The City of Danville, Illinois is requesting proposals under RFP #810 for the 2 West Main roof replacement, with the RFP opening at 10:00 a.m. on October 29, 2026, at the City Clerk's office, 17 W. Main Street, Danville, Illinois 61832. All work must comply with the Illinois Prevailing Wage Act and pay Illinois prevailing wage rates to all laborers.

The scope removes the existing PVC roof system to the underlying insulation and hauls it off site, then installs a single layer of 1.5-inch polyisocyanurate insulation topped with 50 mil white Duro-Last single-ply thermoplastic membrane. The membrane is mechanically fastened using Duro-Last-approved fasteners and poly plates. Additional work includes custom Duro-Last flashings for stacks, vents, and parapet walls, with parapets anchored by 4-inch two-piece compression metal and decorative covers; walkway pads at access points and HVAC service ends; custom drain sleeves with a new metal dome strainer on interior drains; and two-way vents at one per 1,000 square feet. The contractor supplies its own construction equipment.

Proposals are priced per square foot across approximately 15,000 square feet of roof area. Additional walkway pads requested by the building owner are priced at $12.40 per lineal foot. The City intends to have all work completed no later than April 1, 2027.

RFP security equals 5% of the total bid, provided either as a bid bond from an Illinois-licensed surety or as a cashier's check payable to the City of Danville, and the City retains the successful bidder's security until contract execution and project completion. Bidders must submit a Vendor's Sworn Statement confirming they are not delinquent on taxes administered by the Illinois Department of Revenue, and omission results in rejection. Bidders on contracts exceeding $20,000 must submit the Employer Certificate of Compliance Report Form and Workforce Profile Addendum. Bidders must also provide a copy of their sexual harassment policy or establish one within 60 days of submission. The contractor must carry $1 million in comprehensive general liability, automobile, and workers' compensation coverage, naming the City of Danville as additional insured. The manufacturer warranty is 20 years with no dollar limit on repairs or replacement, and the contractor warrants the installation for two years from the manufacturer warranty's effective date.

Questions had to be submitted in writing at least five days before the opening using the Request for Information Form, and oral instructions do not form part of the bidding documents. Bidders must confirm addenda within 72 hours before the opening by contacting Paul Storke at (217) 508-6316 or paul.storke@cityofdanville.org.

Opportunity text

Roof Assembly PVC thermoplastic membrane a. Membrane Thickness: 50 mil b. Color: White c. Attachment: Attached with mechanical fasteners. 1. Barricade off the working area. 2. Dispose of all construction materials. 3. Provide your own equipment for construction. 4 Remove existing PVC roof system to underlying insulation, remove from job site for disposal. 5 Install a single layer of 4x8 sheets of 1.5 polyisocyanurate insulation over roof surface, anchoring each sheet with six fasteners and poly plates. 6 Roof with Duro-Last single ply 50 mil membrane in white, anchoring to roof deck per warranted specifications. Fasteners will be Duro-Last approved with poly plates. 7 Flash all roof obstructions with custom made Duro-Last components - stacks, vents, parapet walls, etc., per manufacturers specifications. - Parapet walls will be flashed over top of wall to exterior surface, and will be anchored with 4" 2-piece compression metal with decorative cover in clients choice of Duro-Last colors. - Protective walkway pads will be installed at the top and bottom of all access points including ladders and hatches and at the service end of all HVAC equipment. Additional walkway pads will be installed at the cost of $12.40/lineal foot at the request of the building owner. - Interior roof drains will have custom built Duro-Last drain sleeves installed per warranted specifications, and a new metal dome strainer will be installed. 8 Install two way vents at the density of one per 1000 square feet for the relief of humidity developed within the roof system during winter use of the structure.

Files

File Type Posted
city of danville RFP Packet - 2 West Main Project.pdf PDF

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for State & Local Contractors