Intersection Signalization Project: US 98 at Church Street and Moll Drive

Closed State & local contract opportunity

Solicitation number
ITB 24-42
State
Florida
Responses due

Opportunity facts

Jurisdiction
Point of contact

Opportunity details come from procurement.opengov.com. Updated .

About this opportunity

Walton County, Florida is soliciting bids for the Intersection Signalization Project at US Highway 98 and Moll Drive/Church Street in Santa Rosa Beach, a construction procurement focused on improving traffic infrastructure. The project involves constructing signalization improvements, including mast arm foundation construction, mast arm installation, electrical work, and pavement markings to create a signalized intersection. Bidders must demonstrate qualifications by proving successful construction of at least 5 new signalized intersections on FDOT facilities within the past 5 years. The Invitation to Bid (ITB 24-42) was released on October 29, 2024, with responses due on December 2, 2024, at 3:00 pm through the county's e-Procurement Portal. A non-mandatory pre-bid conference is scheduled for November 6, 2024. Evaluation criteria will focus on selecting the lowest, most responsible and responsive bidder, with a bid security requirement of 5% of the base bid price. The contract duration is specified as 90 calendar days for substantial completion, with an additional 30 days allocated for punch list completion.

No specific set-aside designations or restrictions for disadvantaged enterprises were explicitly mentioned in the procurement documents. The project will utilize Florida Department of Transportation (FDOT) standards, requiring specific equipment such as a McCain NEMA TS2 Type 2 Cabinet and adherence to detailed technical specifications outlined in the Walton County Technical Special Provision. Liquidated damages are established at $1,685 per day for failure to achieve substantial completion and $842.50 per day for incomplete punch list items. While a specific total project budget is not disclosed, the comprehensive documentation and technical requirements suggest a complex engineering project with multiple technical considerations. The procurement will include a "Limited" Notice to Proceed for long lead time materials procurement, with final proceed authorization contingent upon material verification. The project involves comprehensive insurance requirements, performance and payment bonds, and compliance with regulatory standards including public records laws and E-Verify employment eligibility verification.

Opportunity text

The proposed project, hereinafter referred to as the "Project" consists of the construction of signalization improvements at the existing intersection of US Hwy 98 and Moll Drive/Church Street. The project is located in Santa Rosa Beach on US Hwy 98 approximately 3.48 miles west of the US 98/US 331 intersection in South Walton County. The construction activities will include mast arm foundation construction, mast arm installation, electrical work, pavement markings, etc. to provide a signalized intersection in accordance with the design plans and specifications.

Location:

Contract Time: The contract duration is NINETY (90) days to substantial completion with an additional THIRTY (30) days for punch list completion.

Long Lead Time Materials: A "Limited" Notice to Proceed shall serve as authorization for procurement of only the long lead time materials identified therein. This "Limited" Notice to Proceed has no effect on the contract time for this Project. County must be provided with an estimated delivery date in writing from the supplier of the long lead time materials. Following receipt of these materials, a pay application may be submitted for stored materials prior to beginning performance. The County will verify the amount of materials received prior to issuing the "Final" Notice to Proceed.