Z2NZ--Project 578-17-027 Replace Steam Pipe South Leg at the Hines VA Hospital in Hines, IL
Closed Pre-Solicitation Posted
This opportunity was awarded. See the award notice from , or the latest solicitation from .
- Solicitation number
- 36C25223R0026
- Agency
-
Veterans Integrated Service Network 12
Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Place of performance
- Hines VA Hospital 5000 S. 5th Avenue Hines, Illinois 60141, United States
Notice details come from SAM.gov. Updated .
About this opportunity
This pre-solicitation notice from the Department of Veterans Affairs seeks information from specialized construction small businesses to replace steam pipes at the Edward Hines, Jr. VA Hospital in Hines, Illinois. The project involves replacing steam pipes between vaults and buildings to provide reliable steam and increase efficiency, with a project magnitude estimated between $10-20 million. Responses from interested parties are due by December 19, 2022 and must include company information, descriptions of two similar past projects valued between $10-20 million, bonding capacity documentation, and subcontracting plans, including any set-aside designations.
The NAICS code for this procurement is 238220, plumbing, heating and air conditioning contractors, with a small business size standard of $16.5 million. The PSC code is Z2NZ for repair or alteration of other utilities. There is no set-aside designated for this project at this time. If awarded, all work must be completed within 1,095 calendar days of the notice to proceed date by March 2026. The government will evaluate responses to determine contractor capability before selecting an acquisition method.
Notice text
THIS IS A SOURCES SOUGHT NOTICE ONLY
Solicitation: 36C25223R0026
Project: 578-17-027 Replace Steam Pipe, South Leg
Place of Performance: Edward Hines, Jr. VA Hospital (EHVAH)
5000 South 5th Avenue
Hines, IL 60141-5000
PART 1 - General Description:
The purpose of this notice is to obtain information on the interests, capabilities, and qualifications of multiple types of small business firms to determine if a set-aside is appropriate. Responses to this Sources Sought announcement will be used by the Government to make appropriate acquisition decisions. Proposals are NOT being requested or accepted at this time.
The Department of Veterans Affairs, Great Lakes Acquisition Center, requests letters of interest from the following types of specialized construction small businesses firms interested in performing construction work at the Edward Hines, Jr. VA Hospital:
Service-Disabled Veteran Owned Small Businesses (SDVOSB),
Veteran Owned Small Businesses (VOSB),
Women Owned Small Businesses (WOSB),
8(a) Businesses,
HUBZone Businesses, and
Small Businesses (SB)
Large Business
This project is classified under NAICS Code: 238220 Plumbing, Heating and Air Conditioning with a small-business size limit of $16.5 Million and PSC Z2NZ (Product Service Code Repair or Alteration of Other Utilities)
In accordance with VAAR 852.219-10(d) -
(4), in the case of a contract for specialized construction, it [the prime contractor] will NOT pay more than 85% of the amount paid by the government to it to firms that not VIP-listed SDVSOBs.
(5) Any work that a VIP-listed SDVSOB subcontractor further subcontracts will count towards the percent of subcontract amount that cannot be exceeded. For supply or construction contracts, cost of materials is excluded and not considered to be subcontracted.
Ref: https://www.va.gov/oal/docs/business/pps/deviationVaar20190718.pdf
The magnitude of construction for this work is between $10,000,000 and $20,000,000.
PART 2 - SCOPE OF WORK OVERVIEW:
The goal of this project is to replace the steam pipe between Vault 9 and Vault 7 steam tunnel intersection located in the west side of the Hines VA campus and to replace the pipe between Vault 9 and Pit 5 located on the east side of the Hines VA campus near building 37 to reliably provide steam to Buildings 217, 221,215,48, and 37.
The south steam line buried pipe west of Vault 9 ruptured in 2017, requiring an emergency steam line repair. The repair process revealed corroded pipe due to direct contact with the ground and a nonfunctional cathodic protection system, it was determined that the VA needs to replace this buried pipe. Additional investigation revealed that the entire direct buried perma-pipe system is also at risk of failure and needs to be replaced. This project is a preventative measure necessary to mitigate the risk of another failure in the piping between steam Vault 9 and the Vault 7 steam tunnel intersection as several remaining steam and condensate pipes are more than 95 years old with insulation deteriorated at multiple locations. These buried pipes supply steam to patient care buildings 217 and 221. Replacement will increase efficiency and provide energy savings.
The objectives of this project are to:
1) Replace the sump pump controls on the existing steam vaults.
2) Construct new concrete box conduit steam tunnels per drawings and specifications.
3) Construct roof top pipe rack on building 217 per drawings and specifications.
4) Construct pipe rack over the outer corridor per drawings and specifications.
5) Perform the work in a manner least likely to interfere with the daily operations of the hospital.
6.) This project shall be executed in one single, uninterrupted phase. Contractors must plan accordingly for shut-downs, coordination with active hospital operations, standard weather conditions and lead-lead material fabrications/deliveries.
PART 3 - PERIOD OF PERFORMANCE:
Complete all work including submittals, reviews, quality assurance, and closeout no later than 1,095 calendar-days from the Notice to Proceed (NTP) as shown below. This project is knowingly on a tight schedule; contractor must plan accordingly to maintain the contractual period of performance. This schedule includes submittals, submittal reviews, material lead-time, installation, standard testing, testing and balancing, owner, and AE punchlist inspections and contract corrective action, and standard closeout.
ACTIVITY
DURATION (CALENDAR DAYS)
Completion Date (Approximate)
Award
0
3/15/2023
Kick-Off Meeting/NTP
14
4/1/2023
Submittals (Schedule, QC, Safety, ICRA, Product Data, Shop Drawings, Schedule of Values, etc.)
45
5/16/2023
VA Submittal Reviews
21
6/5/2023
Mobilization
1
6/6/2023
Site Work (including mobilization, installations, shut-downs, testing, inspections, commissioning, training, punchlist/corrections and demobilization)
1005
3/7/2026
Administrative Closeout
23
3/31/2026
Â
Â
Â
TOTAL DURATION = 1095 MAX
1095
Â
*** Some Actions occur simultaneously
PART 4 - Interested sources shall submit the following:
Company name, address, point of contact, phone number, SAM OID number, and business status.
Indicate the primary nature of your business, any teaming agreements or arrangements, self- performance, and intentions of subcontracting program, including set-asides.
Documentation relating to capability of performance. Provide two (2) examples of projects similar in scope, complexity, and cost magnitude of project description above.
Letter from the surety regarding the maximum bonding capability for a single contract action as well as the total aggregate bonding capacity.
Total submittal shall be no longer than (6) six pages in one .pdf file or word document.
Responses are required to be sent via email to Kristi.Kluck3@va.gov no later than Monday, December 19 2022 CST.
THIS IS NOT A REQUEST FOR PROPOSALS. It is a market research tool being utilized to determine the availability of potential qualified contractors before determining the method of acquisition. In addition, this Sources Sought is not to be construed as a commitment by the government, nor will the government pay for any information solicited or delivered.
Files
| File | Type | Posted |
|---|---|---|
| 36C25223R0026.docx | DOCX document |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Z2NZ--578-17-027 Replace Steam Pipe South Leg at Edward Hines, Jr. VA Hospital in Hines, IL | Award Notice | |
| Z2NZ--578-17-027 Replace Steam Pipe South Leg at Hines | Solicitation | |
| Z2NZ--578-17-027 Replace Steam Pipe South Leg at Hines | Pre-Solicitation | |
| This notice | Pre-Solicitation |
Similar open opportunities
| Opportunity | Agency | Set-aside | Responses due |
|---|---|---|---|
| Z2DA--FY27 NRM 558-24-160, Domestic Water, Chilled Water and Steam Piping (VA-26-00066009) | Veterans Integrated Service Network 6 | Service-Disabled Veteran-Owned Small Business | |
| N048-- B41 Isolation Valve Installation | Veterans Integrated Service Network 16 | Service-Disabled Veteran-Owned Small Business | |
| Z1DA--550-20-121 Demo Old Boiler Plant B100 (CON) | Veterans Integrated Service Network 12 | No set-aside | |
| Z2NZ--Turn Key Chiller Equipment (Purchase and Install) | Veterans Integrated Service Network 16 | Service-Disabled Veteran-Owned Small Business | |
| J048--NEW - Energy Center Steam Header& Boilers valves, gaskets, and vent replacement | Veterans Integrated Service Network 17 | Service-Disabled Veteran-Owned Small Business |
On GovTribe
Work this opportunity
- Track it in your pipeline
- Find teaming partners
- Similar opportunities