Y1DA--Project# 614-20-109 Cooling Tower Replacement
Closed Solicitation Posted
This opportunity was awarded. See the award notice from .
- Solicitation number
- 36C24925B0010
- Agency
- Veterans Integrated Service Network 9 Veterans Health Administration, Department of Veterans Affairs
- Responses due
- Set-aside
- No set-aside
Opportunity facts
- NAICS code
- 238220 Plumbing, Heating, and Air-Conditioning Contractors
- Points of contact
-
- Michael R. Brown michael.brown1305@va.gov (615) 225-5975
Notice details come from SAM.gov. Updated .
About this opportunity
The Department of Veterans Affairs Veterans Health Administration Veterans Integrated Service Network 9 is procuring cooling tower replacement services for the Lt. Col. Luke J. Weathers, Jr. VA Medical Center in Memphis, Tennessee. The project involves replacing the main cooling tower and associated equipment, including condenser water pumps, primary and secondary chilled water pumps, fan variable frequency drives, condenser water valves, and exhaust fans, while utilizing existing concrete basins. The solicitation specifies that new cooling towers must match existing tower base dimensions and meet all design conditions, with B.A.C. as the preferred original equipment manufacturer due to size constraints in the existing area. A mandatory site visit was scheduled for July 14, 2025, and the current bid due date is August 18, 2025, at 1:00 PM CDT following a recent amendment that also removed the requirement for providing a temporary portable cooling tower during installation.
This procurement is designated as a 100% set-aside for Service-Disabled Veteran-Owned Small Businesses (SDVOSB) under NAICS code 238220 with a small business size standard of $19 million. The contract includes a 365-calendar day performance period and requires a bid guarantee of 20% of the bid price. Contractors must maintain active System for Award Management registration and be listed in the SBA certification database to be eligible for award. The project involves comprehensive infrastructure replacement work at the Memphis VA Medical Center located at 1030 Jefferson Avenue, with detailed specifications covering mechanical, electrical, and safety requirements. Wage determination requirements apply under the Davis-Bacon Act for construction work in Fayette and Shelby Counties, Tennessee, with established minimum hourly rates for various trade classifications ranging from $30.20 for carpenters to $38.17 for asbestos workers.
Notice text
2 versions
Update #2 · Latest ·
614-20-109 Cooling Tower Replacement
Update #1 ·
36C24925B0010
614-20-109 Cooling Tower Replacement
The specs document page 23 list concrete as « NOT USED . Would the government please confirm contractor is to use/leave existing walls and concrete base?
A: For clarity, it is understood the question refers to page 3 (not 23) of 398, Table of Contents, which states, DIVISION 03 CONCRETE NOT USED. Although there is no concrete work, section 099100 Painting applies to painting existing concrete. [Lee to verify Client wants interior concrete painted. Also, are ALL engineering disciplines sure we have no new concrete??? No concrete duct banks??? No equipment pads??? Electrical specs have concrete!!!]
Would the government please confirm the contractor is to use the existing basins?
A: The existing concrete cooling tower basins shall remain and will be reused for the new cooling towers.
The submittals reference stainless steel basins, does that imply new basins?
A: The cooling towers have an open bottom and discharges into the existing concrete basins. The hot water distribution basin at the top of the towers shall be constructed of stainless steel.
Is the government open to similar Towers or brand name specific?
A: The government is open to equal cooling towers. However, the cooling tower must meet all design conditions and specifically, the new cooling tower base dimensions must match the existing cooling tower as specified in the schedule on sheet MP601. New towers must be installed on the existing concrete basins.
Would the government specify preferred brand or OEM?
A: Due to size constraints in the existing area, the original equipment manufacturer, B.A.C., would be preferred, additionally it has been specifically called out as the basis of design in the Cooling Tower Schedule on sheet MP601.
Attachments
| File | Type | Posted |
|---|---|---|
| 36C24925B0010 0002.docx | DOCX document | |
| 36C24925B0010 0001.docx | DOCX document | |
| Wage Determination_TN20250200 06-06-2025.pdf | ||
| UEI _ TAX ID.docx | DOCX document | |
| C28_Specifications Cooling Tower.pdf | ||
| RFI Form.docx | DOCX document | |
| Contractor EMR Certification Form.docx | DOCX document | |
| 36C24925B0010_1.docx | DOCX document | |
| C27_Drawings Cooling Tower.pdf |
Notice history
| Notice | Type | Posted |
|---|---|---|
| Y1DA--614-20-109 Cooling Tower Replacement | Award Notice | |
| Y1DA--Project# 614-20-109 Cooling Tower Replacement | Solicitation | |
| Y1DA--Project# 614-20-109 Cooling Tower Replacement | Pre-Solicitation |
On GovTribe
Work this opportunity on GovTribe
- Track it in your pipeline
- Find teaming partners
- Similar opportunities
- Ask GovTribe AI about this opportunity