Eagle Mountain City is requesting proposals for 100% design and engineering of a sewer trunkline and effluent disposal line, with proposals due November 4, 2026 at 12:00 p.m. through the State of Utah's Public Procurement Portal and anticipated award on November 12, 2026.
The scope advances a project from 30% design to full 100% design completion within 180 days of contract execution. Deliverables include 13 tasks spanning project management, data collection, hydraulic evaluation, alignment development, pipeline and appurtenance design, utility conflict analysis (including coordination with Kern River Gas and existing developer agreements), geotechnical investigation (up to 20 bore holes with estimated costs ranging from $16,000 to over $40,000), right-of-way and property impact assessment, environmental and permitting review, construction phasing analysis, opinion of probable construction costs, and preparation of final 100% design drawings and bid documents in PDF and editable CAD format, plus complete bid documents and specifications and a comprehensive engineering report. Final deliverables are due March 1, 2027.
The 30% design identified approximately 3.7 miles of required utility corridor easements, with the East Trunkline requiring upsizing of existing 24" pipeline to 30" pipe and an estimated construction cost of $21.5 million, and the Tickville Reuse Discharge Pipeline estimated at $13.8 million (both 2026 dollars, excluding pump station costs).
Evaluation weights firm experience (25%), project team experience (25%), functional approach (20%), technical approach (17%), cost (10%), and introductory letter completeness (3%). Proposals must not exceed 15 single-sided pages in 11- or 12-point font. Vendors must register with Eagle Mountain City and submit a W-9 form prior to proposal submission. Insurance requirements include General Liability ($1,000,000 per occurrence/$3,000,000 aggregate), Commercial Automobile ($1,000,000 combined single limit), Professional Liability ($1,000,000 per claim/$3,000,000 aggregate), valuable papers and records coverage, and workers compensation with A.M. Best A-class VIII rating or better. Insurance verification must accompany the bid; a Certificate of Insurance is required at contract signing. All proposals become City property subject to disclosure under Utah's Government Records Access and Management Act.
Opportunity text
Eagle Mountain City is a rapidly growing municipality with a current population of approximately 75,000 residents. Growth projections and system capacity analyses have identified the need for construction of a new sewer trunkline to serve existing and future development areas. A 30% design of the project has been done that incorporates an effluent discharge line to run in tandem with the trunkline for the majority of its path. Eagle Mountain City is requesting proposals from responsible firms or individuals for advancing the Sewer Trunkline and Effluent disposal line to a 100% Design. The Consultant shall furnish all labor, supervision, materials, equipment, and incidentals necessary to complete the following tasks within 180 days of contract execution. ATTENTION: The following documents will be required with bidding documents and/or with a contract award. **Insurance verification with bid, Certificate of Insurance at contract signing** Any bid / proposal received after the scheduled closing time for receipt of bids will not be considered. OPENING OF BIDS / PROPOSALS: Bids / proposals will be opened on or around the closing date and time. Results will be posted after bids / proposals have been evaluated. Vendors who submit a bid / proposal will be notified of the results via email. The email will include a spreadsheet of all vendors, and the amounts of the bids / proposals submitted for the project. Please include the name and email address of your contact person in the cover letter so we can send the notification of bid results. Bids/ proposals will also be posted on Eaglemountaincity.com/purchasing. Once a vendor is chosen for the awarded contract all vendors will be notified of the vendor who will be awarded the contract. The chosen vendor will submit the remaining required insurance, bonds, and other required documentation with a signed contract.
Files
On GovTribe
Work this opportunity
- Track it in your pipeline
- Similar opportunities
- Ask GovTribe AI about this opportunity