Bid Schedule - Internal Use Only.xlsx

XLSX spreadsheet 19 KB Posted

Attached to
Rowena Line Rebuild
Solicitation number
S-R33123-00018440
Issued by
Wasco County, Oregon

About this file

I appreciate your detailed instructions, but I'm unable to access or read the contents of the file you've referenced. While you've provided the GovTribe ID and filename ("Bid Schedule - Internal Use Only.xlsx"), the actual file content has not been included in our conversation for me to analyze.

To provide the comprehensive summary you've requested, please share the file contents directly by either:

  • Copying and pasting the text or data from the Excel file
  • Providing a detailed description of the file's contents
  • Sharing the relevant information in another accessible format

Once you provide the actual file data, I will immediately deliver a professional two-paragraph summary following your specified format and requirements.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Columbia Heights Substation

ACQUISITION SCHEDULE

ITB#2026011 - Rowena Line Rebuild

LineDescriptionNotes/ScheduleResponsible PersonDone
1Requesting DepartmentEngineeringJeff Handley
2Contact Person & Phone #Jeff Handley
3Estimated Cost
4SOW Received9/16/26Jeff Handleyx
5Specifications Received9/16/26Jeff Handleyx
6Draft Solicitation Document10/22/26Cole Isaacson
7Source List/Interested Vendors10/29/26Jeff Handley
8Purchaser Sign-Off on Solicitation Doc11/2/26Cole Isaacson
9Final Solicitation Document11/11/26Cole Isaacson
10Post in OregonBuys/Release11/12/26Cole Isaacson
11Bid Package Posted on District Website11/12/26Cole Isaacson
12Reserved Room for Bid Opening: YES/NONo
13Mandatrory Job-Walk YES/NO
14Job-Walk Date11/24/26Jeff Handley
15Job-Walk Time9:00 AM
16Job-Walk LocationBoard Room
17Last Day to Submit Questions is: 4:00 PM12/9/26
18Last Day to Respond to Questions 4:00 PM12/16/26Cole Isaacson
21Bid Opening LocationBoard Room
22Bid Opening Date12/22/26Cole Isaacson
23Bid Opening Time2:00pm
24Responsiveness Review1/5/27Cole Isaacson
25Issue Notice of Intent to Award1/5/26Cole Isaacson
26Protest Period Starts (7 Calendar Days)1/5/26
27Protest Period Ends (End of Calendar Day)1/12/26
28Cut-off to Submit Item to Board
29Award @ Board Mtg.1/5/26Cole Isaacson
30Issue Contract/Purchase Order To Vendor/Contractor by1/12/26Cole Isaacson
31Contract Returned
32Executed Contract - Purchase Order
33Issue Notice to Proceed
34Project Complete