conc Pavt with Integral Curb, Nonreinf, 8 inch, Modified for total 1,678 Sy
j. HMA, 5EML changed from 604 Ton to 624 Ton
k. HMA, 4EML changed from 584 Ton to 598 Ton
l. HMA, 2EML changed from 1,165 Ton to 1,196 Ton
2. ADJUSTMENTS TO CROSS SECTIONS FOR WAYNE COUNTY JURIDICTION
a. 1.5 Inch 5EML changed to minimum of 2 Inch 5EML
i. Pay item stays the same as HMA, 5EML, quantities adjusted.
b. 8 Inch Concrete changed to 10 Inch Concrete
i. Pay item changed from Conc Pavt with Integral Curb, Nonreinf, 8 Inch, Modified changed to Conc Pavt with Integral Curb, Nonreinf, 10 Inch, Modified
c. 6 Inch Aggregate changed to 9 Inch Aggregate
i. Pay item changed from Aggregate Base, 6 Inch, Modified changed to Aggregate Base, 9 Inch, Modified
d. Quantities of all applicable pay items based on Wayne County Cross Section adjustments have been corrected accordingly (CP-12, CP-20, CP-34, CP-52, and CP-79)
e. An additional note about restoration to take place 1 foot around the restored/repaired areas for Wayne County Jurisdiction was added to all applicable pages (CP-12, CP-20, CP-34, CP-52, and CP-79).
3. Altered location of known lead/galvanized water service line from 457 Salliotte to 479 Salliotte
4. Added callouts to unknown water service line material for 380 Salliotte, 370 Salliotte, 342 Salliotte, and 307 Salliotte.
#20519.00 City of Ecorse
Giffels Webster 00 91 13-2 Addendum No. 1
5. Water Main Standard Details and 33 10 00 Water Utilities updated product numbers and opening direction for gate valves and hydrants.
a. Gate Valves opening clockwise (right):
i. 6 IN – EJ PRODUCT 2200610
ii. 8 IN – EJ PRODUCT 2200810
iii. 12 IN – EJ PRODUCT 2201210
iv. 16 IN – EJ PRODUCT 2201610
b. Hydrants opening counterclockwise (left)
i. EJ 5BR250 PRODUCT 55027D
6. Pre-Bid Meeting held at 10:00 AM on June 10, 2025, at Ecorse City Hall. Meeting minutes are included in this addendum.
7. Revised General Decision Number: MI20250075 06/06/2025.
Bidder shall acknowledge receipt of this ADDENDUM NO. 1 in the designated area on the provided Bid Form documentation prior to the Bid due date.
6303 26 Mile Road | Suite 100 | Washington, MI 48094 | (586) 781-8950
Meeting Minutes
Meeting: Pre-Bid Meeting Date: June 10, 2025
Time: 10:00 AM Project: Ecorse DWSRF 7892-01 Water
Main Replacement
Location: Ecorse City Hall Project No.: 20519.00
Meeting minutes in bold italic font
1. Project Overview
a. Over 12,500 of 8” water main replacement
b. Existing system in poor condition and must maintain service until new main is installed, tested, and accepted.
c. 500 lead service line replacements
d. All work to be conducted within the ROW, no easements acquired
2. DWSRF Funding & Requirements
a. American Iron & Steel
i. Contractor asked if the project was Buy America. Technically terminology has changed but all included in the contract documents.
b. Davis-Bacon & Prevailing Wage (certified payrolls)
c. Start date is not expected until late 2025 due to loan closing.
3. Line Stops
a. Expecting existing gate valves are not operable to get a solid shut down, but can continue to test with DPW to minimize where possible.
b. Would the city consider an actuator for valve?
i. Yes they would and they will continue to test in the meantime.
4. Lead Service Replacements
a. Along alignments vs. throughout city
i. The pay item for throughout the rest of the city will need to include all hard and soft surface restoration. See Special Provision.
b. 45 days’ notice & permit release form must be signed
c. A map & list of other known lead/galvanized services will be provided to awarded contractor. The list is much more than 500 included in scope.
d. LSLR is funded separately, so will do more or less than 500 dependent on unit price.
e. Contractor is responsible for complete install up to the meter. City DPW will determine if meter replacement is necessary and if it is, DPW will replace.
5. Exploratory Investigation, Vertical
a. Where the curb stop was not located.
b. As-needed quantity.
6. Tree Replacements
June 10, 2025
a. Must offer property owners replacement trees at all locations where a tree is removed.
b. Giffels Webster & City DPW will start this coordination this summer.
7. Storm Sewer Replacement
a. Contractor to protect existing sewer and structures if possible. Pay items are included to account for removal & replacement where engineer deems reasonable, but exact removal & replacements will be determined during construction
8. Road/pavement and fence disturbance
a. Pay items are included to account for removal & replacement where engineer deems reasonable, but exact removal & replacements will be determined during construction. The hope is to minimize disturbance for only remove what is required.
b. There are two separate pay items for fence removal and replacements.
i. The EA item is for the front yard fences that need a water service replaced.
9. Railroad Crossings
a. CN “GTW” & Conrail
b. Monitoring
i. Giffels Webster survey team can provide survey shots during jack & bore.
c. Training, insurance, etc.
d. Please review contract documents for requirements. Costs associated with permit fees & any required training can be included in the cash allowance item with required backup.
10. High Pressure Gas
a. Coordinate with applicable agencies / companies
b. Giffels Webster will provide additional information to awarded contractor, but only 2 locations where we are in close proximity (4th & Salliotte, both are short stretches).
11. Wayne County Permit
a. Still under review
b. Southfield crossing at Monroe
i. Traffic Control expected to maintain two way traffic along Southfield at all times. Expect to flip detour once backfilled & restored.
c. Potential pedestrian detours
d. Cross section of pavement sections will be updated.
12. Contamination
a. See G2 report for mitigation along known contaminated parcels.
b. Dispose that material at Type II landfill (must be tested & manifested).
c. Owner will provide environmental testing for samples to be sent to landfill.
13. Salliotte Light Poles
a. Bid is to salvage and reconnect existing light poles.
14. Utility Poles
a. Protect/deflect as necessary.
15. Abandon/remove existing WM structures that will no longer be active.
16. Traffic Control
June 10, 2025
a. Maintain access for residents at all times. Many of these are one-way streets.
b. Mail & garbage pickup
i. Contractor requested map showing the garbage pickup days in the city. This will be included in the minutes & Addendum No. 1.
17. Changes to be included in the upcoming addendum:
a. Updated detail sheet for Gate Valves: open right (clockwise) & hydrants
i. Update product numbers
b. Pavement cross sections for Wayne County roads
c. Minor quantity discrepancies
d. Revised Wage Rate Decision Number
18. Bid Opening
a. Monday, June 23, 2025, at 10 AM
19. Miscellaneous Q&A
a. Engineer’s estimate is approximately $13 million.
b. More than one product type (i.e. for joints) if one source cannot fulfill the entire project as long as they meet City Standard Details and AWWA standards. The hope is that with the extended time from Award to Notice to
Proceed the items can all be procured from one source.
c. The pressures vary throughout the entire water main system. Generally fairly low due to buildup in older pipes.