About this opportunity

Northern Wasco County People's Utility District (NWCPUD) is soliciting bids through an Invitation to Bid for the Rowena Line Rebuild, with bids due December 22, 2026. The work rebuilds aged 12.47 kV distribution line between The Dalles and Rowena in Wasco County, Oregon, and requires a Union Pacific Railroad crossing permit and National Scenic Area permit adherence.

The scope covers approximately five miles of feeder distribution line along Highway 30 and cross-county routes. It includes removing and replacing 93 distribution poles per the Personal Services Agreement (Attachment A), converting eleven H-frame structures to single-pole configurations, installing new distribution conductor, modifying guy wires and anchors, transferring existing transformers and customer services, and restoring disturbed areas. NWCPUD furnishes poles, conductors, crossarms, insulators, and transformers, and the contractor handles transport and proper handling. Staking sheets (Attachment K) show approximately 85 pole replacements and Attachment E lists 80 primary pole locations, so bidders should reconcile pole counts before pricing.

Work must comply with NWCPUD Construction Unit Standards, Oregon OSHA requirements, the National Electrical Safety Code, and the Manual on Uniform Traffic Control Devices. The Union Pacific crossing at Mile Post 80.92 on the Portland Subdivision near Crates requires a Contractor's Right of Entry Agreement, a $1,000 administrative fee, Railroad Protective Liability of $2 million per occurrence and $6 million aggregate, and at least ten working days' notice before construction begins. Required contractor insurance includes commercial general liability of at least $2 million per occurrence and automobile liability of $1 million. All workers are subject to prevailing wage compliance. Fire prevention planning and coordination with NWCPUD operations for service interruptions are also required.

Compensation is a lump-sum contract amount plus a unit rate for rock excavation billed by actual locations. Materials, direct expenses, and subconsultant invoices are reimbursed at cost plus ten percent, with receipts required. Bidders must submit a bid bond at 5% of the bid amount. Completion is required within 120 calendar days of execution. The agreement expires upon final acceptance or December 31, 2027, whichever occurs first, and the district may terminate on thirty days' written notice.

Opportunity text

a. Northern Wasco County People's Utility District (hereinafter called "District") issues this ITB soliciting the Rowena Line Rebuild. Northern Wasco County Public Utility District (NWCPUD) owns and operates an electric distribution system serving from The Dalles to Rowena. Portions of the existing 12.47 kV distribution system along Highway 30 and cross county have reached the end of their service life and require replacement to maintain system reliability and safety.