About this file
This document is a pole GPS location inventory and modification schedule for a utility infrastructure project involving the upgrading and reconfiguration of electrical transmission poles across multiple jurisdictions in the Pacific Northwest region. The project encompasses 80 primary pole locations plus numerous auxiliary poles (identified with suffix designations such as A, H, and intermediate numbers), spanning from urban areas to agricultural zones and right-of-way corridors along Interstate 84 and Highway 30. The scope of work includes replacing poles with higher-class structures, installing new guy anchors at specified distances and bearings, removing obsolete anchoring systems, and converting several H-style structures to single-pole configurations. Each pole is precisely located using latitude and longitude coordinates and associated with specific tax lots and zoning designations including GMA Urban Areas, GMA Open Space, GMA R-5, GMA A-1 and A-2 zones, and SMA Public Recreation and Agricultural areas.
The document provides technical specifications for each pole location, including current pole height and class designations (such as P40, P45, P55, P65, P70), new pole specifications (PI45-3, PI50-3, PI55-3, PI60-3, PI65-3), and detailed anchor installation and removal requirements with directional bearings and distances measured in feet and compass degrees. Notable structural modifications include changing multiple poles from H-style to single-pole configurations with corresponding anchor adjustments, installing new poles at previously unoccupied locations (such as pole 43.5 and 44.5A), and removing obsolete guy anchors. The project involves coordination across multiple zoning categories and right-of-way jurisdictions, with tax lot acreages ranging from 100 to 2,900 acres, indicating a substantial geographic scope requiring careful compliance with local land use regulations and easement requirements.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Attachment C - National Scenic Area Permit.pdf | ||
| Attachment B - Union Pacific Railroad Permit.pdf | ||
| Attachment E1 - Pole GPS Location kmz.kmz | KMZ file | |
| Attachment F - Construction Units.csv | CSV file | |
| 02 - Bid Form.docx | DOCX document | |
| Attachment I - OLD PUD SPEC.pdf | ||
| Attachment K - Staking Sheets.pdf | ||
| Attachment D - NWCPUD Construction Standards.pdf | ||
| Attachment A - Agreement.pdf | ||
| Attachment H - Sag and Tension Table.pdf | ||
| Bid Schedule - Internal Use Only.xlsx | XLSX spreadsheet | |
| Attachment J - DWG File.dwg | DWG drawing | |
| Attachment G - Bonds.pdf | ||
| 01 - ITB - Rowena Rebuild.pdf |
Show all 14
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ZONING
REFRENCE
NUMBER
MAPNUMBER
CURRENT POLE HIGHT
AND CLASS
NEW POLE HIGHT
AND CLASS
GUYS BEING
REMOVED/INSTALLED
GUY LOCATIONS LATITUDE LONGITUDE TAX LOT NOTES
(GMA) URBAN AREAS 6 232112090 P40-2 PI45-3 45.63797548 -121.206864 2N 13E 21 600
(GMA) URBAN AREAS 7 232111120 P45-2 PI55-3 45.63865702 -121.207126 2N13E 21 C 2900
(GMA) URBAN AREAS 8 232111130 P40-2 PI45-3 45.63932427 -121.207373 2N 13E 21 600
(GMA) URBAN AREAS 9 232110150 P55-4 PI55-3 45.63995233 -121.207609 2N 13E 21 600
(GMA) OPEN SPACE 10 232110170 P55-4 PI50-3 45.64047344 -121.207811 2N 13E 21 100
(GMA) OPEN SPACE 11 232109190 P50-2 PI55-3 45.64102954 -121.208006 2N 13E 21 100
(GMA) OPEN SPACE 12 232108220 P50-2 PI60-3 45.64143518 -121.208171 2N 13E 21 100
(GMA) OPEN SPACE 13 232108240 P55-2 PI55-3
TWO ANCHORS REMOVED
TWO ANCHORS INSTALLED
20' @ 345° 20' @103°
45.64198804 -121.20839 2N 13E 21 100
(GMA) OPEN SPACE 14 232106250 P55-2 PI55-3 45.64207857 -121.208818 N/A INTERSTATE 84 RIGHT-OF-WAY
(GMA) A-1 (160) 15 232104260 P70-1 NO CHANGE
ONE ANCHOR REMOVED
THREE ANCHORS
INTALLED
20' @ 283° 20' @ 214° 20' @120°
45.64224094 -121.209796 N/A INTERSTATE 84 RIGHT-OF-WAY
(GMA) R-5 16 232103280 P55-3 PI45-3 45.64283467 -121.21038 2N 13E 21 400
(GMA) R-5 17 232101300 P55-4 PI55-3 45.64340497 -121.21093 2N 13E 21 400
(GMA) R-5 18 232100320 P50-1 PI45-3 45.64399576 -121.211461 2N 13E 21 400
(GMA) R-5 21 232050381 P50-3 PI50-3 NEW ANCHOR INSTALLED 15' @ 179° 45.64532845 -121.21229 N/A HIGHWAY 30 RIGHT-OF-WAY
(GMA) R-5 22 232050390 P45-4 PI45-3 INSTALL NEW ANCHOR 15' @ 349° 45.64595031 -121.212337 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 23 232050420 P45-4 PI45-3 45.64650912 -121.212355 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 24 232051420 P40-4 PI45-3 45.64701604 -121.212362 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 25 232050440 P45-4 PI45-3 45.6475223 -121.21237 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 26 232050470 P45-4 PI45-3 45.64813153 -121.212373 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 27 232050500 P45-3 PI45-3 45.64893618 -121.212381 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 28 232050520 P45-3 PI45-3 45.64959092 -121.212393 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 29 231750020 P45-3 PI45-3 45.65019869 -121.212414 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 30 231750040 P40-4 PI50-3 45.65081652 -121.212417 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 31 231752070 P45-2 PI45-3 45.65159607 -121.212442 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) R-5 32 231750090 P45-2 PI45-3 45.65220129 -121.212512 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) A-2 (40) 33 231749110 P45-2 PI45-3 45.65283958 -121.212567 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) A-2 (40) 34 231749140 P45-4 PI45-3 45.65356139 -121.212652 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) A-2 (40) 35 231749160 P45-4 PI45-3 INSTALL NEW ANCHOR 15' @ 145° 45.65423791 -121.212712 N/A HIGHWAY 30 RIGHT-OF-WAY
(GMA) A-2 (40) 36 231749190 P45-4 PI45-3
ONE ANCHOR REMOVED
TWO ANCHORS INSTALLED
20' @ 72° 20' @ 355°
45.65501944 -121.212795 N/A HIGHWAY 30 RIGHT-OF-WAY
(GMA) A-2 (40) 37 231748210 P45-4 PI45-3 INSTALL NEW ANCHOR 15' @ 58° 45.65562354 -121.213362 2N 13E 17 D 100
(GMA) A-2 (40) 38 231746230 P55-4 PI60-3 45.65620685 -121.213986 2N 13E 17 D 100
(GMA) A-2 (40) 39 231744260 P45-4 PI50-3
INSTALL TWO NEW
ANCHOR
20' @ 145° 20' @ 107°
45.65691526 -121.214613 2N 13E 17 AD 200
(GMA) A-2 (40) 40 231741300 P55-4 PI55-3 INSTALL ONE ANCHOR 25' @ 146° 45.65802616 -121.215659 2N 13E 17 AD 101 H STRUCTUR (GMA) A-2 (40) 41 231736380 P50-4 PI55-3 INSTALL ONE ANCHOR 30' @ 327° 45.66010565 -121.217656 2N 13E 17 AC 100 H STRUCTUR
(GMA) A-2 (40) 42 231733420 P55-4 PI50-3 ADD TWO NEW ANCHORS
20' @ 56° 20' @ 338°
45.66116148 -121.218728 2N 13E 17 AB 200
CHANGING STRUCTURE FROM H STYLE TO
SINGLE POLE. REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-2 (40) 43 231732440 P55-3 PI50-3 ADD GUY WIRE 15' @ 30.5° 45.66197673 -121.219472 2N 13E 17 AB 100
CHANGING STRUCTURE FROM H STYLE TO
SINGLE POLE. REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-2 (40) 43.5 231731461 NONE PI45-3 45.662503 -121.220017 2N 13E 17 AB 100 NEW POLE AND LOCATION
(GMA) A-2 (40) 44 231729480 P45-4 PI45-3
ADD TWO NEW GUY
ANCHORS
15' @ 101° 25' @ 34°
45.66305785 -121.220529 2N 13E 17 AB 100
CHANGING STRUCTURE FROM H STYLE TO
SINGLE POLE. REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-2 (40) 44.5 231727510 P40-4 NO CHANGE 45.66370101 -121.221109 2N 13E 17 AB 100 TAP LINE TO SERVICE
(GMA) A-2 (40) 45 231723500 P45-4 PI45-3 ADD NEW GUY ANCHOR 25' @ 28° 45.66338212 -121.222844 2N 13E 17 B 100
CHANGING STRUCTURE FROM H STYLE TO
SINGLE POLE. REMOVE SEVERAL OLD GUY
WIRES
(SMA) PUBLIC REC 46 231720500 P65-2 PI55-3 REMOVE GUY ANHOR 45.66355082 -121.22403 2N 13E 17 B 100 (SMA) PUBLIC REC 47 231718510 P45-4 PI45-3 45.6636603 -121.224997 2N 13E 17 B 100
(SMA) PUBLIC REC 48 231715510 P45-2 PI45-3 45.66382082 -121.226105 2N 13E 17 B 100
(SMA) PUBLIC REC 49 231714520 P45-4 PI50-3
REMOVE GUY ANHOR AND
ADD GUY ANCHOR
15' @ 203° 45.66393028 -121.226995 2N 13E 17 B 100
(SMA) PUBLIC REC 50 230811000 P45-2 PI50-3 45.66426201 -121.227639 2N 13E 8 200
(SMA) PUBLIC REC 51 230809010 P45-4 PI45-3 45.66474324 -121.228654 2N 13E 8 200
(SMA) PUBLIC REC 52 230806040 P45-4 PI50-3 45.66521394 -121.229611 2N 13E 8 200
(SMA) PUBLIC REC 53 230802040 P50-4 PI45-3 ADD 1 GUY ANCHOR 25' @ 94° 45.66531222 -121.230789 2N 13E 8 200
H STRUCUTURE / REMOVE SEVERAL OLD
GUY WIRES
(SMA) AG 54 230747040 P60-2 PI45-3 ADD 1 GUY ANCHOR 20' @ 274° 45.66550155 -121.234227 2N 13E 8 200
H STRUCUTURE / REMOVE SEVERAL OLD
GUY WIRES
(SMA) AG 55 230745050 P60-3 PI50-3 45.6656765 -121.235196 2N 13E 7 500
(SMA) AG 56 230742060 P50-4 PI60-3 45.66584124 -121.236125 2N 13E 7 500
(SMA) AG 57 230740070 P45-4 PI50-3 45.66604415 -121.237093 2N 13E 7 500
(SMA) AG 58 230737080 P55-2 NO CHANGE 45.6662485 -121.238069 2N 13E 7 400
(SMA) AG 59 230735080 P45-2 PI45-3 45.66643034 -121.239065 2N 13E 7 400
(SMA) AG 60 230733090 P45-2 PI45-3 45.66667234 -121.240113 2N 13E 7 400
(GMA) A-1 (160) 61 230731100 P55-4 PI60-3 45.66679528 -121.240846 2N 13E 7 400
(GMA) A-1 (160) 62 230728100 P45-2 PI50-3 45.66705425 -121.241989 2N 13E 7 300
(GMA) A-1 (160) 63 230726110 P45-4 PI45-3 45.66716942 -121.242667 2N 13E 7 300
(GMA) A-1 (160) 64 230723120 P45-4 PI50-3 45.66738355 -121.243597 2N 13E 7 300
CHANGING STRUCTURE FROM H STYLE TO
SINGLE POLE. REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-1 (160) 65 230721130 P45-4 PI50-3 45.66753797 -121.244512 2N 13E 7 300
(GMA) A-1 (160) 66 230719130 P45-4 PI45-3 45.66770862 -121.245285 2N 13E 7 300
(GMA) A-1 (160) 67 230718130 P45-4 PI45-3 ADD NEW ANCHORS 20' @ 102° 45.66787181 -121.245952 2N 13E 7 300
H STRUCTUR / REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-1 (160) 68 230712150 P45-4 PI45-3 ADD NEW ANCHORS 20' @ 282° 45.66823672 -121.248549 2N 13E 7 200
H STRUCTUR / REMOVE SEVERAL OLD GUY
WIRES
(GMA) A-1 (160) 69 230709160 P45-4 PI45-3 45.66834089 -121.249395 2N 13E 7 200
(GMA) A-1 (160) 70 230706160 P45-4 PI45-3 45.66845725 -121.250292 2N 13E 7 200
(GMA) A-1 (160) 71 230703170 P45-4 PI45-3 45.66859188 -121.25138 2N 13E 7 200
(GMA) A-1 (160) 72 230701170 P45-4 PI45-3 45.66873836 -121.252155 2N 13E 7 200
(GMA) A-1 (160) 73 221253170 P50-2 PI45-3 45.66884399 -121.25296 2N 12E 12 D 100
(GMA) A-1 (160) 74 221250180 P45-4 PI45-3 45.66900782 -121.254104 2N 12E 12 D 100
(GMA) R2 75 221248180 P50-2 PI45-3 45.66910792 -121.25501 2N 12E 12 DA 400
(GMA) R2 76 221245190 P45-4 PI45-3 45.6692955 -121.256014 2N 12E 12 D 200
(GMA) R2 77 221242190 P45-4 PI50-3 45.66942153 -121.256968 2N 12E 12 D 200
(GMA) R2 78 221240200 P45-4 PI65-3 45.66954704 -121.257916 2N 12E 12 D 200
(GMA) R2 80 221237200 P45-4 PI50-2
ADD AND REMOVE
ANCHORS
20' @ 234.5° 45.66967828 -121.258863 2N 12E 12 DB 1300
(GMA) R-5 19 232051350 P50-1 PI50-3
ONE ANCHOR REMOVED
ONE ANCHOR INSTALLED
15' @ 246° 45.64458604 -121.212014 2N 13E 21 400
(GMA) R-5 20 232050360 P55-2 PI50-3 ONE ANCHOR INSTALLED 15' @ 166° 45.64498462 -121.212171 2N 13E 21 400
(GMA) R-5 20A 232052360 P35-4 NO CHANGE 45.645004 -121.211602 2N 13E 21 400 GUY POLE (GMA) A-1 (160) 21A 232049370 P30-6 NO CHANGE 45.655208 -121.212023 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) A-1 (160) 23A 232049420 P25-6 NO CHANGE 45.655208 -121.212023 N/A HIGHWAY 30 RIGHT-OF-WAY (GMA) A-1 (160) 27A 232049500 P30-4 NO CHANGE 45.648858 -121.212567 N/A HIGHWAY 30 RIGHT-OF-WAY (SMA) PUBLIC REC 36A 231750190 P25-6 REMOVE 45.655208 -121.212023 N/A INTERSTATE 84 RIGHT-OF-WAY (GMA) A-2 (40) 40H 231741301 P55-4 PI55-3 INTALL ONE ANCHOR 25' @ 146° 45.65802616 -121.215659 2N 13E 17 AD 100 (GMA) A-2 (40) 41.5 231736350 P40-4 NO CHANGE 45.660106 -121.217656 2N 13E 17 AC 100 TAP LINE TO SERVICE (GMA) A-2 (40) 41H 231736381 60-3 PI55-3 INSTALL GUY 30' @ 327° 45.660082 -121.217689 2N 13E 17 AC 100
(GMA) A-2 (40) 42H 231733421 P55-3 REMOVE 45.661185 -121.218695 2N 13E 17 AB 200
(GMA) A-2 (40) 43H 231732441 P55-3 REMOVE 45.661953 -121.219505 2N 13E 17 AB 100
(GMA) A-2 (40) 44.5A 231727491 NONE PI50-3 45.663219 -121.221678 2N 13E 17 AB 100 NEW POLE AND LOCATION
(GMA) A-2 (40) 44H 231729481 P45-4 REMOVE 45.663034 -121.220562 2N 13E 17 AB 100
(GMA) A-2 (40) 45H 231723501 P45-3 REMOVE 45.663382 -121.222844 2N 13E 17 B 100
(SMA) PUBLIC REC 52A 230806041 P30-4 PI35-3 NEW ANCHOR INSTALLED 20' @ 29° 45.665283 -121.229587 2N 13E 8 200 GUY POLE
(SMA) PUBLIC REC 53H 230802441 P45-3 PI45-3 NEW ANCHOR INSTALLED 25' @ 94° 45.66528 -121.2308 2N 13E 8 200
(SMA) AG 54H 230747041 P60-2 PI45-3 NEW ANCHOR INSTALLED 20' @ 274° 45.665469 -121.234237 2N 13E 8 200
Intentionally left Blank
(GMA A-1 (160) 67H 230718131 P45-4 PI45-3 NEW ANCHOR INSTALLED 20' @ 102° 45.667841 -121.245968 2N 13E 7 300 REMOVE SEVERAL GUYS
(GMA) A-1 (160) 68H 230712151 45-4 PI45-3 NEW ANCHOR INSTALLED 20' @ 282° 45.668206 -121.248566 2N 13E 7 200