Bid Schedule - Internal Use Only.xlsx
XLSX spreadsheet 19 KB Posted
- Attached to
- Rowena Line Rebuild
- Solicitation number
- S-R33123-00018440
- Issued by
- Wasco County, Oregon
About this file
I appreciate your detailed instructions, but I'm unable to access or read the contents of the file you've referenced. While you've provided the GovTribe ID and filename ("Bid Schedule - Internal Use Only.xlsx"), the actual file content has not been included in our conversation for me to analyze.
To provide the comprehensive summary you've requested, please share the file contents directly by either:
- Copying and pasting the text or data from the Excel file
- Providing a detailed description of the file's contents
- Sharing the relevant information in another accessible format
Once you provide the actual file data, I will immediately deliver a professional two-paragraph summary following your specified format and requirements.
View the file
Other files
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Columbia Heights Substation
ACQUISITION SCHEDULE
ITB#2026011 - Rowena Line Rebuild
| Line | Description | Notes/Schedule | Responsible Person | Done |
| 1 | Requesting Department | Engineering | Jeff Handley | |
| 2 | Contact Person & Phone # | Jeff Handley | ||
| 3 | Estimated Cost | |||
| 4 | SOW Received | 9/16/26 | Jeff Handley | x |
| 5 | Specifications Received | 9/16/26 | Jeff Handley | x |
| 6 | Draft Solicitation Document | 10/22/26 | Cole Isaacson | |
| 7 | Source List/Interested Vendors | 10/29/26 | Jeff Handley | |
| 8 | Purchaser Sign-Off on Solicitation Doc | 11/2/26 | Cole Isaacson | |
| 9 | Final Solicitation Document | 11/11/26 | Cole Isaacson | |
| 10 | Post in OregonBuys/Release | 11/12/26 | Cole Isaacson | |
| 11 | Bid Package Posted on District Website | 11/12/26 | Cole Isaacson | |
| 12 | Reserved Room for Bid Opening: YES/NO | No | ||
| 13 | Mandatrory Job-Walk YES/NO | |||
| 14 | Job-Walk Date | 11/24/26 | Jeff Handley | |
| 15 | Job-Walk Time | 9:00 AM | ||
| 16 | Job-Walk Location | Board Room | ||
| 17 | Last Day to Submit Questions is: 4:00 PM | 12/9/26 | ||
| 18 | Last Day to Respond to Questions 4:00 PM | 12/16/26 | Cole Isaacson | |
| 21 | Bid Opening Location | Board Room | ||
| 22 | Bid Opening Date | 12/22/26 | Cole Isaacson | |
| 23 | Bid Opening Time | 2:00pm | ||
| 24 | Responsiveness Review | 1/5/27 | Cole Isaacson | |
| 25 | Issue Notice of Intent to Award | 1/5/26 | Cole Isaacson | |
| 26 | Protest Period Starts (7 Calendar Days) | 1/5/26 | ||
| 27 | Protest Period Ends (End of Calendar Day) | 1/12/26 | ||
| 28 | Cut-off to Submit Item to Board | |||
| 29 | Award @ Board Mtg. | 1/5/26 | Cole Isaacson | |
| 30 | Issue Contract/Purchase Order To Vendor/Contractor by | 1/12/26 | Cole Isaacson | |
| 31 | Contract Returned | |||
| 32 | Executed Contract - Purchase Order | |||
| 33 | Issue Notice to Proceed | |||
| 34 | Project Complete |