The U.S. Army Corps of Engineers San Francisco District is seeking contractors to repair storm-damaged flood control channels in Alameda County, California, under the Zone 7 Flood Control Channels Phase 1 Project. This one-time repair project addresses erosion and bank failures at ten sites along Arroyo Mocho and Alamo Canal (sites G-6 through G-14 and F-11 through F-13) that occurred during atmospheric rivers between December 2022 and March 2023. The repair work involves excavating damaged areas, removing disturbed soil and vegetation, placing rock slope protection at the waterside slope toe, installing soil-filled rock slope protection up to the 10-year water surface elevation, and restoring slopes with compacted backfill followed by erosion control matting and hydroseeding. The contract includes a base performance covering three sites (G-06, G-10, and G-13) with an option for a fourth site (G-14), and all work must be completed within strict environmental windows. The solicitation was originally due June 30, 2025, but was extended to July 3, 2025, at 11:00 AM PST, with a public bid opening scheduled for 11:30 AM PDT the same day.

This procurement is designated as a 100% small business set-aside under NAICS code 237990 (Other Heavy and Civil Engineering Construction), with an estimated contract value between $5,000,000 and $10,000,000. The base contract has a performance period of 106 calendar days, extending to 120 days if the option is exercised, with in-water construction restricted to the period between June 15 and October 15. The project involves restoring flood control channels with earthen slopes previously constructed to 2H:1V grades and channel heights ranging from 15-30 feet. A pre-bid site visit was conducted on June 12, 2025, with multiple contractors attending including Dutra Group, SUULTAAQ, Remedial Transportation Services, Teichert Construction, Maloney-Odin Joint Venture, and Odin. The work will be performed in Alameda County, California, and is funded under Public Law 84-99, which authorizes the Corps of Engineers to repair flood control works damaged by floods or other natural disasters.

Notice text

5 versions

Update #5 · Latest ·

ABSTRACT OF BIDS

Update #4 ·

The amendment modifies the solicitation to these changes represent one of three types, either adding new information, deleting information, or revising existing information. Changes made by this amendment replace the previously issued sections of the advertisement, as referenced in the below summary of changes: 

Site visit sign in sheet.

Update #3 ·

Site Visit sign in sheet

Update #2 ·

THE ZONE 7 FLOOD CONTROL CHANNELS PHASE 1 (10 SITES) PL 84- 99 PROJECT IS AN ONE TIME REPAIR PROPOSED BY USACE TO REPAIR STORM DAMAGED TO FLOOD CONTROL CHANNELS IN ALAMEDA COUNTY. DAMAGES CONSISTED OF EROSION AND BANK FAILURES DURING A SERIES OF ATMOSPHERIC RIVERS BETWEEN DECEMBER 2022 AND MARCH 2023. REPAIRS CONSIST OF TEN (10) SITES ALONG ARROYO MOCHO AND ALAMO CANAL, INCLUDING G-6, G-7, G-8, G-9, G-10, G-13, G-14, F-11, F-12, AND F-13.THE EXISTING FLOOD CONTROL CHANNELS TYPICALLY HAVE EARTHEN SLOPES PREVIOUSLY CONSTRUCTED TO GRADES OF 2H:1V, WITH CHANNEL HEIGHTS RANGING FROM 15-30 FEET. THE DAMAGED SITES VARY IN SIZES. REPAIRS TO DAMAGED SITES WILL RESTORE THE SLOPES TO ORIGINAL GRADE PRIOR TO THE STORM DAMAGES. EARTHWORK WILL START WITH EXCAVATION OF THE DAMAGED AREA, REMOVING DISTURBED SOIL AND VEGETATION WITHIN THE AREA. REPAIRS WILL CONSIST OF PLACING ROCK SLOPE PROTECTION (RSP) AT THE WATERSIDE SLOPE TOE, PLACING SOIL-FILLED RSP UP TO THE 10-YEAR WATER SURFACE ELEVATION, AND RESTORING THE UPPER PORTION OF THE SLOPE WITH COMPACTED BACKFILL. AFTER THE REMAINING SLOPE IS BACKFILLED AND COMPACTED ABOVE THE STONE PROTECTION, EROSION CONTROL MATTING WILL BE INSTALLED AND HYDROSEEDED.

Update #1 ·

THE ZONE 7 FLOOD CONTROL CHANNELS PHASE 1 (10 SITES) PL 84- 99 PROJECT IS AN ONE TIME REPAIR PROPOSED BY USACE TO REPAIR STORM DAMAGED TO FLOOD CONTROL CHANNELS IN ALAMEDA COUNTY. DAMAGES CONSISTED OF EROSION AND BANK FAILURES DURING A SERIES OF ATMOSPHERIC RIVERS BETWEEN DECEMBER 2022 AND MARCH 2023. REPAIRS CONSIST OF TEN (10) SITES ALONG ARROYO MOCHO AND ALAMO CANAL, INCLUDING G-6, G-7, G-8, G-9, G-10, G-13, G-14, F-11, F-12, AND F-13.THE EXISTING FLOOD CONTROL CHANNELS TYPICALLY HAVE EARTHEN SLOPES PREVIOUSLY CONSTRUCTED TO GRADES OF 2H:1V, WITH CHANNEL HEIGHTS RANGING FROM 15-30 FEET. THE DAMAGED SITES VARY IN SIZES. REPAIRS TO DAMAGED SITES WILL RESTORE THE SLOPES TO ORIGINAL GRADE PRIOR TO THE STORM DAMAGES. EARTHWORK WILL START WITH EXCAVATION OF THE DAMAGED AREA, REMOVING DISTURBED SOIL AND VEGETATION WITHIN THE AREA. REPAIRS WILL CONSIST OF PLACING ROCK SLOPE PROTECTION (RSP) AT THE WATERSIDE SLOPE TOE, PLACING SOIL-FILLED RSP UP TO THE 10-YEAR WATER SURFACE ELEVATION, AND RESTORING THE UPPER PORTION OF THE SLOPE WITH COMPACTED BACKFILL. AFTER THE REMAINING SLOPE IS BACKFILLED AND COMPACTED ABOVE THE STONE PROTECTION, EROSION CONTROL MATTING WILL BE INSTALLED AND HYDROSEEDED.

Files

Notice history

Notice Type Posted
Zone 7 flood control channels phase 1 (10 sites) PL 84-99 project Award Award Notice
This notice Latest solicitation Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Canonsburg-Houston, Pennsylvania, Local Protection Project (LPP) PL84-99 Rehabilitation Canonsburg-Houston, Strabane, Washington County, Pennsylvania 15317 · NAICS 237990 ENDIST Pittsburgh Total Small Business

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity