This document is a Phase 2 submission instruction guide for a federal design-build contract solicitation (W9128F26RA054) issued by the U.S. Army Corps of Engineers.

Offerors must submit two separate electronic volumes in PDF format with OCR capability via email. Volume I (Technical Proposal) contains Factor 4 – Technical Approach to the Sample Project, limited to 15 pages excluding Buy American Act discussion. The technical approach should describe all aspects of the design-build methodology, identify and mitigate technical risks, clarify any project phasing, list assumptions, and provide designer/A-E service capabilities including company name, CAGE Code/UEI, technical specializations, and design-construction coordination procedures. Offerors must also provide a draft project schedule in Gantt chart format (exempt from page limits) with critical activities and milestones including task order kickoff, design completion, manufacturing, permitting, site work phases, commissioning, performance verification, and closeout, but the schedule shall not include funding, pricing data, or narrative descriptions. Volume II (Price Proposal) contains Factor 5 and must include: (1) Binding Maximum Labor Rate Schedule (Section 00 10 00, Table 1) with unburdened and burdened hourly rates for all contract terms with no category title modifications; (2) Binding Maximum Indirect Rates (Table 2) with flexibility for Overhead/G&A based on accounting structure, supported by recent audit documentation or detailed cost pool breakdowns; (3) Escalation Rate (Table 3); and (4) Sample Project Pricing Bid Sheet (Table 4) requiring time-phased labor breakdown using only binding labor rates without discounting, documented indirect cost application using binding cap rates without discounting, maximum binding profit rate (sample project only, not included in base contract), and direct labor assumptions in bullet format that address gaps in contractual documents rather than restating compliance. The sample project involves interior and exterior renovations of approximately 3,600 square feet at Fort Carson, Colorado, Building 1959, to create a secure area meeting ICS 705 construction standards and SCIF accreditation requirements, with work limited to eight-hour days and five-day work weeks, commencing no later than 30 days after NTP (assumed August 2027) and completing within 450 calendar days. Davis-Bacon prevailing wage rates apply for El Paso County, Colorado, with Executive Orders 13706 and 13658 requirements regarding paid sick leave and minimum wage rates. Failure to submit complete proposals following all instructions and requirements may result in the Government considering the entire offer nonresponsive. All inquiries must be submitted through ProjNet Bidder Inquiry system with one question per inquiry only.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 00 21 16

PHASE 2 OF 2 PHASE SUBMISSION INSTRUCTIONS

INDEX

1. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1.1. PROPOSAL FORMAT

1.2. SUBMITTAL REQUIREMENTS

1.3. INQUIRIES/QUESTIONS

1.4. VOLUME I, TAB 1 - FACTOR 4 – TECHNICAL APPROACH TO THE SAMPLE

PROJECT

1.4.1. Submission Requirements

1.5. VOLUME II, TAB 3 - FACTOR 5 – PRICE FOR THE SAMPLE PROJECT

1.5.1. Submission Requirements

1. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS

1.1. PROPOSAL FORMAT

a. Submit each file for Phase 2 proposal in electronic format, per the instructions above, identified by the Solicitation Number (W9128F26RA054), Company Name, and Phase/Volume identification. Each Volume will be submitted as a separate file. The proposal shall be submitted in Volumes as follows:

Phase 2, Volume I, Technical Proposal:

Table of Contents Tab 1 FACTOR 4 – Technical Approach to the Sample Project

Phase 2, Volume II, Price Proposal and Other Required Documentation:

Cover Letter Table of Contents Tab 1 Acknowledgement of Amendments Tab 2 FACTOR 5 – Price Proposal for the Sample Project (to include Section 00 10 00)

TABLE 1: Phase 2 Evaluation Factors

Volume Evaluation Factor Location Title Page Limitations

I Factor 4 Tab 1 Technical Approach to the Sample Project

15 pages*

Buy American Act Discussion or Documentation not applicable to page count.

II Factor 5 Tab 2 Price Proposal for the

Sample Project (to include Section 00 10 00)

No Page Limitations for Price

b. Proposal Characteristics

a) All text shall be at least 10 pt. font and easily read. The page size of the Offeror’s proposal shall not exceed 8-1/2 by 11 inches. All text shall be at a minimum single-spaced.

b) Each page should contain the following information in the top and bottom margin. Exact placement (center, off-center, left, right, etc.) and sequence of presentation is at the discretion of the Offeror.

• Page number. Pages for each factor should be separately and sequentially numbered (i.e., the first page submitted for evaluation of each factor should be “Page 1”). This includes all pages for Factor 3. The page numbers are needed by the Government for reference during the selection process.

• Factor number and title. For example, “Factor 3 –Resumes of Corporate Personnel.”

• Solicitation Number

• Company name of Offeror and (at the Offeror’s discretion) the company logo

• Disclosure information can be placed in the bottom margin.

c) Offeror shall submit a cover letter containing:

• Solicitation number

• Name, title, address, email, and telephone number of the offeror.

• Names, titles, emails, and telephone numbers of persons authorized to negotiate on the Offeror’s behalf with the Government in connection with this RFP.

• Name, title and signature of the person authorized to sign the proposal.

• Names, titles, emails, and telephone numbers of proposal coordinators who will handle correspondence with the Government on behalf of the Offeror in connection with this RFP, if different from the personnel provided above (primary and alternate).

• A statement specifying agreement with all terms, conditions and provisions included in the RFP.

• CAGE Code, Unique Entity Identifier (Unique Entity ID), and Tax Identification Number (TIN) of the offeror.

d) Offerors must acknowledge all amendments for this solicitation. This can come in their Phase 2 proposal, sending a separate letter, or by email.

1.2. SUBMITTAL REQUIREMENTS

All proposals shall be submitted electronically via email to sara.edwards@usace.army.mil and tyler.hegge@usace.army.mil. All submissions shall be in Adobe PDF format with Optical Character Recognition (OCR) applied to all documents that will enable word searches to be conducted using Adobe-compatible PDF software. The two (2) volumes listed below shall be submitted as SEPARATE files. Offerors should follow Controlled Unclassified Information (CUI) guidelines and use proper markings if submitting documents that are considered CUI via email when allowed per instructions in 00 20 00. Proper markings include the following: banner markings should appear above the email text containing CUI, the email subject line should also indicate the email contains CUI, and file names for any attachments containing CUI.

Title the single files in the following format:

W9128F26RA054_COMPANY NAME_PHASE2_VOLUME_I

W9128F26RA054_COMPANY NAME_PHASE2_VOLUME_II

For the purposes of determining whether the proposal was received “late” in accordance with FAR 15.208, see 00 20 00 Proposal Submission Instructions. Do not assume that electronic mailto:sara.edwards@usace.army.mil mailto:tyler.hegge@usace.army.mil communication is instantaneous. Please make allowances for delays in transmittal.

Electronic Proposals shall be received No Later Than (NLT) the date and time indicated in Block 13 of the SF 1442 for this solicitation or as identified in subsequent amendments.

Failure to submit a complete proposal in accordance with (IAW) instructions and requirements may result in the Government considering the entire offer as nonresponsive.

1.3. INQUIRIES/QUESTIONS

Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.

***Please Note: Offerors shall only submit one question per inquiry. All inquiries containing multiple questions shall be rejected. See Section 00 21 00 INSTRUCTIONS TO OFFERORS (Phase 1) for additional information.

The Solicitation Number is: W9128F26RA054

The Bidder Inquiry Key is: TO BE INCLUDED IN PHASE 2

1.4. VOLUME I, TAB 1 - FACTOR 4 – TECHNICAL APPROACH TO THE

SAMPLE PROJECT

1.4.1. Submission Requirements

The Offeror should clearly describe all aspects of the technical approach including any deviations from the specifications included in Attachment 00 21 16 A. The Offeror should provide an analysis of the significant risks associated with the technical approach along with a plan on how the Offeror intends to manage and/or mitigate those risks. The Offeror should clearly identify any potential phasing required to execute the technical approach. The Offeror should list and discuss any and all assumptions made when developing their technical approach.

The Offeror shall also provide a narrative of the designer(s)/ Architect Engineer (A-E) service capabilities.

1.4.1.1 Designer(s)/A-E Service Capabilities

a. Identify how your company intends to execute the design effort for the

Design-Build sample project.

b. If design will be accomplished by a company other than the Offeror’s, provide the following information for designer/A-E firm:

i. Company’s name

ii. CAGE Code or UEI

c. Describe the technical capabilities and specialization (if any) of your in-house or teamed designer/A-E (for example, structural, mechanical, electrical, etc.), if any.

http://www.projnet.org/projnet

d. Describe how your company would coordinate design and construction efforts, to include design quality role, and the role of the Government in Design-Build (DB) projects.

1.4.1.2 Project Schedule for Sample Project

The Offeror shall provide a draft project schedule with the proposal for accomplishing the work effort of the SOW of the sample project with this RFP.

The project schedule is exempt from the page limitations. The schedule should be in the form of a Gantt chart. Critical activities should be included. The schedule should outline key activities and milestones defined at the appropriate level, and logically sequenced to support and manage achievement of the proposed objectives, consistent with the narrative discussion of the approach in the proposal.

Key activities and milestones should include task order kickoff, design begin, design completion, manufacturing of components and long lead items, manufacturing completion, permitting, site work begin, site work complete, commissioning, performance verification and task order close out. The schedule should include critical path items that may affect the ability to meet the schedule.

The project schedule shall not include any funding or pricing data, nor shall it include narratives of the approach of the project.

1.5. VOLUME II, TAB 3 - FACTOR 5 – PRICE FOR THE SAMPLE PROJECT

1.5.1. Submission Requirements

IMPORTANT: The Offeror shall submit all price submission requirements for Factor 5 separately in Phase 2, Volume II. Do not submit Factor 5 submission requirements in Volume I of Phase 2.

Volume II shall include the following information in order as stated below:

a. Binding Maximum Labor Rate Schedule (reference Section 00 10 00, Table 1)

b. Maximum Indirect Rates (reference Section 00 10 00, Table 2)

c. Escalation Rate (reference Section 00 10 00, Table 3)

d. Sample Project Pricing Bid Sheet (reference Section 00 10 00, Table 4 and Attachment 00 21

16 A)

Failure to include all items may render the proposal non-responsive and ineligible for award.

1.5.1.1 Binding Maximum Labor Rate Schedule

a. The Offerors shall complete Section 00 10 00, Table 1 “Binding Maximum Hourly Labor Rate Schedule” in its entirety. The Offerors shall propose the hourly unburdened and burdened rates for each contract term for all of the labor categories identified in Table 1. Do not change in any way the titles of the listed labor categories. Failure to complete Table 1 in its entirety may result in an Offeror being excluded from consideration for award.

b. The hourly burdened labor rates proposed by the Offerors shall include direct cost, payroll taxes, insurance, benefits, and any other applicable labor costs (not already included in either the Offeror’s Indirect Rates) but shall exclude profit. Offerors shall provide an example of how the mark-ups are applied to the unburdened labor rates.

c. The hourly burdened labor rates proposed in Table 1 will be legally binding and will be the maximum rates that the Offerors shall use for all task orders and task order modifications issued during the five (5) year period of performance of the contract (base and option terms) and potential 6-month option, including the sample project.

d. The Government reserves the right to request information other than certified cost or pricing data from the Offerors, in order to assess the reasonableness of the proposed labor rates.

1.5.1.2 Binding Maximum Indirect Rates

a. The Offerors shall complete Section 00 10 00 Table 2 “Binding Maximum Indirect Rates” in its entirety. The binding maximum rates proposed in Table 2 will be legally binding and shall be the maximum rates that the Offerors will use on all task orders and modifications issued during the five (5) year period of performance of the contract (base and option terms) and the potential 6-month extension, including the sample project. Depending on an Offeror's accounting structure, the Offeror may have either Overhead/G&A or both. The intent is to provide Offerors the flexibility in proposing in accordance with its accounting structure. If an Offeror only has one (e.g. Home Office Overhead) and not the other (e.g.

G&A), the Offeror can mark whichever one as not applicable in the Binding Maximum Indirect Rates table.

b. The cost pools shall be in accordance with the Offeror’s most recent audited rates, if available.

1. If the Offeror has been audited within a year of the proposal submission date, the Offeror is instructed to provide a copy of the audit, to include, if available, any other rate information received from the Administrative Contracting Officer of the cognizant audit agency. The Offeror will not be required to provide the breakdown of each of their cost pools.

2. If the Offeror does not have a recent audit, the Offeror shall provide detailed information showing cost accounts included in each of their cost pools in order to explain all overhead rates, G&A markups, labor burden (fringes), and any other pools. The composition of the base on which the pool is distributed shall also be shown. An example of a G&A expense rate computation is listed below and may be used as a guide. Note that the list is not inclusive of all allowable or unallowable costs:

Indirect Salaries $100,000 Officers’ Salaries $85,000 Payroll Taxes $9,500 Insurance $14,500 Rent $35,000 Utilities $14,000 Repairs & Maintenance $6,500 Interest Expense -0- * Advertising -0- * Office Supplies $1,500 Personal Property Taxes

$2,200

Contributions -0- * Depreciation Office Equipment

$ 8,500

Legal Fees $ 3,500 Bad Debts -0- * State Income Taxes $7,500

TOTAL G&A

EXPENSE

$287,700

Total Direct Labor $3,000,000 Add Labor Burden @ 35%

$1,050,000

Other Direct Costs $3,000,000

TOTAL BASE $7,050,000

Percentage Computation

G&A Expenses $ 287,700

4.08%

Base $7,050,000

* Examples of unallowable costs in accordance with FAR Part 31. All costs unallowable per FAR Part 31 should be removed from overhead pools before computation of the submitted rate.

1.5.1.3 Sample Project Pricing

a. The Offeror shall complete the Contract Rate Pricing Schedule (reference Section 00 10

00) in its entirety. The hours included in the Contract Rate Pricing Schedule represents an estimated number of hours for each of the labor disciplines based on historical contract information and anticipated level of contingency support that may be required for a project.

These hours are not contractually binding and are used only for evaluation purposes.

b. Offerors shall provide the following information (other than certified cost or pricing data) to substantiate the basis for the proposed lump sum price. Failure to provide the requested information may result in the Offeror being excluded from consideration for award. For the sample project effort, the Offerors should assume that they will self-perform the work.

1) Section 00 10 00 Direct Labor. Provide a time-phased (e.g., monthly, quarterly, etc.)

breakdown of labor hours, rates, and cost by appropriate category, and furnish basis for estimates. Offerors shall use only the Section 00 10 00 labor disciplines for the Direct Labor.

All other labor is included as part of the plug variable within the Materials and Services.

Offerors shall use the proposed hourly burdened labor rates in Section 00 10 00, Table 1 for the labor disciplines in pricing the sample task project. For the purposes of the sample project, Offerors shall not discount their proposed binding rates. Offerors that do not utilize the binding rates proposed in Section 00 10 00, Table 1 to calculate the price for the sample project will not be considered for award.

2) Indirect Costs (other than Profit). Offerors shall indicate how they have computed and applied their indirect costs. Offerors shall use the binding cap rates in Section 00 10 00, Table 2 in pricing the sample task order. For the purposes of the sample project, Offerors shall not discount their proposed binding cap rates. Offerors that do not utilize the binding cap rates proposed in Section 00 10 00, Table 2 to calculate the price for the sample project will not be considered for award. If the Offeror has additional indirect rates to those proposed in Section 00 10 00, the Offeror shall indicate the rate used and include a cost breakdown for the indirect rate. The Offeror shall show trends and budgetary data to provide a basis for evaluating the reasonableness of rate.

3) Profit: The Offeror shall propose their maximum binding profit rate for the purposes of the Sample Project Pricing, the Offeror shall not discount their maximum binding profit rate. Proposed profit applies only to the Sample Project and will not be included in the base contract. Profit will be negotiated at the task order level; refer to Section 00 10 00.

4) Direct Labor Assumptions: Offerors shall list all assumptions relevant to the direct labor in bullet format. Any assumptions that conflict with guidance provided in the solicitation documents will not be considered to be valid. Solicitation documents include, but not limited to, the drawings and specification, the Statement of Work (SOW), contract clauses, responses to requests for information (RFI), and any other document(s), attachment(s), and exhibit(s) provided by the Government for the requirement. The Government requires all assumptions that state that the proposal follows the guidance of contractual documents, including RFI responses, be removed from the price proposal.

The Government recognizes that some assumptions or statements of understanding may be required. In these situations, the Offerors shall submit assumptions as follows:

i) If the assumption is based on the contractual documents, including RFI responses, not addressing a situation, the assumption shall include the following:

• A description of the issue including the basis for the assumption (e.g. past experience at these locations, lesson learned, etc.)

• The proposed solution; and

• The cost impact of the proposed solution

NOTE: Offerors are discouraged from providing unrealistic solutions.

ii) If an Offeror believes that any of the contractual documents are conflicting or in error, after the RFI process, the assumption shall include the following:

• A general description of the conflicting or incorrect information with references to the location of the questioned information, such as the specific RFI response number, drawing sheet, specification section, or other contract document.

• The information that was used in the proposal. If there is a conflict between the specifications and drawing sheets, follow the guidance in FAR clause 52.236-21 Alt I.

• The cost associated with that information.

NOTE: If the RFI response resolves an error or conflict in a requirements document, an assumption stating that the RFI response and the original document are in conflict is not needed.

Attachment 00 21 16A

Sample Project

NOTE: The sample project has been scoped so that it captures a variety of activities that may be required under the contract. It should not be construed as indicative of typical project size.

It does not actually exist; as such as-built or concept drawings are not available.

Scope of Work

1. Project is located at Fort Carson, CO

2. Design & Construction Objectives. Space Brigade of Army Space and Missile Defense Command requires additional space to expand their current Secure Area to meet additional mission requirements. This space will be integrated with their current Secure Area and will utilize a server space in existing room 161. The unit needs additional space for secure working areas, private offices, and conference rooms to hold TS/SCI meetings with more than 6 people. This facility will also accommodate expanded growth of the unit and its mission.

3. Project Scope. Building 1959 project will include interior and exterior renovations to the current open office area (2,394 sf), Battalion conference room (342 sf), and two secure offices (143 and 168 sf), one unsecured office (140 sf), and secured vestibule (42 sf), separating the unsecured corridor to the north to the proposed secured area to the south.

Exterior modifications are limited to infill insulated metal wall panels and demolition of current windows into the proposed secure office area. Overall area to be renovated is approximately 3,600 sf. These renovations will include, demolition to stud structure of walls within the proposed secure area footprint, remounting internal components to the finish surface in accordance with ICS 705-1standards. New Acoustic Ceiling Tile (ACT) and finishes to match existing and repair of any finishes, surfaces, or features damaged during construction, and creation of a new unsecured corridor to separate secure area from nonsecured circulation. Additional access controls tied into the existing infrastructure will be required. Additionally, the entire Secure Area perimeter walls will be protected by RF Foil in accordance with ICS 705-1. The new construction of this facility shall meet ICS 705 construction standards to become an accredited SCIF.

4. Facility Functions. This renovation of an existing facility will create secured open office area, a secure conference room, two secured offices, a secured vestibule, and a new unsecured corridor. This facility will function as a secure area and needs to be designed as such.

5. Project Site. The project is located at Ft. Carson, Colorado, (Building 1959). Vicinity and location maps can be found in the drawings provided with this RFP.

6. It shall be the responsibility of the Design-Build Contractor to assemble the best-value-priced construction systems for this project that meet or exceed the design criteria set forth herein.

7. Design, construction, and commissioning must abide by current design criteria and standard designs. Facilities and construction methods must comply with applicable state and DoD environmental regulations.

8. Codes and Criteria All pertinent building codes, life safety codes, and reference criteria shall be met or exceeded. This project utilizes the DoD Building Code, as defined by UFC 1-200-01 and its references. If there is a conflict in requirements, order of precedence shall be as follows,in order of decreasing precedence: a. Life Safety, as defined by DoD Building Code UFC 1-200-01 and its references b. RFP Specifications c.

RFP Drawings d. Non-life safety criteria, as defined by DoD Building Code UFC 1-200- 01 and its references e. Other criteria as listed herein.

9. Design and Construction Measurement Units Design, products, and construction for the project shall be accomplished using English units of measurement. All measurement in the technical specifications sections shall be shown in English.

10. Sensitive Compartmentalized Information Facility (SCIF). This project includes work to be completed inside an existing active accredited secure area. This work, to include new finishes and a new door inside the perimeter of the SCIF, as well as new communications penetrations at the SCIF perimeter, must not impact the existing SCIF's accreditation.

The contractor must provide the AO with plans for work affecting the current function SCIF (construction of PDS, and cable tray) and must receive approval prior to construction. Work within the SCIF still requires much of the oversight and document control required for new construction projects for SCIF's. See below for requirements.

Construction personnel that work within the SCIF boundary must be escorted while performing their work. The government will provide escorts for contractor personnel.

When referencing the project, the SCIF shall be referred to as a "Secure Area" when referenced in either verbal or written communication with design and construction personnel who do not need to know that this project is a SCIF for the completion of their tasks.

11. SCIF Criteria. Areas identified in the design documents as "Secure Areas" are designed, constructed, and accredited to the criteria listed below. The contractor shall implement the project oversight, security, and document control requirements listed in following criteria: Use the most current version of the referenced criteria available at the bid submission deadline:

a. ICD/ICS 705 - Technical Specifications for Construction and Management of Sensitive Compartmented Information Facilities.

b. ICS 705-1 - Physical and Technical Security Standards for Sensitive Compartmented Information Facilities.

c. ICS 705-2 - Standards for the Accreditation and Reciprocal Use of Sensitive Compartmented Information.

d. UFC 4-010-05 - Sensitive Compartmented Information Facility Planning, Design and Construction.

This specification indicates the Contractor and Government's role(s) in administering the secure areas during construction for maintaining accrediting by assigned authorities.

12. Work Plan will consist of a narrative to describe work dates, times, personnel, and work activities per the work breakdown structure. As-builts, pictures, certifications, warranties, and other closeout materials are not part of the work plan but must be addressed in the technical solution and schedule.

13. The contractor shall commence with the work no later than 30 calendar days after NTP and complete the work within 450 calendar days of NTP.

14. The contractor is responsible for coordination of obtaining all required permits for completion of this work.

15. For purposes of the Sample Project price, the Offeror should assume that the on-site management team are locally based.

16. Construction work limited to eight hour days and a five day work week.

17. NTP assumed to be issued August 2027.

18. Utilize the below Davis-Bacon labor rates:

"General Decision Number: CO20260022 05/18/2026

State: Colorado

Construction Types: Building

Counties: Colorado Counties of El Paso

Modification Number Publication Date

0 01/02/2026 1 05/18/2026

ASBE0028-002 07/01/2025

Rates Fringes

ASBESTOS WORKER/HEAT & FROST INSULATOR - MECHANICAL

(DUCT, PIPE & MECHANICAL SYSTEM INSULATION).........$ 36.98 16.82

ELEC0113-005 06/01/2025

Rates Fringes

ELECTRICIAN (INCLUDES LOW VOLTAGE WIRING)...........$ 40.70 18.47

ELEV0025-001 01/01/2025

Rates Fringes

ELEVATOR MECHANIC FOOTNOTE: A.VACATION:

6%/UNDER 5 YEARS BASED ON REGULAR HOURLY RATE FOR

ALL HOURS WORKED. 8%/OVER 5 YEARS BASED ON REGULAR

HOURLY RATE FOR ALL HOURS WORKED. B. PAID

HOLIDAYS: NEW YEAR'S DAY; MEMORIAL DAY;

INDEPENDENCE DAY; LABOR DAY; VETERANS' DAY;

THANKSGIVING DAY; THE FRIDAY AFTER THANKSGIVING

DAY; AND CHRISTMAS DAY..............................$ 56.57 38.44

ENGI0009-017 05/01/2024

Rates Fringes

POWER EQUIPMENT OPERATOR: CRANE (91 TO 140 TONS)....$ 37.34

15.20

POWER EQUIPMENT OPERATOR: CRANE (51 TO 90 TONS).....$ 36.09

15.20

POWER EQUIPMENT OPERATOR: CRANE (50 TONS AND UNDER).$ 35.78

15.20

POWER EQUIPMENT OPERATOR: CRANE (141 TONS AND OVER).$ 39.80

15.20

IRON0024-009 11/01/2024

Rates Fringes

IRONWORKER: ORNAMENTAL..............................$ 39.21 12.50

IRON0024-011 11/01/2024

Rates Fringes

IRONWORKER, STRUCTURAL..............................$ 39.21 12.50

PAIN0079-009 08/01/2024

Rates Fringes

PAINTER (SPRAY).....................................$ 27.41 11.56

PLAS0577-002 05/01/2025

Rates Fringes

CEMENT MASON/CONCRETE FINISHER......................$ 34.73 15.15

PLUM0058-003 07/01/2025

Rates Fringes

PLUMBER (EXCLUDES HVAC DUCT, PIPE AND UNIT

INSTALLATION).......................................$ 47.60 18.10

PLUM0058-004 07/01/2025

Rates Fringes

PIPEFITTER, INCLUDES HVAC PIPE INSTALLATION

(EXCLUDES HVAC DUCT AND UNIT INSTALLATION)..........$ 47.60

18.10

SFCO0669-002 04/01/2025

Rates Fringes

SPRINKLER FITTER (FIRE SPRINKLERS)..................$ 48.60 27.57

SHEE0009-009 07/01/2025

Rates Fringes

SHEET METAL WORKER INCLUDES HVAC DUCT INSTALLATION

(EXCLUDES HVAC PIPE AND UNIT INSTALLATION)..........$ 43.05 22.65

SUCO2013-008 07/31/2015

Rates Fringes

TRUCK DRIVER: DUMP TRUCK...........................$ 17.34 0.00

SHEET METAL WORKER (HVAC UNIT INSTALLATION ONLY)....$ 24.00

2.18

ROOFER..............................................$ 16.71 0.00

PAINTER (BRUSH AND ROLLER)..........................$ 17.20 0.00

OPERATOR: GRADER/BLADE.............................$ 21.50 0.00

OPERATOR: BOBCAT/SKID STEER/SKID LOADER............$ 18.58 2.42

OPERATOR: BACKHOE/EXCAVATOR/TRACKHOE...............$ 20.26 8.62

LABORER: PIPELAYER.................................$ 16.96 3.68

LABORER: MASON TENDER - CEMENT/CONCRETE............$ 16.00 0.00

LABORER: MASON TENDER - BRICK......................$ 15.99 0.00

LABORER: COMMON OR GENERAL.........................$ 13.40 1.40

CARPENTER...........................................$ 22.63 6.98

BRICKLAYER..........................................$ 21.96 0.00

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at https://www.dol.gov/agencies/whd/government-contracts.

Note: Executive Order 13658 generally applies to contracts subject to the Davis-Bacon Act that were awarded on or between January 1, 2015 and January 29, 2022, and that have not been renewed or extended on or after January 30, 2022. Executive Order 13658 does not apply to contracts subject only to the Davis-Bacon Related Acts regardless of when they were awarded. If a contract is subject to Executive Order 13658, the contractor must pay all covered workers at least $13.65 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract from May 11, 2026, through December 31, 2026. The applicable Executive Order minimum wage rate will be adjusted annually.

Additional information on contractor requirements and worker protections under Executive Order 13658 is available at www.dol.gov/whd/govcontracts.

Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (iii)).

The body of each wage determination lists the classifications and wage rates that have been found to be prevailing for the type(s) of construction and geographic area covered by the wage determination. The classifications are listed in alphabetical order under rate identifiers indicating whether the particular rate is a union rate (current union negotiated rate), a survey rate, a weighted union average rate, a state adopted rate, or a supplemental classification rate.

Union Rate Identifiers

A four-letter identifier beginning with characters other than �SU�, �UAVG�, �SA�, or �SC� denotes that a union rate was prevailing for that classification in the survey. Example:

PLUM0198-005 07/01/2024. PLUM is an identifier of the union whose collectively bargained rate prevailed in the survey for this classification, which in this example would be Plumbers.

0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. The date, 07/01/2024 in the example, is the effective date of the most current negotiated rate.

Union prevailing wage rates are updated to reflect all changes over time that are reported to WHD in the rates in the collective bargaining agreement (CBA) governing the classification.

Union Average Rate Identifiers

The UAVG identifier indicates that no single rate prevailed for those classifications, but that 100% of the data reported for the classifications reflected union rates. EXAMPLE:

UAVG-OH-0010 01/01/2024. UAVG indicates that the rate is a weighted union average rate. OH indicates the State of Ohio.

The next number, 0010 in the example, is an internal number used in producing the wage determination. The date, 01/01/2024 in the example, indicates the date the wage determination was updated to reflect the most current union average rate.

A UAVG rate will be updated once a year, usually in January, to reflect a weighted average of the current rates in the collective bargaining agreements on which the rate is based.

Survey Rate Identifiers

The �SU� identifier indicates that either a single non-union rate prevailed (as defined in 29 CFR 1.2) for this classification in the survey or that the rate was derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As a weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SUFL2022-007 6/27/2024. SU indicates the rate is a single non-union prevailing rate or a weighted average of survey data for that classification. FL indicates the State of Florida. 2022 is the year of the survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. The date, 6/27/2024 in the example, indicates the survey completion date for the classifications and rates under that identifier.

�SU� wage rates typically remain in effect until a new survey is conducted. However, the Wage and Hour Division (WHD) has the discretion to update such rates under 29 CFR 1.6(c)(1).

State Adopted Rate Identifiers

The �SA� identifier indicates that the classifications and prevailing wage rates set by a state (or local) government were adopted under 29 C.F.R 1.3(g)-(h). Example: SAME2023-007 01/03/2024. SA reflects that the rates are state adopted. ME refers to the State of Maine. 2023 is the year during which the state completed the survey on which the listed classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination.

The date, 01/03/2024 in the example, reflects the date on which the classifications and rates under the �SA� identifier took effect under state law in the state from which the rates were adopted.

WAGE DETERMINATION APPEALS PROCESS

1) Has there been an initial decision in the matter? This can be:

a) a survey underlying a wage determination

b) an existing published wage determination

c) an initial WHD letter setting forth a position on a wage determination matter

d) an initial conformance (additional classification and rate) determination On survey related matters, initial contact, including requests for summaries of surveys, should be directed to the WHD Branch of Wage Surveys. Requests can be submitted via email to davisbaconinfo@dol.gov or by mail to:

Branch of Wage Surveys Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 Regarding any other wage determination matter such as conformance decisions, requests for initial decisions should be directed to the WHD Branch of Construction Wage Determinations.

Requests can be submitted via email to BCWD-Office@dol.gov or by mail to:

Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210

2) If an initial decision has been issued, then any interested party (those affected by the action) that disagrees with the decision can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7).

Requests for review and reconsideration can be submitted via email to dba.reconsideration@dol.gov or by mail to:

Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210 The request should be accompanied by a full statement of the interested party's position and any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.

3) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:

Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.

Washington, DC 20210.

END OF GENERAL DECISION

1. PROPOSAL FORMAT AND SUBMITTAL REQUIREMENTS
1.1. PROPOSAL FORMAT
1.2. SUBMITTAL REQUIREMENTS
1.3. INQUIRIES/QUESTIONS
Prospective Offerors shall submit contracting and technical inquiries and questions concerning this solicitation document via Bidder Inquiry in ProjNet at www.projnet.org/projnet.
1.4. VOLUME I, TAB 1 - FACTOR 4 – TECHNICAL APPROACH TO THE SAMPLE PROJECT
1.4.1. Submission Requirements
1.4.1.1 Designer(s)/A-E Service Capabilities
1.4.1.2 Project Schedule for Sample Project
1.5. VOLUME II, TAB 3 - FACTOR 5 – PRICE FOR THE SAMPLE PROJECT
1.5.1. Submission Requirements
1.5.1.1 Binding Maximum Labor Rate Schedule
1.5.1.2 Binding Maximum Indirect Rates
1.5.1.3 Sample Project Pricing

File details come from the government source that posted it. Updated .