00 80 00.pdf
PDF 8 KB Posted
- Solicitation number
- FA813727R0002
About this file
This document is a Section 00 80 00 specification containing special provisions for contractors working on Tinker Air Force Base (TAFB).
The specification establishes mandatory requirements for contractor operations on the airfield and base. Key provisions include: (1) Contractor responsibility for dewatering excavated areas using sufficient pumps to remove rainwater promptly; (2) Haul routes directed by project drawings or the Contracting Officer; (3) Pre-coordination of all airfield activities with the Contracting Officer and Chief of Airfield Management (CAM) prior to work commencement, with strict adherence to TAFBI 13-204 and Section 00 80 05; (4) Maintenance of open runways, taxiways, and aprons unless otherwise specified, with construction equipment limited to 12 feet in height and absolute prohibition on equipment or personnel in aircraft movement areas or within 200 feet of runways without Tinker Control Tower permission; (5) Flight line driver training and portable radio communication requirements for Contractor personnel operating equipment in movement areas or on aircraft-parking ramps for projects exceeding seven days, with the CAM authorized to waive training for short-duration projects subject to airfield orientation briefing; (6) Airfield authorization passes required prior to project commencement; (7) Right-of-way granted to taxiing and towed aircraft at all times with close coordination between Contractor foreman and Airfield Manager; (8) Traffic control and barricades compliant with the U.S. Department of Transportation's Manual on Uniform Traffic Control Devices, with all associated costs borne by the Contractor; (9) Road closure restrictions limiting blockage to one lane on two-lane roads and requiring two lanes open on four-lane roads (three during rush hour); (10) Contractor responsibility for waste material removal and off-base disposal; and (11) Optional winter recess negotiation between December 1 and March 1 as a no-cost modification extending the Delivery Order completion date.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Tinker AFB Tinker General Requirements
SECTION 00 80 00
SPECIAL PROVISIONS FOR WORKING ON TINKER AFB
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only. The most current edition of the listed publications at the time of contract/delivery order award shall be used.
TINKER AIR FORCE BASE (TAFB)
TAFBI 13-204 (2021) Airfield Operations
1.2 DEWATERING EXCAVATED AREA
It shall be the Contractor's responsibility to protect the construction area from damage due to rainwater. The Contractor shall provide and maintain at the job site sufficient pumps to remove rainwater from the excavated area as soon as practicable.
1.3 HAUL ROUTES
The haul routes to be used by the Contractor shall be as directed on the project drawings or by the Contracting Officer.
1.4 AIRFIELD OPERATIONS
All contractor activities on the airfield shall be pre-coordinated with the Contracting Officer in conjunction with the Chief, Airfield Management (CAM) prior to the Contractor proceeding on the airdrome. The provisions of TAFBI 13-204 and Section 00 80 05 SPECIAL PROVISIONS FOR WORKING ON OR NEAR THE AIRFIELD shall be strictly adhered to.
All runways, taxiways and aprons shall remain open during this project, unless specified otherwise by the Contracting Officer. The height of construction vehicles and equipment shall be limited to 12 feet above the surface. Absolutely no equipment or personnel will be allowed on the aircraft movement area or within 200 feet of the runways without permission from the Tinker Control Tower.
All Contractor personnel who will be operating their equipment or vehicles within the movement area or on any aircraft-parking ramp shall receive flight line driver training and have portable radios capable of communicating with Tinker Ground Control for projects over seven days.
The CAM may authorize certain contractors and other personnel to drive on the airdrome for short specified periods without completing the flight line driving training. However, Airfield Management will brief contractors and project engineers (or other supervisors responsible for the work being accomplished) and will provide flight line orientation for contractor vehicle operators prior to allowing them to drive on the airdrome.
January 2022 Page 1 Section 00 80 00
Tinker AFB Tinker General Requirements
Prior to commencing work on this project, the Contractor shall coordinate with the Contracting Officer for any airfield authorization passes that may be required.
Taxiing and towed aircraft shall have the right-of-way at all times.
Close coordination will be maintained between the Contractor's on-site foreman and the Airfield Manager.
1.5 TRAFFIC CONTROL AND BARRICADES
1.5.1 Automobile Movement Areas
Construction areas affecting automobile movement areas shall be protected by an adequate number of barricades with working flashing lights, warning devices, construction signs, flagmen and personnel. The barricades and warning devices shall be in accordance with the "Manual on Uniform Traffic Control Devices for Streets and Highways" developed by the U.S. Department of Transportation as an approved national standard. All costs associated with providing the traffic control and barricades shall be considered incidentals and shall be borne by the Contractor at no additional cost to the Government.
1.5.2 Road Closures
On two lane roads, only one lane may be blocked at a time. On four lane roads, at least two lanes shall be kept open at all times and three at rush hour.
1.6 WASTE AREA
Unless otherwise specified in these specifications, all waste materials removed shall become property of the Contractor and shall be taken off base for disposal. Disposal site location shall be the responsibility of the Contractor.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
3.1 WINTER RECESS
A winter recess, between December 1 and March 1, can be negotiated per Delivery Order between the Contracting Officer and the Contractor. It shall be a no cost modification to the contract moving the Delivery Order completion date the amount of the recess time.
-- End of Section --
January 2022 Page 2 Section 00 80 00
File details come from the government source that posted it. Updated .