FAR 52.211-10 Commencement, Prosecution, and Completion of Work

Clause Federal Acquisition Regulation Apr 1984 version

Facts

Citation
FAR 52.211-10
Type
Clause
Current version
April 1984
Prescribed in
FAR 11.404(b)
Alternates
Alternate I
Text as of
FAC 2026-01
Official text
acquisition.gov

Text from acquisition.gov. Federal Register history from the Federal Register's records of the rules that amended this clause.

Text

As prescribed in 11.404(b), insert the following clause in solicitations and contracts when a fixed-price construction contract is contemplated. The clause may be changed to accommodate the issuance of orders under indefinite-delivery contracts for construction.

Commencement, Prosecution, and Completion of Work (Apr 1984)

The Contractor shall be required to (a) commence work under this contract within [fill-in] calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than [fill-in].* The time stated for completion shall include final cleanup of the premises.

  • The Contracting Officer shall specify either a number of days after the date the contractor receives the notice to proceed, or a calendar date.

(End of clause)

Alternate I (Apr 1984)

Alternate I (Apr 1984). If the completion date is expressed as a specific calendar date, computed on the basis of the contractor receiving the notice to proceed by a certain day, add the following paragraph to the basic clause:

The completion date is based on the assumption that the successful offeror will receive the notice to proceed by [fill-in]. The completion date will be extended by the number of calendar days after the above date that the Contractor receives the notice to proceed, except to the extent that the delay in issuance of the notice to proceed results from the failure of the Contractor to execute the contract and give the required performance and payment bonds within the time specified in the offer.

Quick answers

What is FAR 52.211-10?

FAR 52.211-10 is a clause of the Federal Acquisition Regulation, titled "Commencement, Prosecution, and Completion of Work".

What is the current version of FAR 52.211-10?

The current version is dated April 1984.

Where is FAR 52.211-10 prescribed?

It is prescribed in FAR 11.404(b), Contract clauses.

Are changes to FAR 52.211-10 proposed?

No proposed rule from the last 3 years is waiting on a final rule.

On GovTribe

Follow the rules behind federal contracts

  • Search Federal Register rules and proposed rules for the FAR, DFARS and agency supplements
  • Solicitations, awards and government files in one search
  • Ask GovTribe AI about the rules that apply to a contract